Saturday, September 26, 2026
MiningNewsTerminal
Saturday, September 26, 2026 Admin

IVN.TO ·

Platreef successfully completes sinking of Shaft 1 to its final depth of approximately 1,000 metres below surface Mine development work now focused on equipping Shaft 1 as Platreef’s initial production shaft Project team achieves South African shaft-sinking industry leader

Mine Development & Operations

June 16, 2020

Platreef successfully completes sinking of Shaft 1

to its final depth of approximately 1,000 metres below surface

Mine development work now focused on equipping Shaft 1

as Platreef’s initial production shaft

Project team achieves South African shaft-sinking industry leader

status for safety performance

Updated Definitive Feasibility Study expected to be finalized

in Q3 2020; will include a scoping study on the phased

development production plan

MOKOPANE, SOUTH AFRICA – Ivanhoe Mines’ (TSX: IVN; OTCQX: IVPAF) Co-

Chairmen Robert Friedland and Yufeng “Miles” Sun announced today that the company’s

South African subsidiary, Ivanplats, has successfully completed the sinking of Shaft 1 to a

final depth of 996 metres below surface, at the company’s palladium, platinum, nickel,

copper, gold and rhodium Platreef mining licence.

The Platreef Project, which contains the thick, high-grade, flat-lying, underground Flatreef

Deposit, is a Tier One discovery by Ivanhoe Mines' geologists on the Northern Limb of

South Africa's Bushveld Igneous Complex; the world's premier platinum producing region.

Underground mine development work now will focus on the construction of the 996-metre-

level station at the bottom of the shaft, with final completion forecasted by the end of July

2020, well ahead of the contractual schedule. The shaft can then be reconfigured and

equipped for rock, personnel and material hoisting.

The new auxiliary winder for the 7.25-metre diameter Shaft 1, which is scheduled to be

delivered to Platreef later this year, will be used to assist in equipping the shaft and

thereafter for logistics, shaft examination and auxiliary functions. The auxiliary winder will

provide a second means of ingress and egress from the shaft after removal of the stage

winder. Shaft 1 is located approximately 350 metres away from a high-grade area of the

Flatreef orebody, planned for bulk-scale, mechanized mining.

“The Platreef Project has long been recognized as one of the world’s largest deposits of

high-grade platinum-group metals, (PGMs) nickel and copper. With the sinking of Shaft 1

2

now complete, we are exploring near-term development pathways at Platreef that will allow

us to expedite production at the next world-class mine on the Northern Limb,” said Mr.

Friedland. “We are particularly pleased that the project remains ‘Fall-of-Ground’ incident

free since shaft-sinking operations began in July 2016, which is a tribute to the excellent

work by the Platreef Project team and its South African sinking contractor, Moolmans.”

The Platreef team has proudly achieved South African shaft-sinking industry leader status

in terms of safety performance.

Members of the Platreef team celebrate the completion of sinking Shaft 1 to a

final depth of 996 metres below surface. Shaft 1’s headframe is in the

background.

Updated DFS is nearing completion, which includes a scoping study on the

phased development production plan for the Platreef Project

Ivanhoe is updating the Platreef Project’s 2017 definitive feasibility study (DFS) to take into

account development schedule advancement since 2017 when the DFS was completed,

updated costs and refreshed metal prices and foreign exchange assumptions.

Concurrently, Ivanhoe is finalizing a Preliminary Economic Assessment (PEA) for the

phased development production plan for the Platreef Project. The plan targets significantly

lower initial capital, to accelerate first production by using Shaft 1 as the mine’s initial

production shaft, followed by expansions to the production rate as outlined in the 2017

DFS.

3

The re-evaluation is being done in parallel with the ongoing mine development work to

access the thick, high-grade, flat-lying Flatreef deposit that was discovered in 2010 and

outlined in the Platreef 2017 Feasibility Study.

“The pending study will assess phased development options at Platreef with substantially

lower upfront capital. The goal is to prioritize near-term production while safeguarding our

strong balance sheet. We are confident that the project will, in time, become one of the

world’s largest and lowest-cost primary producers of platinum-group metals and provide

long-lasting and meaningful benefits to all of our stakeholders, including the 20 local

communities − comprising approximately 150,000 local Mokopane area residents − that

are our equity partners," Mr. Friedland added.

Sifiso Mblangwe and his shaft-sinking teammates at a pre-shift safety meeting.

The team achieved a South African shaft-sinking industry leader status for its

safety performance.

Underground mining to incorporate highly-productive, mechanized methods

Planned mining methods will use highly-productive, mechanized methods, including long-

hole stoping and drift-and-fill mining. Each method will utilize cemented backfill for

maximum ore extraction. The ore will be hauled from the stopes to a series of internal ore

passes and fed to the primary ore silos adjacent to Shaft 2, where it will be crushed and

hoisted to surface.

Shaft 1 reached the top of the high-grade Flatreef Deposit (T1 mineralized zone) at a depth

of 780.2 metres below surface in Q3 2018. The thickness of the mineralized orebody (T1

and T2 mineralized zones) at Shaft 1 is 29 metres, with grades of platinum-group metals

ranging up to 11 grams per tonne (g/t) 3PE (platinum, palladium and rhodium) plus gold, as

4

well as significant quantities of nickel and copper. The 29-metre intersection yielded

approximately 3,000 tonnes of ore, estimated to contain more than 400 ounces of

platinum-group metals. The ore is stockpiled on surface and is being used for metallurgical

test work.

Platreef’s shaft-sinking team operating the six-boom jumbo to drill the final

round to a depth of 996 metres below surface. Underground development work

now will focus on the construction of the 996-metre-level station.

The development of the three primary mining access level stations has been completed

with only the 996 metre spillage clearing level remaining, which will be completed by end

July 2020. The three development stations will provide initial, underground access to the

high-grade orebody. Shaft 1 changeover detailed designs are being completed and will

enable Shaft 1 to be configured for permanent hoisting and dewatering.

The mining zones in the current Platreef Mine plan occur at depths ranging from

approximately 700 metres to 1,200 metres below surface. When completed, Shaft 2 is

expected to provide primary access to the mining zones; secondary access is expected to

be via Shaft 1. During mine production, both shafts also are expected to serve as

ventilation intakes. Three additional ventilation exhaust raises are planned to achieve

steady-state production.

Ivanplats received its Integrated Water Use Licence in January 2019, which is valid for 30

years and enables the Platreef Project to make use of water as planned in the 2017 DFS.

5

Figure 1: Schematic section of the Platreef Mine, showing Flatreef’s T1 and T2

thick, high-grade mineralized zones (red and dark orange), underground

development work completed to date in shafts 1 and 2 (white) and planned

development work (gray).

6

Revenue per tonne of ore at the Platreef Project in South African Rand near all-

time highs

Significant increases in the price of palladium, rhodium, gold and nickel over the last three

years has resulted in the weighted price of the ‘basket’ of metals contained in the ore at the

Platreef palladium-platinum-rhodium-nickel-copper-gold project to rise to levels that are

significantly higher than when the 2017 DFS was completed. In addition, the South African

Rand has depreciated significantly against the US dollar in recent years, resulting in the

weighted price of Platreef’s ‘basket’ of metals in South African Rand trading near all-time

highs.

Figure 2. Revenue per tonne of ore at the Platreef Project since 2016 (shown in

US dollars)

7

Figure 3. Revenue per tonne of ore at the Platreef Project has risen steadily since

2016 (shown in South African rand).

Source for figures 1 & 2: Bloomberg. Based on historical weekly commodity prices at the end of each week.

Notes for Figures 1 and 2:

1. Based on Platreef Mineral Reserves with an effective date of May 24, 2017.

2. Probable Mineral Reserve of 124.7 million tonnes at a grade of 1.95 grams per tonne (g/t) platinum, 2.01

g/t palladium, 0.30 g/t gold, 0.14 g/t rhodium, 0.34% nickel and 0.17% copper.

3. A declining NSR cut-off of $155 per tonne (t) to $80/t was used for the Mineral Reserve estimates.

4. The NSR cut-off is an elevated cut-off above the marginal economic cut-off.

5. Metal prices used in the Mineral Reserve estimate: US$1,600 per ounce (oz) platinum, US$815/oz

palladium, US$1,300/oz gold, US$1,500/oz rhodium, US$8.90 per pound (lb) nickel and US$3.00/lb

copper.

6. Tonnage and grade estimates include dilution and mining recovery allowances.

7. Applies life-of-mine average recoveries of 87.4% for platinum, 86.9% for palladium, 78.6% for gold,

80.5% for rhodium, 87.9% for copper and 71.9% for nickel.

8. Total cash cost includes mine site costs, plus realization costs such as treatment and refining charges,

royalties and transportation.

8

About the Platreef Project

The Platreef Project is owned by Ivanplats (Pty) Ltd, which is 64%-owned by Ivanhoe

Mines. A 26% interest is held by Ivanplats’ historically-disadvantaged, broad-based, black

economic empowerment (B-BBEE) partners, which include 20 local host communities with

approximately 150,000 people, project employees and local entrepreneurs. In Q2 2019,

Ivanplats reached Level 2 contributor status in its verification assessment on the B-BBEE

scorecard. A Japanese consortium of ITOCHU Corporation, Japan Oil, Gas and Metals

National Corporation and Japan Gas Corporation owns a 10% interest in Ivanplats, which it

acquired in two tranches for a total investment of $290 million.

Boilermaker, Aide Samuel Teffo (left), Millwright, Lerato Maake (centre), and

Rigger, Innocent Nchabeleng (right), display medals they received for their

excellent safety performance during the sinking of Shaft 1.

Qualified Person

Disclosures of a scientific or technical nature in this news release have been reviewed and

approved by Stephen Torr, who is considered, by virtue of his education, experience and

professional association, a Qualified Person under the terms of NI 43-101. Mr. Torr is not

considered independent under NI 43-101 as he is the Vice President, Project Geology and

Evaluation. Mr. Torr has verified the technical data disclosed in this news release.

Ivanhoe has prepared a current, independent, NI 43-101-compliant technical report for the

Platreef Project, titled The Platreef 2017 Feasibility Study Technical Report dated

September 4, 2017, prepared by DRA Global, OreWin Pty. Ltd., Amec Foster Wheeler,

Stantec Consulting, Murray & Roberts Cementation, SRK Consulting, Golder Associates,