Saturday, September 26, 2026
MiningNewsTerminal
Saturday, September 26, 2026 Admin

IVN.TO ·

Kamoa-Kakula Copper mines 339,000 tonnes of ore grading 5.50% copper in February, including 107,000 tonnes grading 9.01% copper from the high-grade centre of the Kakula Mine, setting a new production record

Drill Results

March 1, 2021

Kamoa-Kakula Copper mines 339,000 tonnes of ore grading 5.50%

copper in February, including 107,000 tonnes grading 9.01% copper

from the high-grade centre of the Kakula Mine, setting a new

production record

■

Volume of ore from underground mining now exceeding steady-state

monthly requirements of the Phase 1, 3.8-Mtpa concentrator

■

Pre-production ore stockpiles now hold 2.16 million tonnes grading

4.44% copper, containing more than 95,000 tonnes of copper

■

Major conveyor belt changeover to permanent configuration

completed in February, with underground ore now directly delivered

to the surface stockpile

■

Overall progress of Kamoa-Kakula’s first phase, 3.8-Mtpa mining and

milling operation now 78% complete; initial commissioning underway

at the concentrator and first copper production on track for July 2021

■

Phase 2 expansion to 7.6 Mtpa progressing well toward a Q3 2022

start-up

■

Potential for sustained higher copper prices further improves

outstanding project economics

KOLWEZI, DEMOCRATIC REPUBLIC OF CONGO – Ivanhoe Mines (TSX: IVN; OTCQX:

IVPAF) Co-Chairs Robert Friedland and Yufeng “Miles” Sun are pleased to announce

that underground ore production at the Kamoa-Kakula Copper Project in the Democratic

Republic of Congo (DRC) has for the first time exceeded the steady-state requirements

of the Phase 1, 3.8-million-tonne-per-annum (Mtpa) concentrator plant. In February, the

project mined and stockpiled 339,000 tonnes of ore grading 5.50% copper from the

Kakula and Kansoko mines. The tonnage was 13% higher than January, while the

copper grade continued to trend higher.

2

The new production record in February was achieved even with undertaking the

scheduled conveyor belt changeover to the permanent configuration at the Kakula

Mine, which limited underground ore haulage for one week.

The 339,000 tonnes mined in February include 47,300 tonnes grading 4.62% copper

from the Kansoko Mine, establishing a new monthly production record at Kansoko. The

total tonnage mined also includes 107,000 tonnes grading 9.01% copper from the high-

grade centre of the Kakula Mine.

The project’s pre-production surface stockpiles now contain approximately 2.16 million

tonnes of high-grade and medium-grade ore at an estimated blended average of 4.44%

copper. Contained copper in the stockpiles increased by approximately 19,000 tonnes

in February – a 19.2% increase over January’s production – to a cumulative total of

more than 95,000 tonnes (the current copper price is approximately US$9,100 a tonne).

Kamoa-Kakula is on track to have more than three million tonnes of high-grade and

medium-grade ore stockpiled on surface, holding more than 125,000 tonnes of

contained copper, prior to the planned start of processing in July 2021.

George Gilchrist, Ivanhoe Mines’ Vice President, Resources (left), and Franck

Twite, Kamoa Copper’s Senior Supervisor Geology (right), mapping an ultra-high-

grade ore zone at Kakula. The dark gray layers of chalcocite ore contain

approximately 10% copper based on results from nearby channel sample

profiles.

3

Potential for sustained higher copper prices draws attention to the

project’s exceptional economics using long-term copper prices of

US$4.00/lb and US$4.50/lb

In September 2020, Ivanhoe published outstanding economic results of the independent

Integrated Development Plan 2020 (IDP20) for the Kamoa-Kakula Copper Project. The

IDP20 comprised three development scenarios: Kakula definitive feasibility study (DFS)

at a mining rate of 6 Mtpa; Kakula-Kansoko pre-feasibility study (PFS) at a mining rate

of 7.6 Mtpa, and Kamoa-Kakula preliminary economic assessment (PEA) at a mining

rate of 19 Mtpa. The base case, long-term copper price used in the IDP20 was US$3.10

per pound (lb), on a real basis.

Since the IDP20 was published, spot copper prices have surged to new nine-year highs

of more than US$4.30/lb. While this surge has not yet changed long-term copper price

assumptions, this warrants a closer look at the long-term copper price sensitivities

published at the time of the various development scenarios using long-term copper

prices of US$4.00/lb (US$8,818/ tonne) and US$4.50/lb (US$9,921/tonne), given the

potential now for sustained higher copper prices.

The Kakula 2020 FS highlights that a mining rate of 6 Mtpa yields an after-tax NPV8% of

US$5.5 billion and IRR of 77% at a long-term copper price of US$3.10/lb, rising to US$8.4

billion and IRR of 100% at a copper price of US$4.00/lb, and US$9.5 billion and 106.9% at

a copper price of US$4.50/lb.

The Kakula-Kansoko 2020 PFS highlights that a mining rate of 7.6 Mtpa yields an after-

tax NPV8% of US$6.6 billion and IRR of 69% at a long-term copper price of US$3.10/lb,

rising to US$10.5 billion and IRR of 93% at a copper price of US$4.00/lb, and US$12.0

billion and 99.8% at a copper price of US$4.50/lb.

The Kamoa-Kakula 2020 PEA highlights that a mining rate of 19 Mtpa yields an after-tax

NPV8% of US$11.1 billion and IRR of 56.2% at a long-term copper price of US$3.10/lb,

rising to US$18.1 billion and IRR of 79.9% at a copper price of US$4.00/lb, and US$20.9

billion and IRR of 89% at a copper price of US$4.50/lb.

“We’ve been publicly stating for the record confidence about higher copper prices in

real terms for a long time. The stars now are aligning for the start of production at

Kamoa-Kakula,” said Mr. Friedland. “We believe we’re only on the cusp of what will be a

structural, powerful and long-term commodity rally given supply limitations and

fundamental demand from global green initiatives.”

“The economics for pushing ahead with the Phase 3 and 4 expansions to bring the

project’s mining rate to 19 Mtpa are compelling,” Mr. Friedland added. “At this

expanded rate, Kamoa-Kakula will rank as the world’s second largest copper producer,

with peak annual copper production of more than 800,000 tonnes. Our team has only

scratched the surface on our massive, 100%-owned exploration licences in the

4

adjoining Western Foreland region that shares virtually identical geology to Kamoa-

Kakula and is the focus of an expansive exploration campaign from this year onwards.”

Underground mine development remains well ahead of schedule, providing

the confidence to push forward with Kamoa-Kakula’s Phase 2 construction

February’s advancement of 2,798 metres brings total underground development to

approximately 35.5 kilometres – around 12.4 kilometres ahead of schedule. The monthly

underground development in February was comprised of 2,389 metres at the Kakula

Mine and 409 metres at the Kansoko Mine.

Drift-and-fill stoping operations are progressing well at the Kakula Mine, with

approximately 70% of January’s ore production coming from stoping operations and

the remainder coming from mine development activities. Drift-and-fill stoping is a

highly-productive mining method of extracting underground ore, where a single tunnel,

known as a stope, is extracted leaving an open void that is subsequently backfilled to

allow for the extraction of the neighbouring stope in sequence.

Mark Farren, Kamoa Copper’s CEO, commented: “An outstanding performance in

February under some challenging circumstances, given that we completed a major

conveyor belt changeover at Kakula. The changeover slowed underground development

and load-and-haul operations, as the underground tips could not be used for a week

and ore had to be trucked to surface. Despite the temporary conveyor-related

slowdown, we saw a strong mining performance with record tonnes and copper grade

delivered to surface stockpiles.”

“We continue to successfully mine the high-grade stoping areas in the center of the

Kakula Mine at selective cuts of approximately 10-metres high by 7.5-metres wide in a

single pass. This bulk mining method is enormously beneficial as it generates large-

volume, high-grade ore blocks that can be mined selectively,” Mr. Farren added.

5

Jumbo drill in operation in a 10-metre-high by 7.5-metre-wide high-grade stoping

area in the central part of the Kakula Mine.

Mine geologist Micheline Kyenge showing the ultra-high-grade chalcocite ore in

the Kakula central area that is averaging more than 8% copper.

6

Auto electrician Raul Mwenze – one of thousands of bright, young Congolese

who are helping transform Kamoa-Kakula into the world’s next great copper

mine.

Kansoko’s ore mined in February was approximately 47,300 tonnes at an average grade

of 4.62% copper. The tonnage was 82% higher than achieved in January and the

average copper grade was 7% higher. Kansoko now has introduced a third mining crew,

and is ramping up production. Kansoko will be an important part of the production mix

for the Phase 2 concentrator plant when it begins operations – currently planned for Q3

2022.

Phase 1 copper production from the Kakula Mine is scheduled to begin in July 2021.

Kakula is projected to be the world’s highest-grade major copper mine, with an initial

mining rate of 3.8 Mtpa at an estimated early average feed grade of more than 6.0%

copper, ramping up to 7.6 Mtpa in Q3 2022. Phases 1 and 2 combined are forecast to

produce up to approximately 400,000 tonnes of copper per year. Based on independent

benchmarking, the project’s phased expansion scenario to 19 Mtpa would position

Kamoa-Kakula as the world’s second largest copper mining complex, with peak annual

copper production of more than 800,000 tonnes.

A 2020 independent audit of Kamoa-Kakula's greenhouse gas intensity metrics

performed by Hatch Ltd. of Mississauga, Canada, confirmed that the project will be

among the world's lowest greenhouse gas emitters per unit of copper produced.

7

The Kamoa-Kakula Copper Project is a joint venture between Ivanhoe Mines (39.6%),

Zijin Mining Group (39.6%), Crystal River Global Limited (0.8%) and the Government of

the Democratic Republic of Congo (20%).

Mechanic Landry Moma Twite performing maintenance on a jumbo drill rig at the

Kakula North heavy equipment workshop.

Construction is advancing rapidly on the concentrator equipment workshop (left)

and storehouse (right).

8

The bulk reclaim tip at the Kakula Mine is nearing completion.

February’s ore production was 13% higher than January at slightly higher

grades; pre-production surface ore stockpiles now total approximately 2.16

million tonnes grading 4.44% copper

Chart 1: Cumulative tonnes and grade of pre-production ore stockpiles at the

Kakula and Kansoko mines – May 2020 to February 2021.