Saturday, September 26, 2026
MiningNewsTerminal
Saturday, September 26, 2026 Admin

IVN.TO ·

Kakula Copper Mine underground development exceeds 1,840 metres in August; more than 20.6 kilometres now complete Installation of ball mills and other major equipment for Kakula’s first 3.8-million-tonne-per-annum processing plant well underway

Mine Development & Operations Metallurgy & Processing

September 1, 2020

Kakula Copper Mine underground development exceeds 1,840 metres

in August; more than 20.6 kilometres now complete

Installation of ball mills and other major equipment for Kakula’s first

3.8-million-tonne-per-annum processing plant well underway

Second mining crew added at the Kansoko Mine, increasing the pace

of underground development at Kamoa-Kakula’s second mine

Pre-production surface stockpiles at Kakula North, Kakula South and

Kansoko now contain an estimated 671,000 tonnes of ore

Ivanhoe Mines to issue independent definitive feasibility study

and expansion studies for the entire Kamoa-Kakula Copper Project on

September 8, 2020; host Investor Day on September 10, 2020

KOLWEZI, DEMOCRATIC REPUBLIC OF CONGO – Ivanhoe Mines (TSX: IVN; OTCQX:

IVPAF) Co-Chairs Robert Friedland and Yufeng “Miles” Sun announced today that

underground development at the Kakula Copper Mine totalled 1,842 metres in August,

bringing the cumulative total underground development completed to date to more than

20.6 kilometres – approximately 6.0 kilometres ahead of schedule.

The majority of the underground development headings at the Kakula Mine currently are

traversing medium-grade sections of the orebody, with average grades ranging between

3% and 5% copper. A concentrated effort was made in August to complete the ledging

development in the room-and-pillar section of the mine to accommodate critical

infrastructure, such as piping and electrical cabling, for the mine’s permanent water-

handling system.

The ledging development work will be completed early this month and will allow the

mining teams to begin highly-productive stoping operations; however, the development

work was in lower-grade ore and resulted in a temporary, modest decrease in overall

stockpile grade in August and early September.

The stockpile grade is expected to improve, as planned, beginning this month as the

majority of the working areas will transition to the higher-grade ore zones near the

centre of the deposit that have copper grades approximately +5% to +8%.

2

The beneficial handover of the high-capacity ore conveyor system at the Kakula North

declines was achieved at the end of July. All of the ore being mined in the northern

portion of the Kakula Mine now is transported to surface via the conveyor system and

placed on a blended, run-of-mine surface stockpile. The blended stockpile contains

483,000 tonnes grading an estimated 3.76% copper; comprised of 116,000 tonnes of

high-grade ore grading 6.08% copper and 367,000 tonnes of medium-grade ore grading

3.02% copper.

Two additional, pre-production ore stockpiles are located at the Kakula South decline

(approximately 121,000 tonnes grading 2.36% copper) and the Kansoko decline

(approximately 68,000 tonnes grading 2.21% copper). More than 109,000 tonnes

of ore was added to the project’s pre-production stockpiles in August.

Surface conveyor systems to transport the ore from the Kakula North stockpile to the

processing plant are under construction.

First copper production expected in less than a year

Initial production at the Kakula Mine is scheduled for Q3 2021. Kakula is projected to be

the world’s highest-grade major copper mine, with an initial mining rate of 3.8 million

tonnes per annum (Mtpa) at an estimated average feed grade well in excess of 6%

copper over the first five years of operation.

The Kakula Mine will have one of the most favourable environmental footprints of any

tier-one copper mine anywhere in the world. The mine will be powered by clean,

renewable hydroelectricity and be among the world's lowest greenhouse gas emitters

per unit of copper produced. Kakula also will have a relatively small surface footprint as

approximately 55% of the mine’s tailings will be pumped back into underground

workings.

The Kamoa-Kakula Copper Project is a joint venture between Ivanhoe Mines (39.6%),

Zijin Mining Group (39.6%), Crystal River Global Limited (0.8%) and the DRC

government (20%).

“Together with our joint-venture partners, we look forward to sharing the independently

verified engineering and economic studies on September 8th that will showcase why

Kamoa-Kakula is, without question, the world’s best new copper project,” said Mr.

Friedland. “Kamoa-Kakula is unique as it combines ultra-high-copper grades with thick,

shallow, flat-lying ore zones, providing the economies of scale and low mining costs of

large, open-pit mining operations, but without the visual environmental impact

associated with open-pit mining.”

“We also plan to soon announce the appointment of a leading environmental consulting

firm to audit Kamoa-Kakula’s greenhouse gas intensity metrics, providing

Environmental, Social and Governance investors with independent and transparent

verification of the project’s achievements towards our goal of producing the world’s

greenest copper,” Mr. Friedland added.

3

Aerial view of the Kakula Mine showing the tonnes and grade of the main pre-

production stockpiles at the northern declines. The stockpile currently contains

approximately 483,000 tonnes grading 3.76% copper; comprised of

approximately 116,000 tonnes at 6.08% copper and 367,000 at 3.02% copper.

Kakula southern decline medium-grade ore stockpile currently containing

approximately 121,000 tonnes grading 2.36% copper.

4

Kansoko decline medium-grade ore stockpile currently containing approximately

68,000 tonnes grading 2.21% copper.

Kakula Mine development progressing towards zone of +8% copper in centre

of deposit

Underground development of the Kakula Mine – the first of multiple, near-surface

copper deposits that are planned to be put into production on the 400-square-kilometre

Kamoa-Kakula mining licence – is now significantly ahead of schedule. Mine access

drives 1 and 2 (interconnected, parallel tunnels that will provide access to ore zones)

being driven from the Kakula northern declines continue to advance towards the

southern portion of the orebody.

Development of the eastern perimeter drives also is well advanced as are the access

drives to the room-and-pillar mining area. Development of twin access drives being

driven from Kakula’s southern portal has reached the +5% copper mining zone, with

mining crews working to establish the connection of these drives with mine access

drives 1 and 2 from the northern side of the orebody. The northern and southern access

drives are expected to join in November 2020, which will be a major milestone in the

development of the Kakula orebody.

Once the northern and southern access drives are connected, the majority of mining

activities will focus on the initial drift-and-fill mining blocks in the centre of the Kakula

deposit, where the average grade is higher than 8% copper. Drift-and-fill stoping is a

5

highly-efficient form of underground mechanized mining and will allow the operation to

efficiently recover significantly more tonnes from the orebody.

Underground mining with two mining crews also is taking place at the Kansoko Mine,

located at the Kamoa deposit, approximately 10 kilometres north of the Kakula Mine.

The construction of Kakula’s second permanent underground water-handling system is

nearing completion with the first of four pump trains commissioned in early August; the

second pump train was commissioned in the last week of August. The new system adds

800 litres per second of underground pumping capacity, bringing the total installed

capacity to 1,400 litres per second. Two additional underground water dams are under

construction; one at bottom of the southern declines, and one along the north eastern

perimeter drifts.

Ivanhoe plans to issue the independent definitive feasibility study for the development

of the 6 Mtpa Kakula Mine on September 8, 2020. The company also will issue a pre-

feasibility study, including mining 1.6 Mtpa from the Kansoko Mine, to take full

advantage of an expanded plant capacity of 7.6 Mtpa at Kakula. In addition, the

company will issue an updated, expanded preliminary economic assessment for the

overall development plan of up to 19 Mtpa for all of the copper discoveries made to date

at the Kamoa-Kakula Project.

Martin Nkulu, conveyor belt attendant, monitoring high-grade copper ore being

delivered to surface via the Kakula North decline conveyor, which has the

capacity to transport 2,000 tonnes of ore an hour.

6

A load of copper ore being transported up the Kakula South decline. One of the

two southern access drives has entered the +5%-copper mining zone, while the

other will enter it shortly. The southern access drives are expected to join the

northern access drives in November.

Kasongo Mahji at a surface settling pond for Kakula’s second permanent

underground dewatering pipe system that was commissioned in early August.

7

Figure 1: The eastern portion of Kakula Mine ─ representing less than half of the

overall 13.3-kilometre-long Kakula Deposit ─ overlain on southern Manhattan

Island to give a sense of the scale of the underground operations.

Figure 2: Underground development completed to the end of July (in black) and scheduled development

(green, brown, blue & black) until September 30, 2020. Shown are the 3%, 5% and 8% copper contours and the

location where the northern and southern access drives are scheduled to join in November 2020 (red circle).