Jaguar Mining Reports Updated Mineral Reserves and Mineral Resources Boosts Proven and Probable Mineral Reserves BY 63% __________________________________________________________________________________
1
JAGUAR MINING INC.
1400-25 Adelaide Street East, Toronto, Ontario M5C 3A1 T: 416-847-1854
JAGUAR MINING REPORTS UPDATED MINERAL RESERVES AND MINERAL
RESOURCES
BOOSTS PROVEN AND PROBABLE MINERAL RESERVES BY 63%
__________________________________________________________________________________
Toronto, March 31, 2025 – Jaguar Mining Inc. ("Jaguar" or the "Company") (TSX: JAG, OTCQX:
JAGGF) is pleased to announce its annual Mineral Reserves and Mineral Resources (MRMR)
statement for 2024.
Detailed tabulations and discussion of this 2024 MRMR disclosure may be found within the Company's
Annual Information Form for the year ended December 31, 2024 , which was filed today. An updated
Technical Report for the MTL complex was prepared in accordance with National Instrument 43 -101 -
Standards of Disclosure for Mineral Projects ("NI 43-101") and also filed today. Both documents can be
found under Jaguar’s profile on SEDAR+ https://www.sedarplus.ca.
HIGHLIGHTS
• Proven and Probable Mineral Reserves (2P Mineral Reserves) increased by 63% to 764
koz (5,903 kt @ 4.03 g/t Au), net of mining depletion. The Onças de Pitangui project reported
the first Mineral Reserves of 284 koz (2,122 kt @ 4.16 g/t Au).
• Measured and Indicated (M&I) Resources decreased by 1% net of depletion to 1,659 koz
(12,325 kt @ 4.19 g/t Au).
• Inferred Mineral Resources increased to 1,676 koz (14,621 kt @ 3.56 g/t Au), highlighting the
Company’s strong growth potential.
• Onças de Pitangui project measured and indicated resources increased by 2% to 457 koz
(3,547 kt @ 4.01 g/t Au) and inferred resources increased by 29% to 490 koz (4,184 kt @ 3.64
g/t Au).
• Faina zone continued its upward trajectory, with a 16% increase in 2P Mineral Reserves to 160
koz (1,019 kt @ 4.87 g/t Au).
• Life of Mine (LOM) plans at Pilar demonstrate five years of production starting in 2025, while
the MTL complex LOM, with the inclusion of the Onças d e Pitangui reserves and resources ,
demonstrates gold production well past 2030.
Vern Baker, CEO of Jaguar Mining stated, “This year’s Mineral Reserve and Mineral Resource update
further advances our organic growth strategy. With the initial disclosure of probable Mineral Reserves
at our Onças de Pitangui project, we increased our reserve base by 63%. While we have challenges to
overcome following the incident at our MTL Complex which resulted in the suspension of operations at
our Turmalina mine, once we are able to return to work at this mine, we see a direct road to increase
the ounce production across the Company. Increasing Mineral Reserves, especially with new
orebodies, is the key to having new mining areas that can take our production to a new level.”
2
JAGUAR MINING INC.
1400-25 Adelaide Street East, Toronto, Ontario M5C 3A1 T: 416-847-1854
Proven and Probable Mineral Reserves and Measured, Indicated and Inferred Mineral Resources
figures are reported for the Company’s two operating mining and production complexes, MTL and
Caeté, and for the Paciência complex (currently on care and maintenance) in the Iron Quadrangle Gold
Province, Minas Gerais, Brazil. The MTL complex (currently suspended) is comprised of the Turmalina
mine (orebodies A, B and C), the Faina zone, the Onças de Pitangui project as well as the Zona Basal
and Pontal deposits. The Caeté complex is comprised of the Pilar mine (orebodies BA, BF, SW, LPA
and TORRE), the Roça Grande mine (on care and maintenance) and the Córrego Brandão open -pit
deposit. The Paciência complex is comprised of the Santa Isabel and Margazão mines (both on care
and maintenance) and the Bahú deposit.
2024 MINERAL RESERVES AND MINERAL RESOURCES
The Mineral Resources and Mineral Reserves reported herein and respective changes in inventory
were consolidated based on estimates sourced from the technical reports listed in Table 3. CIM (2014)
definitions were followed for Mineral Reserves estimates.
The location map in Figure 1 indicates the location of the Company’s production complexes and
respective mines and deposits . The Mineral Rights are situated inside a 60 km radius from Belo
Horizonte, the state capital of Minas Gerais, Brazil.
Figure 1. Schematic location map showing Jaguar’s mineral rights and production complexes
associated to the Rio das Velhas greenschists of the Iron Quadrangle Gold Province
3
JAGUAR MINING INC.
1400-25 Adelaide Street East, Toronto, Ontario M5C 3A1 T: 416-847-1854
Figure 2. Bar chart of the consolidated 2024 Proven & Probable Mineral Reserves by operation
Mineral Reserves
The Company’s Proven and Probable Mineral Reserves as at December 31, 2024, increased by 63%
to 764 koz, net of mining depletion, mainly due to the addition of 284 koz of Mineral Reserves from the
Onças de Pitangui project (see bar chart in Figure 2).
Detailed information of the Company’s current consolidated Mineral Reserves inventory , as at
December 31, 2024, is shown in Table 1 at the end of this release.
MTL Complex Mineral Reserves
A total of 572 koz of Mineral Reserves are attributed to the MTL complex Mineral Reserves, distributed
among the Turmalina mine Orebodies A, B, & C, the Faina zone and the Onças de Pitangui project.
Longitudinal sections shown in Figures 3, 4 and 5 illustrate the spatial distribution of the Mineral
Reserves and actual or planned development associated to the Turmalina mine , the Faina zone and
the Onças de Pitangui project.
The current Mineral Reserves inventory resulted from the following add-ons and depletions in 2024:
Mineral Reserves were estimated by Jaguar staff, reviewed and validated by SLR’s Qualified Persons.
Turmalina mine
The current Proven and Probable Mineral Reserves of 128 koz (1,255 kt @ 3.26 g/t Au) for Orebodies
A, B, & C represent a net decrease of 16 koz from the Mineral Reserves established in December 2023
resulting from:
- The depletion of 29 koz resulting from mining activities in 2024;
- The subtraction of 5 koz resulting from a risk analysis performed in 2024 and,
- The re-categorization of Mineral Resources into18 koz of Mineral Reserves resulting from
in-fill / step-out drilling and geological model reinterpretation.
4
JAGUAR MINING INC.
1400-25 Adelaide Street East, Toronto, Ontario M5C 3A1 T: 416-847-1854
The Turmalina mine 2P Mineral Reserves are distributed among the following orebodies:
- Orebody A (29 koz, 226 kt @ 3.95 g/t Au);
- Orebody B (30 koz, 304 kt @ 3.04 g/t Au); and
- Orebody C (70 koz, 695 kt @ 3.12 g/t Au).
Faina zone
The Faina zone hosts a total of 160 koz (1, 019 kt @ 4.87 g/t Au) of Proven and Probable Mineral
Reserves. The Mineral Reserve addition of 27 koz attributed to the re -categorization of Mineral
Resources exposed by the underground development and infill drilling that took place in 2024. The
addition was offset by the production of 4 koz in 2024, resulting in a net increase of 22 koz com pared
to the prior year.
Onças de Pitangui project
NI 43 -101 Technical Report - Turmalina Mining Complex, Minas Gerais, Brazil , by SLR Consulting
(Canada) Ltd. (SLR), includes an update of Probable Mineral Reserves totalling 284 koz (2,122kt @
4.16 g/t Au) at the Onças de Pitangui project.
Figure 3. Long Sections showing year-over-year changes in Turmalina mine Mineral Reserves
2024 vs 2023
5
JAGUAR MINING INC.
1400-25 Adelaide Street East, Toronto, Ontario M5C 3A1 T: 416-847-1854
Figure 4. Long Sections showing year-over-year changes of the Faina zone Mineral Reserves
2024 vs 2023
Figure 5. Cross Section showing the Onças de Pitangui project Reserves as at December 31,
2024
Caeté Complex Mineral Reserves
Pilar mine
Infill and step-out drilling and geological model reinterpretation executed in 2024 at the Pilar mine
resulted in the addition of 43 koz to the Pilar mine mineral inventory. Th is addition was offset by the
extraction of 45 koz in 2024. As a result, the updated estimates of the Pilar mine Mineral Reserves total
an amount of 192 koz (1536 kt @ 3.89 g/t Au), a 2 koz net decreas e in the 2P Mineral Reserve
categories if compared to the 194 koz (1,906 Kt @ 3.17 g/t Au) of 2P Mineral Reserves.
Mineral Reserves at the Pilar mine are divided between Orebody BA ( 38 koz, 259 kt @ 4.53 g/t Au),
Orebodies BFs (106 koz, 850 kt @ 3.89 g/t Au), Orebody SW (28 koz, 250 kt @ 3.48 g/t Au), Orebody
Torre (13 koz, 114 kt @ 3.61 g/t Au) and others (7 koz, 63 kt @ 3.38 g/t Au).
6
JAGUAR MINING INC.
1400-25 Adelaide Street East, Toronto, Ontario M5C 3A1 T: 416-847-1854
The Longitudinal sections shown in Figure 6 illustrate the spatial distribution of the Mineral Reserves
and actual development at the Pilar mine.
Figure 6. Long Section showing year-over-year changes in Pilar mine Mineral Reserves 2024 vs
2023
Mineral Resources
The Company’s consolidated Mineral Resources as at December 31, 2024, include both the updated
Mineral Resources for the Pilar and Turmalina mines, Faina zone, as well as for the Onças de Pitangui
project, along with the unchanged Mineral Resources from previous disclosures for the Pontal and Zona
Basal deposits, the Roça Grande, Santa Isabel and Marzagão mines, and the Córrego Brandão and
Bahu deposits.
Consolidated Measured and Indicated Mineral Resources decreased by 1% to 1,659 koz (12,325 kt @
4.19 g/t Au), net of mining depletion. Inferred Mineral Resources increased by 3% to 1,676 koz (14,621
kt @ 3.56 g/t Au) which is a 48 koz net increase over the prior year.
Mineral Resources were estimated by Jaguar staff, reviewed and validated by SLR’s Qualified Persons.
Detailed information of the Company’s current consolidated Mineral Resources inventory as at
December 23, 2024, is shown in Table 2 at the end of this release.
7
JAGUAR MINING INC.
1400-25 Adelaide Street East, Toronto, Ontario M5C 3A1 T: 416-847-1854
Figure 7. Graph showing the changes in M&I + I Resource Inventory in 2024 according to the
estimation’s updates and respective material sources.
MTL Complex
Consolidated MTL complex (Measured and Indicated) Mineral Resources underground are reported as
1,104koz (8,219 kt @ 4.18 g/t Au) and Inferred Mineral Resources underground are reported as 906
koz (7,371 kt @ 3.82 g/t Au) . Open pit Inferred Mineral Resources are reported as 32kozs (781 kt @
1.28 g/t Au). The consolidated Mineral Resources are subdivided as follows:
Underground Mineral Resources
• Turmalina mine Measured and Indicated Mineral Resources are reported as 360 koz, (2,875 kt
@ 3.90 g/t Au).
• Turmalina mine Inferred Mineral Resources are reported as 117 koz, (1214 kt @ 3.00 g/t Au).
• Faina zone Measured and Indicated Mineral Resources of 258 koz, (1,532 kt @ 5.23 g/t Au).
• Faina zone Inferred Mineral Resources are reported as 193 koz, (1,145 kt @ 5.25 g/t Au).
• Pontal deposit Measured and Indicated Mineral Resources are reported as 29 koz, (266 kt @
3.44 g/t Au) unchanged from 2023 disclosure.
• Pontal deposit Inferred Mineral Resources are reported as 24 koz, (159 kt @ 4.72 g/t Au)
unchanged from 2023 disclosure.
• Pontal South deposit Inferred Mineral Resources are reported as 81 koz, (669 kt @ 3.76 g/t
Au) unchanged from 2023 disclosure.
• Onças de Pitangui project Measured and Indicated Mineral Resources of 457 koz, (3,547 kt @
4.01 g/t Au).
• Onças de Pitangui project Inferred Mineral Inferred Resources are reported as 490 koz, (4,184
kt @ 3.64 g/t Au).
The year-over-year changes in the Mineral Resources distribution at the Turmalina mine are illustrated
in the longitudinal sections shown in Figures 8, 9 and 10.
8
JAGUAR MINING INC.
1400-25 Adelaide Street East, Toronto, Ontario M5C 3A1 T: 416-847-1854
Open Pit Mineral Resources
• Zona Basal deposit Inferred Mineral Resources (Open Pit) are reported as 32 koz, (781 kt @
1.28 g/t Au) , unchanged since the initial estimates prepared by SLR reported in Technical
Report on the Turmalina Complex, Minas Gerais, Brazil with effective date of November 30,
2023.
Figure 8. Long Section of the Turmalina mine’s Mineral Resources year-over-year changes
(2024 vs. 2023).
Figure 9. Long Section of the Faina zone Mineral Resources year-over-year changes (2024 vs.
2023).