K92 MINING EXPLORATION UPDATE - BLUE LAKE PORPHYRY PROSPECT

• Initial diamond drilling program underway, with the first of six planned 400- metre

deep holes completed

• First hole KTDD0001 intersects 175 metres at 0.28 g/t Au and 0.22% Cu from 259

metres to termination at 433.9 metres, with the hole ending in mineralization

• A grid soil sampling program over an area of approximately 2 km2 identifies a large

coincident gold and copper anomaly

Vancouver, B.C. March 27, 2019 - K92 Mining Inc. (“K92” or the “ Company”) (TSXV:

KNT; OTCQB: KNTNF) is pleased to provide an update on exploration at the Blue Lake

Porphyry Prospect located approximately 4 kms southwest of the Company’s Kora deposit at the

Kainantu gold mine in Papua New Guinea (see Figure 1).

Drilling recently commenced, with the first hole, KTDD0001 intersecting a mineralized silica

cap, followed by a broad zone of intense argillic alteration (pyrophyllite/kaolinite), before

drilling strong propylitic alteration in diorite , predominantly chlorite, with epidote increasing

towards the end of the hole. Significantly, the hole intersected 175 metres @ 0.28 g/t Au and

0.22 % Cu from 259 metres to the end of the hole at 433.9 metres (see Tables 1 & 2 below). The

hole was still in mineralization when completed (see Figures 2 & 3).

The Blue Lake Project was discovered in early 2017 by the K92 exploration team following a

systematic surface mapping and sampling program over the western portion of EL470. Strongly

mineralized silicified breccias in outcrop were initially encountered by K92 in September 2017,

with samples assaying up to 20 g/t Au and 15% Cu.

Since the initial discovery, K92 geologists have mapped (lithology, alteration, structure) the

prospect area in detail at 1:1,00 0, identifying a number of mineralized intrusives and breccias.

An equidistant soil grid at 50 -metre spacing over an area of approximately 2km 2 has been

completed, with more than 1,000 samples collected, revealing a large coincident gold and copper

anomaly.

Petrology of rock chip samples taken from outcrop from widely spaced locations from Blue Lake

confirmed a high sulphidation overprint of outer potassic alteration/mineralisation, where

enargite, tennantite/tetrahedrite, sulphosalt minerals, cuba nite, chalcopyrite, bornite, sphalerite,

2

galena and possible precious metal telluride minerals occur in paragenetic association with

pyrophyllite-sericite, mosaic quartz, diaspore, kaolin clay and pyrite, defining an intermediate to

high-sulphidation style of mineralisation within tonalite porphyry. The presence of secondary

hypersaline fluid inclusion assemblages in primary quartz, ghosting of prograde metasomatic

biotite and actinolite/tremolite, and the distribution of resorbed prograde metasomatic borni te

and chalcopyrite provide evidence for hydrothermal overprinting of a protore porphyry copper

(gold) regime.

A significant conductor was identified from previously completed airborne EM geophysics

within the Blue Lake Prospect, which is coincident with strong Mo anomalism in soil

geochemistry. Integrated datasets (geology, geochemistry and geophysics) all point to a major

mineralized porphyry system at Blue Lake.

Chris Muller, K92 Vice President Exploration, states, “This first hole at Blue Lake has exceeded

our expectations, with t he mineralized silica cap, together with a long, open -ended interval of

equal ratio Au:Cu mineralized propylitic alteration assemblages suggesting proximity to a large,

fertile Au-Cu porphyry system.

This drilling result combined with the geology, geochemistry, geophysics and petrology make

Blue Lake a compelling porphyry prospect.

The Company will continue to advance the Blue Lake Prospect by c ompleting this initial 2,400 -

metre diamond program. At this point we intend to then continue with a further , larger and more

targeted drilling program based on the results and interpretations from this initial program.”

Table 1 – KTDD0001 Drilling Results

Hole_id From (m) To (m) Interval (m) Gold g/t Silver g/t Copper % Gold

equivalent

KTDD0001 5 20 15 0.63 4 0.02 0.7126

KTDD0001 259.3 433.9 174.6 0.28 2 0.22 0.6426

Table 2 – KTDD0001 – Collar Locations and Orientation

Hole_ID Easting

(AGD66)

Northing

(AGD66) mRL Bearing

(AMG)

Bearing

(Magnetic) Inclination Depth (m)

KTDD0001 371391 9316122 1639 120 115 -60 433.9

K92 Vice President Exploration, Mr. Chris Muller, PGeo, a Qualified Person under the meaning

of National Instrument 43-101 – Standards of Disclosure for Mineral Projects, has reviewed and

is responsible for the technical content of this news release. Data verification by Mr. Muller

includes significant time onsite reviewing drill core, soil and outcrop sampling, artisanal

workings, as well as d iscussing work programs and results with geology personnel and external

consultants.

3

About K92 Mining

K92 Mining is currently engaged in the production of gold, copper and silver from the

Kora/Kora North deposit from the Kainantu Gold Mine in Papua New Guinea , as well as

exploration and development of mineral deposits in the immediate vicinity of the mine. The

Company declared commercial production from Kainantu in February 2018 and announced

planned expansion of the mine in March 2019. An updated Preliminary Economic Assessment

on the property was published in January 2019.

ON BEHALF OF THE COMPANY,

John Lewins

Chief Executive Officer and Director

For further information, please contact the Company at +1-604-687-7130.

www.k92mining.com

NEITHER TSX VENTURE EXCHANGE NOR ITS REG ULATION SERVICES PRO VIDER

(AS THAT TERM IS DEF INED IN POLICIES OF THE TSX VENTURE EXCH ANGE)

ACCEPTS RESPONSIBILI TY FOR THE ADEQUACY OR ACCURACY OF THIS

RELEASE.

CAUTIONARY STATEMENT REGARDING FORWARD-LOOKING INFORMATION: This news

release includes certain “forward -looking statements” under applicable Canadian securities

legislation. Forward-looking statements are necessarily based upon a number of estima tes and

assumptions that, while considered reasonable, are subject to known and unknown risks,

uncertainties, and other factors which may cause the actual results and future events to differ

materially from those expressed or implied by such forward -looking statements. All statements

that address future plans, activities, events, or developments that the Company believes, expects,

or anticipates will or may occur are forward -looking information, including statements

regarding the realization of the prelimin ary economic analysis for the Kainantu Project,

expectations of future cash flows, the proposed plant expansion, potential expansion of resources

and the generation of further drilling results which may or may not occur. Forward -looking

statements and info rmation contained herein are based on certain factors and assumptions

regarding, among other things, the market price of the Company’s securities, metal prices,

exchange rates, taxation, the estimation, timing and amount of future exploration and

development, capital and operating costs, the availability of financing, the receipt of regulatory

approvals, environmental risks, title disputes, failure of plant, equipment or processes to operate

as anticipated, accidents, labour disputes, claims and limitations on insurance coverage and

other risks of the mining industry, changes in national and local government regulation of

mining operations, and regulations and other matters.. There can be no assurance that such

statements will prove to be accurate, as actual results and future events could differ materially

from those anticipated in such statements. Accordingly, readers should not place undue reliance

on forward-looking statements. The Company disclaims any intention or obligation to update or

revise any forw ard-looking statements, whether as a result of new information, future events or

otherwise, except as required by law.

4

Figure 1 Blue Lake Prospect Location

5

Figure 2 KTDD0001 Drill Section

6

Figure 3 KTDD0001, 424.4m. Quartz -chalcopyrite stockwork veins in chlorite -epidote

diorite; 1 metre interval assayed 0.26 g/t Au, 0.34 % Cu.