Ivanhoe Mines to issue Kamoa-Kakula 2026 and 2027 production guidance once Stage Two dewatering is further advanced
September 18, 2025
Ivanhoe Mines to issue Kamoa-Kakula 2026 and 2027
production guidance once Stage Two dewatering is further
advanced
■
Stage Two dewatering commenced on schedule; Kakula
underground water levels declining, providing access to
mine workings for inspection and rehabilitation
■
Medium-term production target of over 550,000 tonnes of
copper based on latest mine planning estimates
KOLWEZI, DEMOCRATIC REPUBLIC OF THE CONGO – Ivanhoe Mines’ (TSX:
IVN; OTCQX: IVPAF) Executive Co-Chair Robert Friedland and President and
Chief Executive Officer Marna Cloete announce today that following the last
update made on August 25, 2025, the Stage Two dewatering of the Kakula Mine
has commenced on schedule, and that Kamoa-Kakula’s 2026 and 2027 copper
production guidance will now be issued once Stage Two dewatering activities
are more advanced.
Three out of the four Stage Two high-capacity, submersible pumps were
recently installed and commissioned on schedule. Kamoa-Kakula’s
engineering team expect to have all four Stage Two pumps operating within
the coming days, operating at a combined pumping rate of approximately
2,600 litres per second. Since the commissioning of the three Stage Two
pumps, the underground water level in the Kakula Mine has dropped vertically
by 10 metres, out of a total of approximately 80 metres.
Once all four Stage Two high-capacity, submersible pumps are operational,
the existing Stage One temporary, underground pumping infrastructure will be
repositioned further down the mine, following the water level as it declines.
The total pumping rate out of the Kakula Mine is expected to increase up to a
target of approximately 6,400 litres per second, or 550 megalitres per day,
reducing the vertical underground water level by approximately one metre per
day. The majority of the Stage Two dewatering of the Kakula Mine is expected
to be complete by the end of November 2025, which is when the underground
water level is expected to reach near the bottom of the Stage Two dewatering
shafts, shown in yellow in Figure 1.
As the underground water level falls, the underground mining team have
already started systematically rehabilitating the newly dewatered areas of the
Kakula Mine. The team is initially focused on rehabilitating the areas required
for repositioning the Stage One underground pumping infrastructure.
Mine planning and scheduling is well advanced to support the ramp-up of
underground mining activities from both Kakula and Kamoa mines, with a
2
medium-term target of returning the copper production rate to over 550,000
tonnes per annum. In the meantime, copper production guidance for 2026 and
2027 will be deferred until sufficient physical inspection of the newly
dewatered areas of the Kakula Mine has been completed.
Figure 1 . A schematic of the projected decrease in underground water
levels at the Kakula underground mine from early September (light blue)
to late November 2025 (dark blue). All mining areas above the water level
are now fully accessible.
The completed assembly of the first two, 4.2-megawatt, 650-litre-per-
second, submersible pumps (Pumps 1 & 2) that were commissioned in
late August. The two submersible pumps are positioned at the bottom of
the approximately 400-metre deep shaft (left of the picture).
3
Water pumped out from the Kakula Mine is fed into nearby settling ponds
for treatment. With the underground vertical water level expected to
decline by approximately one metre per day, the majority of the Stage Two
dewatering of the Kakula Mine is expected to be complete by the end of
November 2025.
At an adjacent ventilation shaft, the installation of the remaining two
submersible pumps (Pumps 3 & 4) is complete, with commissioning of
Pump 4 underway. Kamoa-Kakula’s engineering team expect to have all
four Stage Two pumps operating within the coming days.
4
Disclosure of technical information
Disclosures of a scientific or technical nature in this news release have been
reviewed and approved by Steve Amos, who is considered, by virtue of his
education, experience, and professional association, a Qualified Person under
the terms of NI 43-101. Mr. Amos is not considered independent under NI 43-
101 as he is Ivanhoe Mines’ Executive Vice President, Projects. Mr. Amos has
verified the technical data disclosed in this news release.
About Ivanhoe Mines
Ivanhoe Mines is a Canadian mining company focused on advancing its three
principal projects in Southern Africa: the Kamoa-Kakula Copper Complex in
the DRC, the ultra-high-grade Kipushi zinc-copper-germanium-silver mine,
also in the DRC; and the tier-one Platreef platinum-palladium-nickel-rhodium-
gold-copper Mine in South Africa, which is set to start production in Q4 2025.
Ivanhoe Mines is exploring for copper in its highly prospective, 54-100%
owned exploration licences in the Western Forelands, covering an area over
six times larger than the adjacent Kamoa-Kakula Copper Complex, including
the high-grade discoveries in the Makoko District. Ivanhoe is also exploring for
new sedimentary copper discoveries in new horizons, including Angola,
Kazakhstan, and Zambia.
Follow Robert Friedland (@robert_ivanhoe) and Ivanhoe Mines
(@IvanhoeMines_) on X.
Information contact
Investors
Vancouver: Matthew Keevil +1.604.558.1034
London: Tommy Horton +44 7866 913 207
Media
Tanya Todd +1.604.331.9834
Forward-looking statements
Certain statements in this news release constitute “forward-looking statements” or
“forward-looking information” within the meaning of applicable securities laws. Such
statements and information involve known and unknown risks, uncertainties, and
other factors that may cause the actual results, performance, or achievements of the
company, its projects, or industry results to be materially different from any future
results, performance, or achievements expressed or implied by such forward-looking
statements or information. Such statements can be identified using words such as
“may”, “would”, “could”, “will”, “intend”, “expect”, “believe”, “plan”, “anticipate”,
“estimate”, “scheduled”, “forecast”, “predict” and other similar terminology, or state
that certain actions, events, or results “may”, “could”, “would”, “might” or “will” be
taken, occur or be achieved. These statements reflect the company’s current
5
expectations regarding future events, performance, and results and speak only as of
the date of this news release.
Such statements include, without limitation: (i) statements that Kamoa-Kakula 2026
and 2027 production guidance will be issued once dewatering is further advanced;
(ii) statements that Kamoa-Kakula’s engineering team are expecting to have all four
high-capacity pumps operating within the coming days; (iii) statements that once the
new Stage Two high-capacity, submersible pumps are operational, the existing
Stage One temporary underground pumping infrastructure will be repositioned
further down the mine as the water level declines, increasing the total pump out rate
from the Kakula Mine up to a target of approximately 6,400 litres per second, or 550
megalitres per day; (iv) statements that the majority of the dewatering of the Kakula
Mine is expected to be complete by the end of November 2025, which is when the
underground water level is expected to reach near the bottom of the Stage Two
dewatering shafts; (v) statements that as the water level declines, Kakula’s
underground engineering team will systematically rehabilitate, where necessary, the
newly dewatered areas of the mine; (vi) statements that Kamoa-Kakula’s
engineering team have a medium-term target of restoring Kamoa-Kakula’s copper
production rate to 550,000 tonnes of copper per annum; and (vii) statements that
Kamoa-Kakula’s engineering team will delay issuing production guidance to allow
time to physically inspect the newly de-watered areas of Kakula.
Forward-looking statements and information involve significant risks and
uncertainties, should not be read as guarantees of future performance or results, and
will not necessarily be accurate indicators of whether such results will be achieved.
Many factors could cause actual results to differ materially from the results discussed
in the forward-looking statements or information, including, but not limited to: (i)
uncertainty around the rate of water ingress into underground workings; (ii) the
ability, and speed with which, additional equipment can be secured; (iii) the
continuation of seismic activity; (iv) the state of underground infrastructure; (v)
uncertainty around when future underground access can be secured; (vi) future mine
stability cannot be guaranteed; and (vii) future mining methods, may differ the impact
on Kakula operations. Additionally, the factors discussed above and under the “Risk
Factors” section in the company’s MD&A for the three and six months ended June
30, 2025, and its current annual information form, and elsewhere in this news
release, as well as unexpected changes in laws, rules or regulations, or their
enforcement by applicable authorities; changes in the rate of water ingress into
underground workings; the continuation of seismic activity; the state of underground
infrastructure; delays in securing underground access; changes to the mining
methods required in the future; the failure of parties to contracts with the company to
perform as agreed; social or labour unrest; changes in commodity prices; and the
failure of exploration programs or studies to deliver anticipated results or results that
would justify and support continued exploration, studies, development or operations.
Although the forward-looking statements contained in this news release are based
upon what management of the company believes are reasonable assumptions, the
company cannot assure investors that actual results will be consistent with these
forward-looking statements. These forward-looking statements are made as of the
date of this news release and are expressly qualified in their entirety by this
cautionary statement. Subject to applicable securities laws, the company does not
assume any obligation to update or revise the forward-looking statements contained
6
herein to reflect events or circumstances occurring after the date of this news
release.
The company’s actual results could differ materially from those anticipated in these
forward-looking statements as a result of the factors outlined in the “Risk Factors”
section in the company’s MD&A for the three and six months ended June 30, 2025,
and its current annual information form.