K92 Announces Record High-Grade Kora Drill Results from Kora Northern Extension
including 5.82 m at 486.78 g/t Au, 21 g/t Ag and 0.15% Cu (487.1 g/t AuEq) in hole
KMDD0084
Drill Hole KMDD0084 records multiple intersections including 5.82 m at 486.78 g/t
Au, 21 g/t Ag and 0.15% Cu (487.1 g/t Au Eq) plus 4.68 m at 73.54 g/t Au, 4 g/t Ag
and 0.33% Cu (74.1 g/t AuEq)
Drill Hole KMDD00 82 records multiple intersections including 2.75 m at 21.41 g/t
Au, 6 g/t Ag and 1.13% Cu (23.20 g/t AuEq) plus 3.78 m at 32.54 g/t Au, 62 g/t Ag
and 2.59% Cu (37.29 g/t AuEq)
K92 Mining Inc. (TSX-V: KNT; OTCQB: KNTNF) (“K92”) is pleased to announce results from
the continuing grade control drilling of the Kora North Extension.
The r esults reported are from the first two holes from the new Diamond Drill Cuddy Three
(DDC3), with both holes drilled recording intersections of the K1, KL and K2 Lodes.
Results from Hole KMDD00 84 included 5.82 m at 486.78 g/t Au, 21 g/t Ag and 0.15% Cu
(487.1 g/t Au Eq) plus 4.68 m at 73.54 g/t Au, 4 g/t Ag and 0.33% Cu (74.1 g/t AuEq) plus 4.12
m at 7.59 g/t Au, 21 g/t Ag and 1. 92% Cu ( 10.79 g/t AuEq), while Hole KMDD0082 recorded
2.75 m 21.41 g/t Au, 6 g/t Ag and 1.13% Cu (23.20 g/t AuEq) plus 3.78 m at 32.54 g/t Au, 62 g/t
Ag and 2.59% Cu (37.29 g/t AuEq) plus 3.31 m at 8.37 g/t Au, 2 g/t Ag and 0.39% Cu (8.99 g/t
AuEq).
The results from DDC 3 are now the furthest drilled to the south and continue to confirm the
consistency of both the K1 and K2 lodes within this area wh ile also further delineating the KL
structure and confirming its continuity. A plan showing the Kora North development, location of
the three diamond drill cuddies and of the latest grade control drill holes is provided below.
John Lewins, K92 Chief Execu tive Officer and Director, states, “The first hole drilled from the
new drill cuddy DDC3, KMDD0082 was possibly our best hole to date however this has been
totally eclipsed by the results from the second hole, KMDD0084 which included a section of 0.72
metres assaying at over 3,500 g/t Au. These two holes are the furthest south that we have drilled
and appear to indicate a general increase in both copper and gold grades as we move further
south. Importantly from the perspective of building our confidence in the continuity of the Kora –
Irumafimpa system, hole KMDD0084 is just over 200 metres along strike from the deepest hole
drilled by Barrick from surface, BKDD0023. This hole reported over 30 metres of continuous
mineralization from 920 metres down hole and finished in mineralization as the hole could not
be drilled any deeper.
We have already completed the drilling of the next grade control hole from DDC3, which is a
further 25 metres to the south, and await the assay results with great anticipation”.
Table 1 below provides a summary of the results from the latest diamond grade control drill
holes drilled into the Kora North Vein system from DDC 3. Table 2 provides details of collar
location and hole orientation.
Table 1.0 Kainantu Gold Mine – Significant Intercepts from Kora Diamond Drill Cuddy 2
Hole_id From
(m) To (m) Interval
(m)
True
width
(m)
Gold
g/t
Silver
g/t
Copper
%
Gold
equivalent Comment
KMDD0082 35.55 38.30 2.75 2.67 21.41 6 1.13 23.20 K1E
including 35.55 36.26 0.71 0.69 56.70 14 3.44 62.15
including 36.26 36.59 0.33 0.32 1.07 4 1.04 2.71
including 36.59 37.24 0.65 0.63 0.57 3 0.32 1.09
including 37.24 37.50 0.26 0.25 30.45 6 0.16 30.78
including 37.50 38.10 0.60 0.58 9.50 2 0.03 9.57
including 38.10 38.30 0.20 0.19 21.34 1 0.19 21.65
KMDD0082 38.45 40.48 2.03 1.97 3.74 1 0.02 3.78 K1W
including 38.45 39.58 1.13 1.10 3.01 1 0.01 3.04
including 39.58 39.78 0.20 0.19 6.64 1 0.02 6.69
including 39.78 40.38 0.60 0.58 4.23 1 0.02 4.28
including 40.38 40.48 0.10 0.10 3.18 1 0.04 3.26
KMDD0082 46.09 49.40 3.31 2.62 8.37 2 0.39 8.99 KL1
including 46.09 47.80 1.71 1.35 0.52 3 0.60 1.48
including 47.80 48.14 0.34 0.27 1.50 1 0.06 1.60
including 48.14 49.40 1.26 1.00 20.88 2 0.19 21.19
KMDD0082 64.88 68.66 3.78 3.59 32.54 62 2.59 37.29 K2
including 64.88 65.30 0.42 0.40 4.35 15 0.55 5.38
including 65.30 66.37 1.07 1.02 1.52 25 0.83 3.12
including 66.37 66.93 0.56 0.53 209.70 338 14.92 236.93
including 66.93 68.66 1.73 1.64 1.22 7 0.18 1.59
KMDD0084 38.5 43.18 4.68 4.14 73.54 4 0.33 74.10 K1W
including 38.5 39.57 1.07 0.95 96.96 10 0.83 98.35
including 39.57 40.8 1.23 1.09 0.87 2 0.22 1.23
including 40.8 41.15 0.35 0.31 18.84 3 0.32 19.36
including 41.15 41.8 0.65 0.57 8.96 2 0.22 9.32
including 41.8 42.31 0.51 0.45 36.88 1 0.02 36.93
including 42.31 42.64 0.33 0.29 623.77 6 0.13 624.05
including 42.64 43.18 0.54 0.48 4.24 3 0.15 4.50
KMDD0084 48.3 54.12 5.82 5.46 486.78 6 0.16 487.10 KL1
including 49.61 49.85 0.24 0.23 2.52 5 0.07 2.70
including 49.85 50.61 0.76 0.71 3585.93 21 0.15 3586.43
including 50.61 50.93 0.32 0.30 3.31 2 0.00 3.34
including 50.93 51.28 0.35 0.33 11.39 11 0.32 12.02
including 51.28 52.2 0.92 0.86 0.88 1 0.12 1.07
including 52.2 52.48 0.28 0.26 3.56 4 1.14 5.35
including 52.48 52.78 0.3 0.28 273.33 6 0.19 273.69
including 52.78 53.2 0.42 0.39 2.88 1 0.05 2.97
including 53.2 53.66 0.46 0.43 25.15 6 0.15 25.46
including 53.66 54.12 0.46 0.43 8.36 1 0.11 8.54
KMDD0084 62 66.12 4.12 4.00 7.59 21 1.92 10.79 K2
including 62 62.6 0.6 0.58 2.59 2 0.16 2.85
including 62.6 63 0.4 0.39 0.16 1 0.06 0.26
including 63 63.56 0.56 0.54 16.83 19 2.42 20.77
including 63.56 64.21 0.65 0.63 19.98 14 1.20 21.99
including 64.21 65.1 0.89 0.86 7.22 51 5.19 15.80
including 65.1 66.12 1.02 0.99 0.79 19 1.03 2.60
Notes
Gold Equivalent uses Copper price – US$2.90/lb; Silver price US$16.5/oz and Gold price of US$1300/oz
Table 2.0 Kainantu Gold Mine – Collar Locations for Kora Underground Diamond
Drilling
Hole_id Collar location Collar orientation EOH
depth (m) Lode
Local
north
Local
East mRL Dip Local
azimuth
KMDD0082 58903.06 29868.16 1191.07 18.57 291.0 89.9 Kora
KMDD0084 58901.94 29868.29 1190.97 17.86 265.6 101.1 Kora
The current Kora/Eutompi inferred resource, as defined by previous drilling to date, is 4.36
million tonnes at a grade of 7.3 g/t Au, 35 g/t Ag and 2.23 per cent Cu, or 11.2 g/t gold
equivalent (see attached table) and is open for expansion at depth and in both directions along
strike.
K92 has filed and made available for download on the company's SEDAR profile a technical
report titled "Independent Technical Report, Mineral Resource Update and Preliminary
Economic Assessment of Irumafimpa and Kora Gold Deposits, Kainantu Project, Papua New
Guinea," with an effective date of March 2, 2017, that provides additional information on the
geology of the deposits, drilling and sampling procedures, lab analysis, and quality
assurance/quality control for the project, and additional details on the resource estimates.
The PEA estimates for Kora, based on the current resource estimates (4.36 million t onnes of 7.3
g/t Au, 35 g/t Ag and 2.23 per cent Cu):
Over a nine-year operating life, the plant would treat 3.2 million tonnes averaging 7.1 g/t
Au, 25 g/t Ag and 1.7 per cent Cu (9.3 g/t AuEq (1));
This would generate an estimated positive cash flow of $ 537-million (U.S.) using current
metal prices if 15 -metre levels are used in mining; if 25 -metre levels are used, then net
cash flows are estimated as $558 -million (U.S.); this cash flow includes conceptual
allowances for capital;
Production of an estimate d average of 108,000 AuEq (1) ounces per annum over an
eight-year period from year 2 through to year 9;
An estimated pretax net present value (NPV) of $415 -million (U.S.) for 25 -metre levels,
or $397-million (U.S.) for 15-metre levels, using current metal prices, exchange rates and
a 5-per-cent discount;
An estimated after -tax NPV of $329 -million (U.S.) for 25 -metre levels, or $316 -million
(U.S.) for 15 -metre levels, using current metal prices, exchange rates and a 5 -per-cent
discount;
Initial capital cost is estimated to be $13.8 -million (U.S.), including the $3.3 -million
(U.S.) for the plant upgrade identified in the Mincore scoping study, but excluding the
proposed Kora exploration inclines and diamond drilling; sustaining capital cost is
estimated to a f urther $64-million (U.S.) spent over the life of the Kora mining for 25 -
metre levels, or $83-million (U.S.) for 15-metre levels;
Operating cost per tonne is estimated to be $125 (U.S.) per tonne for 25 -metre levels, or
$126 (U.S.) per tonne for 15-metre mining levels;
Excluding initial capital expenditure of $14 -million (U.S.), cash cost is estimated to be
$547 (U.S.) per ounce AuEq (inclusive of a 2.5 -per-cent net smelter return (NSR)
royalty) and all -in sustaining cost (AISC) of $619 (U.S.) per ounce AuEq for 25-metre
mining levels, or $549 (U.S.) per ounce (inclusive of a 2.5 -per-cent NSR royalty) and
AISC of $644 (U.S.) per ounce AuEq for 15-metre mining levels.
Metal prices used were $1,300 per ounce for gold, $18 (U.S.) per ounce for silver and $4,800 per
tonne for copper.
(1) Gold equivalent calculated on above metal prices.
Kora remains open for expansion in every direction and strongly mineralized at the extent of all
drilling.
The PEA is preliminary in nature and includes inferred mineral resources that are considered too
speculative geologically to have the economic considerations applied to them that would enable
them to be categorized as mineral reserves, and there is no certainty that the PEA will be
realized. The technical report contains a full description of all underlying assumptions relating to
the PEA. Mineral resources that are not mineral reserves and do not have demonstrated
economic viability.
Table 3.0 IRUMAFIMPA AND KORA/EUTOMPI RESOURCES
Resource by Deposit and Category
Deposit Resource
Category
Tonnes Gold Silver Copper Gold
Equivalent
Mt g/t MOz g/t MOz % Mlb g/t MOz
Irumafimpa Indicated 0.56 12.8 0.23 9 0.16 0.28 37 13.4 0.24
Inferred 0.53 10.9 0.19 9 0.16 0.27 74 11.5 0.20
Kora/Eutompi Inferred 4.36 7.3 1.02 35 4.9 2.23 215 11.2 1.57
Total Indicated 0.56 12.8 0.23 9 0.16 0.3 4 13.4 0.24
Total Inferred 4.89 7.7 1.21 32 5.06 2.0 218 11.2 1.76
M in Table is millions. Reported tonnage and grade figures are rounded from raw estimates to
reflect the order of accuracy of the estimate. Minor variations may occur during the addition of
rounded numbers. Gold equivalents are calculated as AuEq = Au g/t + Cu%*1.52+ Ag
g/t*0.0141.
K92 Mine Geology Manager and Mine Exploration Manager, Mr. Andrew Kohler , PGeo, a
qualified person under the meaning of Canadian National Instrument 43-101, has reviewed and is
responsible for the technical content of this news release. Data verification by Mr. Kohler
includes significant time onsite reviewing drill core, face sampling, underground workings and
discussing work programs and results with geology and mining personnel.
On Behalf of the Company,
John Lewins, Chief Executive Officer and Director
Neither TSX Venture Exchange nor its Regulation Services Provider (as that term is defined in
policies of the TSX Venture Exchange) accepts responsibility for the adequacy or accuracy of
this release.
CAUTIONARY STATEMENT REGARDING FORWARD-LOOKING INFORMATION: This news
release includes certain “forward -looking statements” under applicable Canadian securities
legislation. Forward-looking statements are necessarily based upon a number of estimates and
assumptions that, while considered reasonable, are subje ct to known and unknown risks,
uncertainties, and other factors which may cause the actual results and future events to differ
materially from those expressed or implied by such forward -looking statements. All statements
that address future plans, activiti es, events, or developments that the Company believes, expects
or anticipates will or may occur are forward -looking information, including statements
regarding the realization of the preliminary economic analysis for the Project, expectations of
future cas h flows, the proposed plant expansion, potential expansion of resources and the
generation of further drilling results which may or may not occur. Forward -looking statements
and information contained herein are based on certain factors and assumptions rega rding,
among other things, the market price of the Company’s securities, metal prices, exchange rates,
taxation, the estimation, timing and amount of future exploration and development, capital and
operating costs, the availability of financing, the receip t of regulatory approvals, environmental
risks, title disputes, failure of plant, equipment or processes to operate as anticipated, accidents,
labour disputes, claims and limitations on insurance coverage and other risks of the mining
industry, changes in national and local government regulation of mining operations, and
regulations and other matters.. There can be no assurance that such statements will prove to be
accurate, as actual results and future events could differ materially from those anticipated in
such statements. Accordingly, readers should not place undue reliance on forward -looking
statements. The Company disclaims any intention or obligation to update or revise any forward -
looking statements, whether as a result of new information, future eve nts or otherwise, except as
required by law.
Kora North Plan
DDC3 DDC2
DDC1
KMDD0082 KMDD0084
100 metres