Kamoa Copper reports record quarterly production of 97,820 tonnes of copper in Q3 2022

Production Results

\

October 5, 2022

Kamoa Copper reports record quarterly production of

97,820 tonnes of copper in Q3 2022

■

Kamoa-Kakula Mining Complex milled approximately

2.1 million tonnes of ore during the quarter at

an average grade of 5.6% copper

■

Kamoa Copper has produced more than

240,000 tonnes of copper year-to-date

■

Phase 3 expansion progressing well, with box cut for the new

Kamoa 1 and 2 mines now complete and decline

development underway

■

Ivanhoe Mines to issue Q3 2022 financial results and

host conference call for investors on November 14

KOLWEZI, DEMOCRATIC REPUBLIC OF CONGO – Ivanhoe Mines (TSX: IVN; OTCQX:

IVPAF) Co-Chairs Robert Friedland and Yufeng “Miles” Sun are pleased to announce

that the Kamoa-Kakula Mining Complex in the Democratic Republic of Congo has set a

new quarterly production record in the third quarter of 2022, with 97,820 tonnes of

copper in concentrate produced.

Kamoa-Kakula’s Phase 1 and 2 concentrator plants set a monthly production record in

September 2022 of 33,484 tonnes of copper in concentrate, and continue to regularly

surpass the combined throughput design capacity of 7.6 million tonnes per annum,

following the early commissioning of Phase 2 in April 2022.

Kamoa-Kakula's Phase 1 and 2 concentrator plants milled approximately 2.1 million

tonnes of ore during the third quarter at an average feed grade of 5.6% copper. This

included high-grade, run-of-mine ore from the Kakula Mine, supplemented with ore from

the surface stockpiles to meet the throughput in excess of design capacity. In line with

design parameters, copper recoveries averaged approximately 86% during the quarter.

2

Ongoing mining optimization work at the Kakula Mine successfully targeted higher head

grades during the third quarter, with the goal of increasing head grades up to 6%

copper. Kamoa Copper continues to evaluate additional material handling capacity at

the Kakula Mine to increase mining rates to feed the de-bottlenecked Phase 1 and 2

processing capacity of 9.2 million tonnes per year. Further details will be incorporated

into the Phase 3 expansion pre-feasibility study, scheduled for year-end.

To date, a total of 118.3 kilometres (73.5 miles) of underground development has been

mined across the mining complex. While the ongoing expansion of underground

infrastructure at the Kakula Mine takes place, ore will be drawn periodically from the

stockpile to maximize copper production, as the concentrators are currently operating

in excess of design capacity. Kamoa-Kakula’s total high- and medium-grade ore surface

stockpiles totaled approximately 4.2 million tonnes at an estimated grade of 4.15%

copper for a total of over 174,000 tonnes of contained copper, as of the end of

September 2022.

The Phase 1 and Phase 2 concentrator plants now are operating at an annualized

production rate of approximately 400,000 tonnes of copper in concentrate, and have

periodically exceeded this rate daily during the third quarter. The de-bottlenecking

program is on track to boost Kamoa Copper's annual production to approximately

450,000 tonnes of copper in concentrate by the second quarter of 2023.

Management continues to anticipate that the early commissioning of the Phase 2

concentrator plant in March 2022, approximately four months ahead of schedule, will

enable Kamoa Copper to deliver in the upper range of its increased 2022 production

guidance of 310,000 to 340,000 tonnes of copper in concentrate.

Ivanhoe Mines’ Founder and Executive Co-Chairman, Robert Friedland commented:

“Kamoa-Kakula has effectively doubled its copper production rate to approximately

400,000 tonnes per year since the first quarter, and is expected to be producing at an

annualized rate of 450,000 tonnes per year by the second quarter of 2023. This all has

been achieved ahead of schedule and on budget ... a true pink unicorn in the mining

industry and a great credit to the operating team at Kamoa Copper and our joint-venture

partner, Zijin Mining.

“This success is built upon Ivanhoe Mines' industry-leading history of mineral

discovery, which will play a pivotal role in the company's future. We remain committed

to discovering and developing tier-one ore bodies … to provide a supply of metals

critically needed for the electrification of the world economy ... and reduction of

greenhouse gases throughout the supply chain.”

Watch a September fly-over of mining and expansion activities at

Kamoa-Kakula: https://vimeo.com/756832174/5e0fc76a83

3

Construction of an additional scavenger-cleaner flotation cell at the Phase 2

concentrator, which is part of the de-bottlenecking program designed to boost

copper production to approximately 450,000 tonnes per annum by Q2 2023.

Also part of the de-bottlenecking program, construction of the additional

concentrate thickener is advancing well.

4

Figure 1: Quarterly copper production since first production at Kamoa-Kakula in

May 2021. Over 345,000 tonnes of copper have been produced to September 30,

2022.

Kamoa-Kakula reports record quarterly production of 97,820 tonnes copper

for Q3 2022

Commercial production from Kamoa-Kakula’s Phase 2 concentrator plant was declared

on April 7, 2022, while steady state production was achieved at the end of May 2022.

The Kamoa-Kakula Mining Complex milled approximately 5.0 million tonnes of ore at an

average feed grade of 5.6% copper year-to-date, and produced approximately 240,736

tonnes of copper in concentrate through September 30, 2022. A total of 2.1 million ore

tonnes were milled during the third quarter at an average feed grade of 5.6% copper.

Kamoa-Kakula set a new quarterly production record in the third quarter of 2022 with

97,820 tonnes of copper in concentrate produced, up from 87,314 tonnes produced in

the second quarter and 55,602 tonnes produced in the first quarter.

Kamoa-Kakula achieved a daily record of 26,361 tonnes of ore milled per day on the last

day of the quarter. In addition, a daily production record of 1,426 tonnes of copper in

concentrate was achieved on September 3, 2022.

Over 100,000 tonnes of copper were floated during the quarter, including the contained

copper that has been floated, but not yet filtered. As at September 30, 2022, there was a

balance of approximately 4,800 tonnes of contained copper in the circuit.

9,858

44,506

51,533 55,602

87,314

97,820

Q2 21 Q3 21 Q4 21 Q1 22 Q2 22 Q3 22

Quarterly Copper Produced (kt)

5

The difference between floated and filtered copper arises from the current bottleneck in

concentrate filter capacity, as the Phase 1 and 2 milling and flotation circuit continues

to operate in excess of design capacity. Floated copper is temporarily stored as a slurry

in a fully lined pond, which will be reclaimed into the concentrate thickener and filter

press once the fourth Larox filter press is installed as part of the de-bottlenecking

program.

The fourth Larox filter press, from Metso Outotec of Espoo, Finland, is expected to

arrive on site by year-end and will be commissioned in January 2023. In the meantime,

Kamoa Copper is working on initiatives to maximize the capacity of the existing three

filter presses.

(L-R) Mbbuti Romain, KKCC General Mounter; and Wang Lei, KKCC Riveter, on

the assembly platform for the new scavenger-cleaner flotation cells, which are

being installed as part of the de-bottlenecking program at the Phase 1

concentrator.

Kamoa Copper’s previously announced de-bottlenecking program is progressing on

schedule to increase the combined design processing capacity of the Phase 1 and

Phase 2 concentrator plants to approximately 9.2 million tonnes per annum.

6

After successfully operating the Phase 1 concentrator, the Kamoa-Kakula team

identified several relatively minor modifications that are expected to increase ore

throughput by approximately 20%, from the design capacity of 475 tonnes per hour to

approximately 580 tonnes per hour. These modifications include increasing the

diameter of several pipes, replacing several motors and pumps with larger ones and

installing additional flotation, concentrate-thickening, concentrate-filtration and tailings-

disposal capacity. The total capital requirement for the de-bottlenecking program is $50

million.

Once completed in the second quarter of 2023, the de-bottlenecking program will enable

the copper production from Kamoa-Kakula’s first two phases to reach approximately

450,000 tonnes per year, positioning the Kamoa-Kakula Mining Complex as the world’s

fourth largest copper producing operation.

The Kamoa Copper process engineering team, together with a number of

internationally-recognized external metallurgy specialists, is investigating new

technologies to economically recover additional copper units from the tailings stream

of the Phase 1 and 2 concentrators, thereby potentially increasing overall recovery

above the design target of 86%.

Lualaba Copper Smelter restarts following scheduled maintenance

The Lualaba Copper Smelter, located approximately 50 kilometres from Kamoa-Kakula,

completed its scheduled maintenance in early September. The transportation of copper

concentrates to the facility has resumed, as well as the export of its blister copper

(approximately 99% contained copper). The Lualaba Copper Smelter is expected to treat

approximately 120,000 tonnes of copper concentrates from Kamoa Copper in 2022.

In line with previous disclosures, Kamoa Copper is in the process of implementing

several initiatives to optimize the transportation of copper products, following higher

logistics costs announced in Q2 2022 due to a significant increase in volumes shipped.

The restart of the Lualaba Copper Smelter will assist in reducing overall shipping

volumes, as the export of blister copper incurs lower logistics costs per unit of copper

compared to copper concentrate. While the logistics optimization initiatives are

underway, Kamoa Copper and other operators have continued to experience disruption

including periodic border congestion and occasional industrial action by truck drivers.

7

A close-up of a blister copper ingot, containing approximately 99% copper, and

its identification tag at the Lualaba Copper Smelter, near Kolwezi.

Kamoa 1 and Kamoa 2 box cut and decline ramp now complete, Phase 3

twin decline excavation well underway

Kamoa-Kakula's Phase 3 will consist of two new underground mines known as Kamoa 1

and Kamoa 2, located 10 kilometres north of the existing Phase 1 and Phase 2

concentrator plants. A new, 5-million-tonne-per-annum concentrator plant will also be

established adjacent to the two new Kamoa mines. In addition, a 500,000-tonne-per-

annum, direct-to-blister flash smelter will be constructed adjacent to the existing Phase

1 and Phase 2 concentrator plants. The associated power and surface infrastructure

constructed for Phase 3 will be designed to support future expansions of the Kamoa-

Kakula Mining Complex.

Construction now is complete on the Phase 3 box cut and decline ramp at the Kamoa 1

and Kamoa 2 underground mines, while excavation of the twin declines to access the

new mining areas is advancing well. Construction works for the ramp, cut-off drains,

and water-collection sumps also now is complete.

Basic engineering design for the entire Phase 3 expansion project is complete, with

procurement activities well advanced. Bush clearing and terracing work for the 5-

million-tonne-per-annum concentrator plant and associated surface infrastructure has

started. Earthworks and civils contracts have been placed.

Upon commencement of Phase 3 production, the Kamoa-Kakula Mining Complex will

have a processing capacity in excess of 14 million tonnes per annum. Phase 3 is

8

expected to increase copper production capacity to approximately 600,000 tonnes per

annum, with commissioning expected by the fourth quarter of 2024. This production

rate will position the Kamoa-Kakula Mining Complex as the third-largest copper mining

operation in the world.

Kamoa-Kakula’s Phase 3 expansion also includes the refurbishment of turbine #5 at the

Inga 2 hydroelectric power station. The turbine will supply an additional 178-megawatts

of clean hydroelectric power to the national grid, which is sufficient to meet the power

requirements of the Phase 3 concentrator, the direct-to-blister flash smelter, as well as

providing spare capacity for future expansions. The blister anode copper produced

from Kamoa-Kakula’s smelter is expected to be one of the lowest carbon emitters per

tonne of copper produced in the world.

The Kamoa-Kakula smelter is designed to use technology supplied by Metso Outotec of

Espoo, Finland, and to meet the International Finance Corporation’s (IFC) emissions

standards. The smelter has been sized to process much of the copper concentrate that

is expected to be produced by Kamoa-Kakula’s Phase 1, 2 and 3 concentrators.

Earthworks excavation is now approximately 60% complete and progressing well at the

smelter site, adjacent to Kamoa-Kakula’s Phase 1 and Phase 2 concentrator plants. Civil

works have also commenced.

3D model of the direct-to-blister flash copper smelter site, located adjacent to the

Phase 1 and 2 concentrators. Construction continues on schedule, with

commissioning expected by the end of 2024.