Kamoa Copper’s Phase 2 concentrator plant approaching 93% completion; hot commissioning of the Phase 2 concentrator plant to begin in April 2022
January 24, 2022
Kamoa Copper’s Phase 2 concentrator plant approaching 93%
completion; hot commissioning of the Phase 2 concentrator
plant to begin in April 2022
■
Dedicated engineering team appointed with goal of boosting
combined Phase 1 and Phase 2 copper production up to
450,000 tonnes per annum
■
Mark Farren, Chief Executive Officer of Kamoa Copper, to retire
following the commissioning of Phase 2
KOLWEZI, DEMOCRATIC REPUBLIC OF CONGO – Ivanhoe Mines (TSX: IVN;
OTCQX: IVPAF) Co-Chairs Robert Friedland and Yufeng “Miles” Sun announced
that Kamoa-Kakula’s Phase 2, 3.8-million-tonne-per-annum (Mtpa) concentrator
plant is expected to be 93% complete by January 31, 2022, with hot
commissioning of the concentrator on track to begin in April 2022, at the front
end of the Q2 2022 previous guidance and several months ahead of the original
schedule.
Hot commissioning involves introducing first ore into the plant at a reduced feed
rate to set equipment parameters and test performance. Feed rate is then steadily
increased.
Kamoa Copper continues to make significant construction progress on the Phase
2 concentrator plant, and the plant is expected to be approximately 93% complete
by the end of January. Hot commissioning now is expected to commence in April,
and the first copper concentrate produced from the Phase 2 plant is expected
approximately one week after ore is fed into the ball mills.
The Phase 2 plant is identical to the Phase 1 3.8-Mtpa concentrator plant and a
faster ramp-up profile is expected, with the added benefit of operational
knowledge gained during the commissioning of Phase 1.
For comparison, the Phase 1 concentrator reached monthly design throughput
during September 2021, which was the fourth full month of operation. First ore
was introduced into Kamoa Copper’s Phase 1 concentrator plant on May 20, 2021,
and first concentrate was produced from the Phase 1 plant on May 25, 2021. The
Phase 1 concentrator currently is running at a throughput that is in excess of its
2
design capacity of 3.8-Mtpa by more than 15%, with 117% of design throughput
achieved in December. Copper recoveries also are being achieved that are in
excess of design recovery of 86%, depending on feed grade, with December’s
recoveries approximately 2% higher.
A dedicated project team has been appointed to de-bottleneck both the Phase 1
and Phase 2 concentrators (after commissioning), with targeted improvements
aimed at increasing plant throughput from the design of 7.6 million tonnes per
annum to 9.0 million tonnes per annum and producing up to 450,000 tonnes per
annum of copper in concentrate from the first two plants once steady-state is
achieved.
As announced earlier this month, the 2022 production guidance for the Kamoa-
Kakula Copper Complex is between 290,000 to 340,000 tonnes of copper in
concentrate. The figures are on a 100%-project basis and copper reported in
concentrate is prior to refining losses or deductions associated with smelter
terms.
“While most of the mining industry struggles to meet construction timelines and
budgets, Kamoa Copper continues to exceed expectations in delivering on the
project’s first two development phases,” said Mr. Friedland. “Kamoa-Kakula
represents only the beginning of our undertaking to unlock the potential of this
remarkable new copper province, which has the unique combination of
outstanding scale, grade, mine life, and environmental, social, and governance
credentials.”
The Phase 3 expansion, which is expected to be commissioned in Q4 2024, also
is advancing, with work ongoing on a new box cut to access the Kamoa Mine. An
updated pre-feasibility study, including the Phase 3 expansion, is expected in Q3
2022.
Mark Farren to retire as Kamoa Copper’s CEO following
commissioning of Phase 2 expansion; successor search underway
Mr. Friedland and Mr. Sun also announced that Mark Farren, Kamoa Copper’s
Chief Executive Officer, will retire from his position at Kamoa Copper following
the commissioning of the Phase 2 expansion project. Kamoa Copper has initiated
a search for Mr. Farren’s replacement, and Mr. Farren will help support a smooth
and seamless transition.
Mr. Farren first joined Ivanhoe Mines in June 2014 as Executive Vice President,
Operations, before his appointment as Chief Executive Officer of Kamoa Copper
in October 2019. During his time as Kamoa Copper’s CEO, Mr. Farren oversaw the
construction, commissioning and operation of the Phase 1 mine and concentrator
at Kamoa-Kakula, as well as the project’s Phase 2 and 3 expansions.
3
“Mark has accomplished a great deal during his time with Ivanhoe Mines and
Kamoa Copper, including delivering the Phase 1 project on budget and ahead of
schedule in an unprecedented macroeconomic environment. Under his watch, the
Phase 1 ramp-up was exceptionally smooth, and the Phase 2 expansion project is
running ahead of schedule. Before he leaves, he will have successfully overseen
the development of the Kamoa-Kakula complex into one of the ten largest copper
producers on the planet,” said Mr. Friedland.
“From all of us at Ivanhoe Mines, together with our partner Zijin Mining, we owe
Mark a debt of gratitude for his efforts. We wish him all the best in his well-
deserved retirement, in which he plans to spend more time fishing.
“It is a well-known adage that time spent fishing is not deducted from one’s
lifespan; as such, when Mark gets bored catching fish, we will gladly welcome
him back in a senior role with any of the Ivanhoe group of companies.”
Yufeng “Miles” Sun added: “Kamoa-Kakula has become an industry benchmark
under Mark’s leadership, especially given the challenges posed by the COVID-19
pandemic. I salute Mark’s significant contributions and wish him continuous
success.”
Jinghe Chen, Chairman of Zijin Mining, said: “Zijin Mining sincerely appreciates
Mark’s diligent work and his magnificent achievements in transforming Kamoa-
Kakula into one of the world’s top copper producers. I wish Mark and his family
all the best in his retirement.”
Ben Munanga, Chairman of the Board of Directors of Kamoa Copper, also
commented: “Kamoa Copper’s outstanding success to date is a product of the
culture and values promoted throughout the organization under Mark’s guidance.
Mark has been instrumental in developing strong managerial talent at Kamoa
Copper, and we are confident that his legacy will continue for many years to
come.”
Mr. Farren commented: “I have had a long-term goal to retire while I am healthy
and able to pursue my hobbies and new adventures. Working with the Ivanhoe
Mines and Kamoa Copper teams over the last decade exceeded my expectations
and I could not have asked for better co-workers or a more supportive ownership
and Board of Directors.
“I am incredibly proud of playing a part in Kamoa-Kakula’s success, and I’m
convinced that the best is still to come. I will continue to work with my successor
and the rest of the team to ensure the smooth commissioning of the Phase 2
expansion.”
4
Kamoa-Kakula’s Phase 1 (left) and Phase 2 concentrator plants.
Electrician Tresor Nawej Tshimwish installing an electrical cable at the
Phase 2 high-pressure-grinding-rolls (HPGR) substation. More than 83% of
the Phase 2 electrical cable has been installed.
5
Mardoche Muswamba (left) and Kakeya Tshidjamba installing electrical
wiring to the pneumatic control valves on the Phase 2 primary mill
cyclones. More than 75% of the Phase 2 instruments have been installed.
Ilunga Geplige strapping cables at the Phase 2 secondary crusher.
Approximately 170,000 metres of copper electrical cable will be used to
wire Kamoa-Kakula’s Phase 2 plant.
6
About the Kamoa-Kakula Copper Complex
Kamoa-Kakula is projected to be the world’s highest-grade major copper
complex, with an initial mining rate of 3.8 Mtpa at an estimated, average feed
grade of more than 6.0% copper over the first five years of operations, and 5.9%
copper over the initial 10 years of operations. Phase 1 is expected to produce
approximately 200,000 tonnes of copper per year, while the Phase 2 expansion is
forecast to increase production to more than 400,000 tonnes of copper annually.
Based on independent benchmarking, the project’s phased expansion scenario to
19 Mtpa would position Kamoa-Kakula as the world’s second-largest copper
mining complex, with peak annual copper production of more than 800,000
tonnes.
The Kamoa-Kakula Copper Project is a joint venture between Ivanhoe Mines
(39.6%), Zijin Mining Group (39.6%), Crystal River Global Limited (0.8%) and the
Government of the Democratic Republic of Congo (20%). A 2020 independent
audit of Kamoa-Kakula's greenhouse gas intensity metrics performed by Hatch
Ltd. of Mississauga, Canada, confirmed that the project will be among the world's
lowest greenhouse gas emitters per unit of copper produced.
Qualified Persons
Disclosures of a scientific or technical nature regarding development scenarios
at the Kamoa-Kakula Project in this news release have been reviewed and
approved by Steve Amos, who is considered, by virtue of his education,
experience and professional association, a Qualified Person under the terms of NI
43-101. Mr. Amos is not considered independent under NI 43-101 as he is Kamoa
Copper’s Head of Projects. Mr. Amos has verified the technical data disclosed in
this news release.
Ivanhoe has prepared an independent, NI 43-101-compliant technical report for
the Kamoa-Kakula Project, which is available on the company’s website and
under the company’s SEDAR profile at www.sedar.com:
• Kamoa-Kakula Integrated Development Plan 2020 dated October 13, 2020,
prepared by OreWin Pty Ltd., China Nerin Engineering Co., Ltd., DRA Global,
Epoch Resources, Golder Associates Africa, KGHM Cuprum R&D Centre Ltd.,
Outotec Oyj, Paterson and Cooke, Stantec Consulting International LLC, SRK
Consulting Inc., and Wood plc.
The technical report includes relevant information regarding the assumptions,
parameters and methods of the mineral resource estimates on the Kamoa-Kakula
Project cited in this news release, as well as information regarding data
verification, exploration procedures and other matters relevant to the scientific
and technical disclosure contained in this news release.
7
About Ivanhoe Mines
Ivanhoe Mines is a Canadian mining company focused on advancing its three
principal projects in Southern Africa: the development of major new, mechanized,
underground mines at the Kamoa-Kakula copper discoveries in the Democratic
Republic of Congo and at the Platreef palladium-rhodium-platinum-nickel-copper-
gold discovery in South Africa; and the extensive redevelopment and upgrading
of the historic Kipushi zinc-copper-germanium-silver mine, also in the Democratic
Republic of Congo.
Kamoa-Kakula began producing copper concentrates in May 2021 and, through
phased expansions, is positioned to become one of the world's largest copper
producers. Kamoa-Kakula is being powered by clean, renewable hydro-generated
electricity and is projected to be among the world’s lowest greenhouse gas
emitters per unit of metal produced. Ivanhoe Mines has pledged to achieve net-
zero operational greenhouse gas emissions (Scope 1 and 2) at the Kamoa-Kakula
Copper Mine. Ivanhoe also is exploring for new copper discoveries on its Western
Foreland exploration licences in the Democratic Republic of Congo, near the
Kamoa-Kakula Project.
Information contacts
Investors: Bill Trenaman +1.604.331.9834 / Media: Matthew Keevil +1.604.558.1034
Forward-looking statements
Certain statements in this release constitute “forward-looking statements” or “forward-looking
information” within the meaning of applicable securities laws. Such statements and information
involve known and unknown risks, uncertainties and other factors that may cause the actual
results, performance or achievements of the company, its projects, or industry results, to be
materially different from any future results, performance or achievements expressed or implied
by such forward-looking statements or information. Such statements can be identified by the
use of words such as “may”, “would”, “could”, “will”, “intend”, “expect”, “believe”, “plan”,
“anticipate”, “estimate”, “scheduled”, “forecast”, “predict” and other similar terminology, or state
that certain actions, events or results “may”, “could”, “would”, “might” or “will” be taken, occur or
be achieved. These statements reflect the company’s current expectations regarding future
events, performance and results and speak only as of the date of this release.
Such statements include without limitation, (i) statements regarding hot commissioning of the
Phase 2 concentrator is on track to begin in April 2022; (ii) statements regarding the first copper
concentrate produced from the Phase 2 plant is expected approximately one week after ore is
fed into the ball mills; (iii) statements regarding the 2022 production guidance for the Kamoa-
Kakula Copper Complex is between 290,000 to 340,000 tonnes of copper in concentrate; (iv) all
statements regarding the Phase 3 expansion is expected to be commissioned in Q4 2024; (v)
statements regarding an updated pre-feasibility study for the Kamoa-Kakula Project, including
the Phase 3 expansion, is expected in Q3 2022; (vi) statements regarding Kakula is projected to
8
be the world’s highest-grade major copper mine, with an initial mining rate of 3.8 Mtpa at an
estimated, average feed grade of more than 6.0% copper over the first five years of operations
and 5.9% copper over the initial 10 years of operations; (vii) statements regarding Kamoa-
Kakula’s Phase 1 is expected to produce approximately 200,000 tonnes of copper per year, and
Phases 1 and 2 combined are forecast to produce up to 450,000 tonnes of copper per year;
(viii) statements regarding based on independent benchmarking, the project’s phased
expansion scenario to 19 Mtpa would position Kamoa-Kakula as the world’s second largest
copper mining complex, with peak annual copper production of more than 800,000 tonnes; and
(ix) statements regarding Kamoa-Kakula will be among the world's lowest greenhouse gas
emitters per unit of copper produced.
Forward-looking statements and information involve significant risks and uncertainties, should
not be read as guarantees of future performance or results and will not necessarily be accurate
indicators of whether or not such results will be achieved. A number of factors could cause
actual results to differ materially from the results discussed in the forward-looking statements or
information, including, but not limited to, the factors discussed below and under “Risk Factors”,
and elsewhere in this release, as well as unexpected changes in laws, rules or regulations, or
their enforcement by applicable authorities; the failure of parties to contracts with the company
to perform as agreed; social or labour unrest; changes in commodity prices; and the failure of
exploration programs or studies to deliver anticipated results or results that would justify and
support continued exploration, studies, development or operations.
Although the forward-looking statements contained in this release are based upon what
management of the company believes are reasonable assumptions, the company cannot
assure investors that actual results will be consistent with these forward-looking statements.
These forward-looking statements are made as of the date of this release and are expressly
qualified in their entirety by this cautionary statement. Subject to applicable securities laws, the
company does not assume any obligation to update or revise the forward-looking statements
contained herein to reflect events or circumstances occurring after the date of this release.
The company’s actual results could differ materially from those anticipated in these forward-
looking statements as a result of the factors set forth below in the “Risk Factors” section in the
company’s 2021 Q3 MD&A and its current annual information form.