Kutcho Copper Provides Corporate Update

Mergers & Acquisitions

Kutcho Copper Corp. | 717 – 1030 West Georgia Street | Vancouver, British Columbia | Canada | V6E 2Y3

Telephone: (604) 628-5623 | www.kutcho.ca

Kutcho Copper Provides Corporate Update

Vancouver, B.C., February 5, 2 020. Kutcho Copper Corp. (TSXV: KC) (OTC: KCCFF ) (“Kutcho

Copper” or the “Company”) owns the Kutcho high grade Copper – Zinc development project located in

north-western British Columbia. The Company completed a Pre-Feasibility study (“PFS”) dated July 31,

2017 that demonstrated positive economics with an after tax NPV of $265 million and an IRR of 27.6%.

The Company completed the acquisition of the project in December 2017 with the suppor t of Wheaton

Precious Metals, involving a staged financing package of over $100 million. The Kutcho project benefits

from existing ground access, a camp and airstrip on site and highway access to the nearby port at Stewart

to ship its concentrates from.

“2019 was an important year for the Company, with several important milestones completed that advanced

the Project towards completion of a Feasibility Study and embark on the Environmental Assessment

Process. In addition, with the signing of the phase on e US-China trade deal, market sentiment shifted

towards a bullish outlook for copper in 2020 and beyond” stated Vince Sorace, President & CEO of Kutcho

Copper. “Kutcho is a high margin, low capital project with lots of upside potential and our objective in

2020 will be to continue to de-risk and advance the project towards a production decision.”

Significant milestones achieved in 2019 include:

1) Completing an updated mineral resource estimate for the Main, Esso and Sumac deposits resulting

in 17.26 Mt of measured & indicated mineral resources at 2.61% CuEq1 and 10.71MT of Inferred

resources at 1.67% CuEq 1. S ignificant exploration potential remains between, below and along

strike from the existing mineral resources, providing further upside opportunities to grow the size

of the project. The updated mineral resource incorporates the significant work and new drilling

conducted by Kutcho Copper during its first year of ownership of the Project, including a

substantial 84% increase in inferred mineral resources compared to the 2017 resource estimate. See

news release dated March 4 th, 2019 and our website at www.kutcho.ca or SEDAR at

www.sedar.com for the 2017 NI 43 -101 Technical Report for previous mineral resource estimate

details.

2) Improved metallurgical results including 92.3% copper recoveries and 84.2% zinc recoveries from

a sample of the Main deposit and 94.5% copper recoveries and 89.3% zinc recoveries from a sample

from the Esso deposit. The recoveries of copper and zinc to their respective concentrates have

improved significantly over the 2017 prefeasibility study life of mine results, including improved

zinc concentrate grades and the rejection of zinc from the copper concentrate, to generate a cleaner,

higher value copper concentrate. Silver recovery was also significantly improved. See news

releases dates September 11th and November 21st, 2019.

3) Undertook extensive quantitative mineralogical analyses by QEMSCAN building a ge o-

metallurgical model of the Main and Esso deposits. This resulted in a comprehensive understanding

of the distribution of copper and zinc bearing minerals, along with other important minerals that

has and should continue to help improve the metallurgical performance at the Kutcho project.

4) Initiated various trade-off studies centered on mining methods, mining costs, tailings management

facility design and location, preliminary geotechnical parameters and stope sizing. These studies

are ongoing and will be the foundation for completion of the upcoming Feasibility Study.

Kutcho Copper Corp.

-2-

5) Submission and acceptance of the final Project Description to the British Columbia Environmental

Assessment Office (BCEAO) and reception of a Section 11 Order that defines the scope of the

Environmental Assessment and the Indigenous Nations that Kutcho and British Columbia will

engage with through the process. With the passing of Bill C-69 (Canadian Impact Assessment Act)

and associated threshold regulations, the Kutcho Project is not required to undertake a federal

environmental assessment.

6) Joined the BC Regional Mining Alliance (“BCRMA”), a consortium of Aboriginal groups, industry

peers, the BC Government, and AME BC. The Alliance was formed to promote and raise awareness

of British Columbia, Canada as a world-class mining jurisdiction.

7) Signed and maintain exploration agreements with both Tahltan and Kaska (Dena) Nations as well

as working collaboratively as the project progresses through the Environmental Assessment

Process.

8) Completed comprehensive baseline data collection for meteorological, groundwater, and surface

water (quantities and quality) that will continue in 2020.

Kutcho Project Mineral Resources Estimate

Class Tonnes

(000) CuEq (%) Cu (%) Zn (%) Au (g/t) Ag (g/t)

Main Deposit

Measured 5,831 2.66 1.92 2.78 0.48 28.7

Indicated 9,003 2.20 1.62 2.13 0.40 29.2

Measured +

Indicated 14,834 2.38 1.74 2.38 0.43 29.0

Inferred 1,902 1.98 1.31 2.16 0.48 29.7

Esso Deposit

Indicated 2,425 3.98 2.52 4.76 0.81 64.0

Inferred 1,025 2.30 1.60 2.23 0.52 41.4

Sumac Deposit

Inferred 7,779 1.52 1.10 1.60 0.17 16.9

Combined

Measured 5,831 2.66 1.92 2.78 0.48 28.7

Indicated 11,428 2.58 1.81 2.68 0.49 36.5

Measured +

Indicated 17,259 2.61 1.85 2.72 0.49 33.9

Inferred 10,706 1.67 1.18 1.76 0.26 21.5

1. The estimates in the table are considered to be amenable to underground extraction methods. The base case cut -off grade is

1.2% CuEq based on the formula CuEq = (Cu% x 0.825) + (Zn% x 0.302) + (Ag g/t x 0.004) + (Au g/t x 0.262). Mineral resources

are not mineral reserves because the economic viability has not been demonstrated.

2. Estimate assumes Mining (underground) US $34.00/t, Processing US $18.00/t, US G&A $10/t, copper price US $3.00/lb, zinc price

US $1.25/t, gold price US $1350/oz, silver price US $17.00/oz, copper payable recovery 82.5%, zinc payable recovery 72.5%,

silver payable recovery 45%, gold payable recovery 40%

3. Effective date of resource estimate February 22nd, 2019

4. Inferred mineral resources are considered too speculative geologically to have economic considerations applied to them that would

enable them to be categorized as mineral reserves. There is also no certainty that these inferred mineral resources will be converted

to the measured and indicated categories through further drilling, or into mineral reserves, once economic considerations are applied.

It is reasonably expected that the majority of inferred mineral resources could be upgraded to indicated or measured mineral

resources with continued exploration.

5. Assumptions used to derive the cut -off grades in order to meet the NI43 -101 requirement for mineral resource estimates to

demonstrate “reasonable prospects for eventual economic extraction”. The cut -off grades to be used in the upcoming feasibility

Kutcho Copper Corp.

-3-

study may vary from those used to limit the mineral resources reported herein, as the inputs to tha t study are determined. No

inference is implied in the changes to the assumptions used in the cut-off grade calculations from the prior mineral resource estimates

as to what will be used in the upcoming feasibility, as those assumptions remain to be determined.

Exploration Opportunities

The Kutcho project covers 90% of the prospective Kutcho formation rocks east of Dease Lake, B.C. These

prospective volcanic rocks are folded, repeating the mineralized horizon threefold on the project, including

the area hosting the known deposits. Most of the drilling on the project has been focused in and around the

three known deposits. However, significant exploration upside has been identified through a review of

historic work, including several priority drill ready targets prospective for the discovery and definition of

additional mineral resources. These prospective targets include:

 The Corefarm Creek target (1) represents a geophysical anomaly extending 1500 m westward from

the Esso deposit. Approximately 150 m of this anomaly has been drill tested, returning several

mineralized intercepts including 7.2 m of 2.0% Cu, 5.2% Zn and ~17 g/t Ag in hole E094B3. There

remains 300 m of untested Kutcho horizon between hole E094B3 and Esso, along with a n

additional 1,000 m of untested horizon to the west of hole E094B3 (Estimated true thickness of

6.12m).

 The Main-Sumac Gap (2) is a 400 m gap between the adjacent Main and Sumac deposits that is

untested by drilling. A conductive geophysical anomaly coincides with the area and is 360 m long.

K003, the most eastern hole to intersect the Sumac deposit and located on the western margin of

the gap returned 5.12 m of 1.29% Cu, 0.49% Zn and 7 g/t Ag (Estimated true thickness of 4.32m).

 The FWZ (4) target lies beneath the Main zone . The FWZ is open to the east, where drilling

currently ends with a 1.5 m intercept of 3.54% Cu, 6.94% Zn, 316.9 g/t Ag and 1.47 g/t Au in hole

E057 and is also open at depth.

Kutcho Copper Corp.

-4-

Management Changes

Michael Rapsch (VP Corporate Communications) has resigned as an officer of the company. We would

like to thank Michael for his time and contribution towards the current and future success of the Company.

Qualified Persons

Robert Sim, P.Geo. Consultant to the Company and a Qualified Person as defined by National Instrument

43-101 ("NI 43-101") has reviewed and approved the contents of this news release related to the mineral

resource estimate. All samples were collected in accordance with in dustry standards. Splits from the drill

core samples were submitted to the ALS sample preparation laboratory in Whitehorse, Yukon Territory,

Canada, and then transferred to ALS' laboratory in Vancouver, British Columbia, Canada for fire assay and

ICP analysis. Accuracy of results is tested through the systematic inclusion of standards, blanks and check

assays. The mineral resource estimate referenced in this press release was prepared in November 2018 by

Robert Sim, P.Geo., an independent Qualified Person as defined by NI 43-101.

Tom Shouldice, Chief Executive Officer of Base Metallurgical Laboratories is a professional metallurgical

engineer with over 20 years of experience in mineral processing. His relevant experience includes plant

operations, project management, engineering and all aspects of metallurgical testing. Tom specializes in

flotation and mineralogical interpretation in relation to metallurgica l response. Mr. Shouldice is a

“Qualified Person” as defined in National Instrument 43-101 “Standards of Disclosure for Mineral Projects”

of the Canadian Securities Administrators and has reviewed and approved metallurgical data presented in

this news release.

Kutcho's additional disclosure of a technical or scientific nature in this press release has been reviewed and

approved by Mr. Rory Kutluoglu, B.Sc, P.Geo., who serves as a Qualified Person under the definition of

National Instrument 43-101.

About Kutcho Copper Corp.

Kutcho Copper Corp. is a Canadian resource development company focused on expanding and developing

the Kutcho high grade copper-zinc project in northern British Columbia. Committed to social responsibility

and the highest environmental standards, the Company intends to advance the Kutcho Project through

feasibility and permitting to a positive construction decision.

Vince Sorace

President & CEO, Kutcho Copper Corp.

For further information regarding Kutcho Copper Corp., please email [email protected] or visit our website

at www.kutcho.ca.

Cautionary Note Regarding Forward-Looking Statements

Neither the TSX Venture Exchange nor its Regulation Services Provider (as that term is defined in the policies of the

TSX Venture Exchange) accepts responsibility for the adequacy or accuracy of this release.

This news release contains certain statements that may be deemed “forward -looking statements” with respect to the

Company within the meaning of applicable securitie s laws. Forward-looking statements are statements that are not

historical facts and are generally, but not always, identified by the words “expects”, “plans”, “anticipates”,

“believes”, “intends”, “estimates”, “projects”, “potential” and similar expression s, or that events or conditions

“will”, “would”, “may”, “could” or “should” occur. Although Kutcho Copper believes the expectations expressed

in such forward-looking statements are based on reasonable assumptions, such statements are not guarantees of future

Kutcho Copper Corp.

-5-

performance, are subject to risks and uncertainties, and actual results or realities may differ materially from those in

the forward-looking statements. Such material risks and uncertainties include, but are not limited to , the Company’s

ability to raise sufficient capital to fund its obligations under its property agreements going forward, to maintain its

mineral tenures and concessions in good standing, to explore and develop the Kutcho project or its other projects, to

repay its debt and for general w orking capital purposes; changes in economic conditions or financial markets; the

inherent hazards associates with mineral exploration and mining operations, future prices of copper and other metals,

changes in general economic conditions, accuracy of mine ral resource and reserve estimates, the ability of the

Company to obtain the necessary permits and consents required to explore, drill and develop the Kutcho project and

if obtained, to obtain such permits and consents in a timely fashion relative to the C ompany’s plans and business

objectives for the projects; the general ability of the Company to monetize its mineral resources; and changes in

environmental and other laws or regulations that could have an impact on the Company’s operations, compliance

with environmental laws and regulations, aboriginal title claims and rights to consultation and accommodation,

dependence on key management personnel and general competition in the mining industry. Forward -looking

statements are based on the reasonable beliefs, estimates and opinions of the Company’s management on the date the

statements are made. Except as required by law, the Company undertakes no obligation to update these forward -

looking statements in the event that management’s beliefs, estimates or opinio ns, or other factors, should change.