Kutcho Copper Reports Updated Mineral Resources of 18.6 MT of Measured & Indicated at 2.58% CuEq1 and 13.2 MT of Inferred at 1.59% CuEq1; Outlines Near Resource Expansion Drill Targets

Exploration Programs

Kutcho Copper Corp. | 717 – 1030 West Georgia Street | Vancouver, British Columbia | Canada | V6E 2Y3

Telephone: (604) 628-5623 | www.kutcho.ca

Kutcho Copper Reports Updated Mineral Resources of 18.6 MT of Measured & Indicated

at 2.58% CuEq1 and 13.2 MT of Inferred at 1.59% CuEq1; Outlines Near Resource

Expansion Drill Targets

Vancouver, B.C., February 11, 2021. Kutcho Copper Corp. (TSXV: KC, OTC: KCCFF) (“Kutcho

Copper” or the “Company”) is pleased to provide an updated mineral resource estimate that is currently

being utilized in its Feasibility Study on its 100% owned Kutcho high grade copper-zinc project located in

British Columbia (“Kutcho Project”). The mineral resource estimate was prepared under the direction of

Robert Sim, P.Geo, of SIM Geological Inc. (SGI).

“We are pleased to announce an updated mineral resource estimate for the Kutcho Project that incorporates

the substantial work completed over the past few years, and most notably since the previous resource

estimate, incorporating the improved metallurgical recoveries achieved in 2020. The updated estimate of

mineral resources includes an 8% increase in Measured and Indicated tonnes and a 24% increase in Inferred

tonnes compared to the 2019 resource estimate (see Company’s press release dated March 4, 2019) . This

updated mineral resource is currently being used as the foundation for the Feasibility Study, which remains

on track to be completed this June . In addition, there remains significant exploration potential between,

below and along strike from the existing mineral resources, providing further upside opportunities to grow

the size of the project.,” stated Vince Sorace, President & CEO of Kutcho Copper.

Kutcho Project - Estimate of Mineral Resources

Class Tonnes

(000)

CuEq1

(%)

Cu

(%)

Zn

(%)

Au

(g/t)

Ag

(g/t)

Pb

(%)

Main Deposit

Measured 6,091 2.57 1.87 2.69 0.47 28.2 0.04

Indicated 9,889 2.10 1.55 2.01 0.39 28.1 0.06

Measured +

Indicated 15,980 2.28 1.67 2.27 0.42 28.1 0.05

Inferred 2,385 1.78 1.19 1.91 0.48 27.5 0.06

Esso Deposit

Indicated 2,604 4.42 2.40 4.48 0.78 61.4 0.07

Inferred 1,640 2.13 1.31 1.58 0.41 35.6 0.01

Sumac Deposit

Inferred 9,219 1.44 1.05 1.52 0.16 16.1 0.03

Combined

Measured 6,091 2.57 1.87 2.69 0.47 28.2 0.04

Indicated 12,493 2.58 1.73 2.52 0.47 35.1 0.06

Kutcho Copper Corp.

-2-

Measured +

Indicated 18,584 2.58 1.78 2.58 0.47 32.8 0.05

Inferred 13,244 1.59 1.11 1.60 0.25 20.6 0.03

1. The estimates in the table form coherent bodies that are considered amenable to underground extraction methods

based on the following parameters: Metal Prices: Copper US $3.25/lb, Zinc US $1.25/lb, Gold US $1550/oz, Silver

US $20.00/oz. Projected operating costs: Mining US $33.75/t, Processing US $17.91/t, G&A US $10.13/t. Process

recoveries Main and Sumac: Copper 87.4%, Zinc 63.8%, Gold 36.9%, Silver 59.0%. Process recoveries Esso:

Copper 94.5%, Zinc 89.3%, Gold 40.8%, Silver 71.2%.

2. The base case cut-off grade is 1.0% CuEq for the Main and Sumac deposits based on the formula: CuEq = (Cu% x

0.874) + (Zn% x 0.245) + (Au g/t x 0.257) + (Ag g/t x 0.0053). The base case cut -off grade for Esso is 0.9%CuEq

based on the formula: CuEq = (Cu% x 0.945) + (Zn% x 0.343) + (Au g/t x 0.284) + (Ag g/t x 0.0064).

3. The effective date of the estimate of mineral resources is September 8, 2020.

4. Mineral resources do not have demonstrated economic viability.

5. The estimate of mineral resources was calculated based on the Canadian I nstitute of Mining, Metallurgy and

Petroleum (“CIM”), CIM Standards on Mineral Resources and Reserves, Definitions and Guidelines prepared by the

CIM Standing Committee on Reserve Definitions.

6. It is reasonably expected that the majority of Inferred mineral resources could be upgraded to Indicated, or Measured,

mineral resources with continued exploration.

7. Kutcho Copper is not aware of any legal, political, environmental, or other risks that could materially affect the

potential development of the mineral resources.

High Priority Near Resource Targets

Figure 1: Isometric View Looking Southwest showing the distribution of drilling and mineral resources by category.

Four priority targets exist on the Kutcho project that are located between, below or along s trike from

existing mineral resources (Figure 1). These targets represent high probability drill areas that could result

in significant accretive value to the Kutcho project;

Kutcho Copper Corp.

-3-

1. The Main-Sumac Gap identifies a 400 m by 380m panel between the Main and Sumac lenses that

is untested by drilling. A conductive geophysical anomaly coincides with the area and is 360 m

long. K003, the most eastern hole to intersect the Sumac lens and located on the western margin of

the gap returned 5.12 m of 1.29% Cu, 0.49% Zn and 7 g/t Ag confirming the potential of this panel.

2. Open Down Dip: Significant portions of all three lenses remain open down dip outside of current

resources including over 36% of the strike length of the Main deposit, 50% of Esso and 100% of

Sumac.

3. The Esso-West Expansion target lies 300 m west of the high-grade Esso deposit where just 150m

of a 1 ,500m long geophysical anomaly has been drill tested. That d rilling returned several

mineralized intercepts including 7.2 m of 2.0% Cu, 5.2% Zn and ~17 g/t Ag in hole E094B3. There

remains 300 m of untested Kutcho horizon between hole E094B3 and Esso, along with an

additional 1000 m of untested horizon to the west of hole E094B3. (off the western edge of the

attached map)

4. Footwall Zone ( FWZ) lies stratigraphically beneath the Main zone and represents a stacked

massive sulphide horizon that is open in all directions. The last drill hole to the east and down dip

intersected 1.5 m of 3.54% Cu, 6.94% Zn, 316.9 g/t Ag and 1.47 g/t Au in hole E057.

Mineral Resource Estimation Methodology

The mineral resources are estimated in conformity with generally accepted CIM Estimation of Mineral

Resources and Mineral Reserves Best Practices Guidelines (November 29, 2019) and are reported in

accordance with NI 43 -101. Drill core samples used to estimate mineral resources were collected in

accordance with industry standards and were submitted to the ALS sample preparation laboratory i n

Whitehorse, Yukon Territory, Canada, and then transferred to ALS' laboratory in Vancouver, British

Columbia, Canada for fire assay and ICP analysis. The precision and accuracy of the assays were monitored

through the systematic inclusion of standards, bl anks and check assays. Mineral resource estimates are

generated using a total of 362 drill holes at the Main deposit, 118 drill holes at the Esso deposit, and 29 drill

holes in the vicinity of the Sumac deposit. Drill holes are collared from surface and ex tend to depths of

700m below surface in some areas. Mineral resource estimates are derived from three -dimensional block

models with nominal block sizes measuring 5 x 2.5 x 5m (LxWxH). Resource estimates are generated

using drill hole sample assay results and the interpretation of geological models which relate to the spatial

distribution of copper, zinc, gold and silver in the deposits. Interpolation characteristics are defined based

on the geology, drill hole spacing, and geostatistical analysis of the da ta. The effects of potentially

anomalous high-grade sample data, composited to 1 metre intervals, are controlled using both traditional

top-cutting as well as limiting the distance of influence during block grade interpolation. Block grades are

estimated using ordinary kriging and have been validated using a combination of visual and statistical

methods to ensure they are appropriate representations of the underlying sample data. Resources in the

Measured category are delineated with drill holes on a regula r 25m pattern. Resources in the Indicated

category are delineated with holes on a nominal 50m pattern and resources in the Inferred category occur

within a maximum distance of 100m from a drill hole. The deposits form consistent zones of mineralization,

above the base case cut -off grades, that are considered to exhibit reasonable prospects for eventual

economic extraction using underground extraction methods.

Qualified Person

Robert Sim, P.Geo., a Qualified Person as defined by NI 43-101, is responsible for the estimate of mineral

resources presented in this news release and has reviewed, verified and approved the contents of this news

release as they relate to the mineral resource estimate, including the sampling, analytical, and test data

Kutcho Copper Corp.

-4-

underlying the mineral resource estimate. Mr. Sim is independent from Kutcho Copper and confirms there

were no limitations from the company in verifying the drilling and sample data with site visit observations

and monitoring of the QAQC program. Kutcho's additional disclosure of a technical or scientific nature in

this press release has been reviewed and approved by Mr. Rory Kutluoglu , B.Sc, P.Geo., Kutcho's

Exploration Manager, who serves as a Qualified Person under the definition of National Instrument 43-101.

About Kutcho Copper Corp.

Kutcho Copper Corp. is a Canadian resource development company focused on expanding and developing

the Kutcho high grade copper-zinc project in northern British Columbia. Committed to social responsibility

and the highest environmental standards, the Company intends to progress the Kutcho Project through

feasibility and permitting to a positive construction decision.

Vince Sorace

President & CEO, Kutcho Copper Corp.

For further information regarding Kutcho Copper Corp, please email [email protected] or visit our website

at www.kutcho.ca.

Cautionary Note Regarding Forward-Looking Statements

Neither the TSX Venture Exchange nor its Regulation Services Provider (as that term is defined in the policies of the

TSX Venture Exchange) accepts responsibility for the adequacy or accuracy of this release .

This news release contains certain statements that may be deemed “forward -looking statements” with respect to the

Company within the meaning of applicable secur ities laws. Forward-looking statements are statements that are not

historical facts and are generally, but not always, identified by the words “expects”, “plans”, “anticipates”,

“believes”, “intends”, “estimates”, “projects”, “potential” , “indicates”, “opp ortunity”, “possible” and similar

expressions, or that events or conditions “will”, “would”, “may”, “could” or “should” occur. Although Kutcho

Copper believes the expectations expressed in such forward-looking statements are based on reasonable assumptions,

such statements are not guarantees of future performance, are subject to risks and uncertainties, and actual results

or realities may differ materially from those in the forward-looking statements. Such material risks and uncertainties

include, but are not limited to, the Company’s ability to raise sufficient capital to fund its obligations under its property

agreements going forward, to maintain its mineral tenures and concessions in good standing, to explore and develop

the Kutcho project or its other projects, to repay its debt and for general working capital purposes; changes in

economic conditions or financial markets; the inherent hazards associates with mineral exploration and mining

operations, future prices of copper and oth er metals, changes in general economic conditions, accuracy of mineral

resource and reserve estimates, the potential for new discoveries, the potential to convert inferred resources to

indicated or measured resources, the potential to optimize the mine pla n, the ability of the Company to obtain the

necessary permits and consents required to explore, drill and develop the Kutcho project and if obtained, to obtain

such permits and consents in a timely fashion relative to the Company’s plans and business objectives for the projects;

the general ability of the Company to monetize its mineral resources; and changes in environmental and other laws

or regulations that could have an impact on the Company’s operations, compliance with environmental laws and

regulations, aboriginal title claims and rights to consultation and accommodation, dependence on key management

personnel and general competition in the mining industry. Forward -looking statements are based on the reasonable

beliefs, estimates and opinions of the Company’s management on the date the statements are made. Except as required

by law, the Company undertakes no obligation to update these forward -looking statements in the event that

management’s beliefs, estimates or opinions, or other factors, should chan ge.

Statements concerning mineral resource and mineral reserve estimates may also be deemed to constitute Forward -

Looking Statements to the extent that they involve estimates of the mineralization that may be encountered if the

Kutcho Project is developed.