Kamoa Copper to expand processing capacity of Kamoa- Kakula’s Phase 1 and Phase 2 concentrators by 21%, to a combined total of 9.2 million tonnes of ore per year

Corporate Updates

February 22, 2022

Kamoa Copper to expand processing capacity of Kamoa-

Kakula’s Phase 1 and Phase 2 concentrators by 21%, to a

combined total of 9.2 million tonnes of ore per year

■

Copper production from the first Kamoa Copper’s two phases

projected to exceed 450,000 tonnes per year by Q2 2023,

positioning Kamoa Copper as the world’s fourth largest copper

producer

■

Construction of Kamoa-Kakula’s Phase 2 concentrator almost

complete and early-stage commissioning activities underway;

first concentrate production expected in April 2022

■

Engineering and early works for the Phase 3 expansion

progressing quickly, with a third, significantly larger

concentrator expected to commissioned in Q4 2024

KOLWEZI, DEMOCRATIC REPUBLIC OF CONGO – Ivanhoe Mines (TSX: IVN;

OTCQX: IVPAF) Co-Chairs Robert Friedland and Yufeng “Miles” Sun announced

that Kamoa Copper has approved a de-bottlenecking plan for Kamoa-Kakula to

increase the combined design processing capacity of the Phase 1 and Phase 2

concentrator plants by approximately 21%, to 9.2 million tonnes of ore per year

(Mtpa), up from 7.6 Mtpa, once steady-state production is achieved at both

concentrators.

The de-bottlenecking initiative is expected to increase Kamoa-Kakula’s Phase 1

and Phase 2 annual copper output to more than 450,000 tonnes by Q2 2023 ─

positioning Kamoa-Kakula as the world’s fourth largest copper producer.

Mark Farren, Kamoa Copper’s CEO, said: “Kamoa-Kakula is blessed with an

incredible endowment of high-grade copper resources. Given that our

underground mine development and ore production are both progressing well

ahead of schedule, the plant expansion will allow the operations team to process

significantly more high-grade copper ore directly from the Kakula Mine in the

years ahead.

2

“Our orebody has a huge advantage in allowing us to adapt our mining cut-off to

mine larger tonnages very efficiently, while maintaining grades above a desired

level. The expansion also provides the team with the flexibility to utilize our

surface stockpiles, for which the mining is already paid for, that totalled more

than 4.4 million tonnes grading 4.61% copper at the end of January.”

Construction of Kamoa-Kakula’s Phase 2, 3.8-Mtpa concentrator plant almost is

complete with early-stage commissioning activities now underway. Hot

commissioning of the concentrator with first ore and initial copper concentrate

production are both on track for April 2022.

Engineering and early works for the Phase 3 expansion, including a new box cut

and twin declines to access new mining areas, is progressing quickly. A third,

significantly larger concentrator is being designed and is expected to

commissioned in Q4 2024. An updated pre-feasibility study, including the Phase 3

expansion, is expected in Q3 2022. Also underway are early works on a direct-to-

blister flash smelter at Kamoa-Kakula that will incorporate leading-edge

technology supplied by Metso Outotec of Finland, and have a nameplate capacity

of 500,000 tonnes a year of approximately 99%-pure blister copper.

The Phase 1 concentrator currently is running at a throughput that is in excess of

its 3.8-Mtpa design capacity by more than 22%, with 112% of design throughput

achieved in January. Copper recoveries of above 87% also are consistently being

achieved that are in excess of design recovery of 85.6%, depending on feed

grade, with January’s recoveries approximately 2.7% higher.

Despite the Phase 1 concentrator incurring significant downtime for critical tie ins

and changes required for the commissioning of the Phase 2 concentrator, the

copper in concentrate produced in January totalled 18,824 tonnes ─ almost the

same as December’s record production of 18,853 tonnes. January’s impressive

operating performance of the Phase 1 concentrator is continuing in February. On

February 7th, the concentrator set a new daily ore throughput record with 13,498

tonnes milled.

3

Figure 1: Kamoa-Kakula’s base-case, pro-forma copper production

(after de-bottlenecking is complete) relative to the world’s projected

top 10 producing mines in 2022 by paid copper production.

Source: Company filings, Wood Mackenzie (February 2022). Note: Kamoa-Kakula production of 435 kt

paid copper production, or 450 kt copper in concentrate, is based on expected Phase 1 and 2 steady

state production, following de-bottlenecking of both Phase 1 and 2 concentrators.

Steve Amos, Ivanhoe Mines’ Head of Projects, DRC, commented: “After

successfully operating the Phase 1 concentrator for more than eight months,

we’ve identified a number of relatively minor modifications to the concentrator

that should increase ore throughput from the current design of 475 tonnes per

hour to 580 tonnes per hour. These modifications include increasing the diameter

of a number of pipes, replacing a number of motors and pumps with larger ones

and installing additional flotation, concentrate-thickening, concentrate-filtration

and tailings-disposal capacity.

“We expect the de-bottlenecking project to cost approximately US$50 million and

take approximately 12 months to complete. These modifications will allow the

team to consistently operate the concentrator plant at the increased throughput

without compromising plant availability, copper recovery or copper concentrate

grade. Engineering design is under way and procurement of long-lead items

already has started. We expect to be in a position to increase Kamoa-Kakula’s

combined processing capacity to 9.2 million tonnes of ore a year by Q2 2023.”

As announced earlier this year, the 2022 production guidance for the Kamoa-

Kakula Copper Complex is between 290,000 to 340,000 tonnes of copper in

-

200

400

600

800

1,000

Paid Copper Production (kt)

4

concentrate. The figures are on a 100%-project basis and copper reported in

concentrate is prior to refining losses or deductions associated with smelter

terms.

The Kamoa-Kakula Mining Complex, with the Phase 1 and Phase 2

concentrator plants circled in red.

Another view of the Kamoa-Kakula Mining Complex, with the Kakula North

ore stockpiles in front and the Phase 1 and Phase 2 concentrators in the

rear.

5

Commissioning team observing the delivery of first ore to Kamoa-Kakula’s

Phase 2 high-pressure-grinding-rolls (HPGR) stockpile on February 18th.

Assembly of Kamoa-Kakula’s Phase 2 flotation cells now is complete and

early-stage commissioning activities are underway.

6

Mill operator Rachel Museka, collecting pulp-density samples at Kamoa-

Kakula’s Phase 1 concentrator.

Gracia Mbaka Indundu, Senior Operator, at the first two concentrate filter

presses, which were supplied by Metso Outotec of Espoo, Finland.

7

Priscille Mandandj, Rachel Museka, Esther Kabiz and Flora Kaj Somp,

celebrating the completion of construction of the Phase 2 ball mills.

Excavating crew at Kamoa-Kakula’s new box cut for the twin declines that

will provide access to the Phase 3 mining areas. (L-R) Katshaba Gracien,

Milto Bikos, Nkulu Mwepu, Maseo Kabey, Mandew Jean, and Mutomb

Jasue.

8

Excavation work is advancing quickly at Kamoa-Kakula’s new box cut for

the twin declines that will provide access to the Phase 3 mining areas.

About the Kamoa-Kakula Copper Complex

Kamoa-Kakula is the world’s fastest growing major copper mine. Kamoa-Kakula

began operations in May 2021 and produced approximately 106,000 tonnes of

copper in concentrate in 2021. Kamoa-Kakula’s 2022 production guidance is

between 290,000 to 340,000 tonnes of copper in concentrate.

Based on independent benchmarking, the project’s phased expansion scenario to

19 Mtpa would position Kamoa-Kakula as the world’s second-largest copper

mining complex, with peak annual copper production of more than 800,000

tonnes.

The Kamoa-Kakula Copper Project is a joint venture between Ivanhoe Mines

(39.6%), Zijin Mining Group (39.6%), Crystal River Global Limited (0.8%) and the

Government of the Democratic Republic of Congo (20%). A 2020 independent

audit of Kamoa-Kakula's greenhouse gas intensity metrics performed by Hatch

Ltd. of Mississauga, Canada, confirmed that the project will be among the world's

lowest greenhouse gas emitters per unit of copper produced.