Saturday, September 26, 2026
MiningNewsTerminal
Saturday, September 26, 2026 Admin

IVN.TO ·

Ivanhoe Mines reports significantly increased hydroelectric power availability for Kamoa-Kakula

Corporate Updates

April 7, 2025

Ivanhoe Mines reports significantly increased hydroelectric

power availability for Kamoa-Kakula

■

Improved operational performance at Kamoa-Kakula increased

copper production to record levels since

mid-March, 2025

■

Kamoa-Kakula produced near-record 133,120 tonnes of copper

during first quarter, with accelerating quarterly production

anticipated

■

20 megawatts of additional imported hydroelectric power

secured, further 30 megawatts expected imminently; up to 50

megawatts of Inga II Turbine #5 hydroelectric power expected

from Q4 2025

■

Given sufficient hydroelectric power, start-up of Kamoa-

Kakula’s direct-to-blister smelter to commence next month,

with 99.7% copper anode production from July 2025

■

Ivanhoe Mines to issue Q1 2025 financial results after market

on April 30, host conference call for investors

on May 1, 2025

JOHANNESBURG, SOUTH AFRICA – Ivanhoe Mines’ (TSX: IVN; OTCQX: IVPAF)

Executive Co-Chair Robert Friedland and President & Chief Executive Officer

Marna Cloete announced today, alongside the company’s first-quarter production

results, that Kamoa-Kakula has reached a major turning point following a

significant increase in imported hydroelectric power in recent weeks enabling the

start-up of the new on-site copper smelter.

Imported hydroelectric power increased by 20 megawatts (MW) to 70 MW in mid-

March. Imported hydropower is expected to increase further to 100 MW

imminently, representing a 100% increase over recent weeks.

2

Kamoa-Kakula delivered record production during the last two weeks of March at

an annualized rate above its 2025 guidance. The outperformance was also

underpinned by strong operating performance from the new Phase 3

concentrator, which delivered record throughput and copper production,

exceeding its nameplate design capacity.

Founder and Co-Chairman Robert Friedland commented:

“Despite recent volatility in global markets and with virtually all global equities

knocked down by panic … and computerized trading algorithms … Ivanhoe Mines

has a very strong balance sheet and generates powerful cash flows ... In addition,

we are in a privileged position with Kamoa-Kakula as one of the lowest-cost

copper producers in our industry… and we expect our operating costs to decline

even further as our state-of-the-art direct-to-blister smelter ramps up this year…

The production of 99.7% pure copper anodes will significantly reduce our C1

cash costs due to a more than 50% reduction in transportation costs per unit of

contained copper and the enjoyment of by-product sulphuric acid sales ... a

critical commodity in great demand in the Democratic Republic of the Congo’s

copper industry.

“We are delighted that Kamoa-Kakula’s growing pains, which led to power

challenges, are behind us following our successful efforts to secure additional

imported hydroelectricity … with more imported hydroelectric power from the

Southern Africa Power Pool on its way very soon. We now have in place a long-

term energy security program that future-proofs our energy mix as we continue to

grow into the very top ranks of the world’s largest copper production complexes.

“We are therefore sufficiently encouraged to inaugurate the startup of our state-

of-the-art Kamoa-Kakula smelter… one of the largest and most technologically

sophisticated smelters in the world. With the smelter coming online, we will no

longer simply be exporting copper concentrate — we will export the world’s

greenest copper anodes for the energy transition. As the world wakes up to a

generational copper deficit, we have the assets, the people, and the infrastructure

to deliver this responsibly sourced and most critical of all metals to world

markets.”

Watch a video highlighting Ivanhoe Mines’ 2025 first quarter

production results: https://vimeo.com/1072835122/ff0199b555

3

Commissioning of Kamoa-Kakula’s state-of-the-art 500,000-tonne-per-

annum direct-to-blister copper smelter has started with the first production

of 99.7% pure copper anodes expected in July 2025.

Summary of quarterly production data from Kamoa-Kakula

Q1 2024 Q2 2024 Q3 2024 Q4 2024 Q1 2025

Phase 1 & 2

Ore tonnes milled (000’s tonnes) 2,061 2,288 2,215 2,329 2,211

Feed grade of ore processed (% copper) 4.80% 5.04% 4.86% 5.08% 5.01%

Copper recovery (%) 87.4% 87.0% 86.6% 87.0% 88.3%

Copper in concentrate produced (tonnes) 86,117 99,706 94,214 102,042 97,575

Phase 3

Ore tonnes milled (000’s tonnes) - 93 1,050 1,326 1,512

Feed grade of ore processed (% copper) - 1.67% 2.64% 2.82% 2.76%

Copper recovery (%) - 83.3% 79.9% 85.1% 85.1%

Copper in concentrate produced (tonnes) - 1,106 22,099 31,777 35,545

Combined Phase 1, 2 and 3

Ore tonnes milled (000’s tonnes) 2,061 2,381 3,266 3,655 3,723

Feed grade of ore processed (% copper) 4.80% 4.91% 4.14% 4.26% 4.10%

Copper recovery (%) 87.4% 86.9% 85.3% 86.6% 87.4%

Copper in concentrate produced (tonnes) 86,117 100,812 116,313 133,819 133,120

Data in red denotes a quarterly record

Kamoa-Kakula produced a near-record 133,120 tonnes of copper

during first quarter, rising to a production rate of over 630,000 tonnes

of copper annualized over last two weeks of March

During the first quarter, the Phase 1, 2, and 3 concentrators milled a record 3.72

million tonnes of ore and achieved a daily milling record of 51,528 tonnes of ore

in late March. The outperformance was underpinned by initiatives implemented

earlier in the quarter that enabled the Phase 3 concentrator to be consistently fed

4

at higher rates than originally designed. Phase 3 milled a record 1.51 million

tonnes of ore during the quarter. The record is equivalent to an annualized milling

rate of 6.1 million tonnes per annum, which is more than 20% higher than the

Phase 3 concentrator’s design capacity of 5.0 million tonnes per annum. The

Phase 1 and 2 concentrators also outperformed during the quarter, although

operations were hampered by maintenance shutdowns in the first half of March.

During March, Kamoa-Kakula’s Phase 1, 2, and 3 concentrators produced an

average of 1,509 tonnes of copper per day, which is equivalent to an annualized

production rate of 550,000 tonnes per annum. After maintenance on the Phase 1

and 2 concentrators was complete, copper production increased to a record

average of 1,732 tonnes per day over the last 14 days of March. The production

record is equivalent to an annualized production rate of over 630,000 tonnes per

annum, well in excess of the 2025 guidance. An outstanding daily production

record of 1,919 tonnes of copper was also achieved on March 28, 2025.

Kamoa-Kakula is maintaining its annual production guidance of 520,000 to

580,000 tonnes of copper.

Figure 1: Chart of the growth in monthly copper production over the past

12 months, from Kamoa-Kakula’s Phase 1 & 2, and Phase 3 concentrators,

with the total annualized copper production rate at the top of each bar

Increase in imported power since mid-March to 70 megawatts; a

further increase to 100 megawatts expected shortly

During March, total average power required for the Phase 1, 2, and 3 operations

was between 130 and 140 MW. At the beginning of the month, Kamoa-Kakula was

drawing 50 MW of domestically generated hydroelectric power, with 50 MW drawn

5

from imported sources. The balance of required power was from on-site, diesel-

generated backup power, of which there is an installed capacity of up to 160 MW.

In March, an agreement was signed to increase total imported hydroelectric

power via the Zambian interconnector by 40% from 50 MW to 70 MW. The

additional power is sourced from Mozambique via the Southern Africa Power

Pool network. Kamoa-Kakula’s operations team expects a further increase in

imported power to 100 MW within the coming days. The increase in power has

provided Kamoa-Kakula’s management team with the confidence to finalize

commissioning and commence the start-up of the smelter. Power drawn by the

smelter is expected to gradually increase from 45 MW, following first concentrate

feed, up to 70 MW once at full capacity.

In addition, wet commissioning of Turbine #5 at Inga II, with a hydroelectric

generation capacity of 178 MW, is now expected to commence in the third

quarter. Kamoa-Kakula is expected to be allocated an initial, additional 50 MW of

hydroelectric power once commissioning is complete, increasing up to 178 MW

as the ongoing grid improvement initiatives are completed in 2026.

Smelter commissioning underway, with heat-up now expected to

commence in May; first copper anode production expected in July

Commissioning of Kamoa-Kakula’s 500,000-tonne-per-annum, direct-to-blister

copper smelter has started, with start-up expected to commence next month. The

initial heat-up process of the smelter is expected to take up to six weeks, after

which the first feed of concentrate will begin. Initial production of copper anode is

expected in July. Ramp up of the smelter is expected to be at approximately 80%

by year-end.

As previously announced, it is expected that between 20,000 to 30,000 tonnes of

copper in concentrate will be stockpiled in the on-site smelter concentrate

storage shed prior to starting up the smelter. At quarter-end, Kamoa-Kakula held

approximately 48,000 tonnes of unsold copper in inventory, up from 30,000

tonnes of unsold copper at the end of 2024. Approximately 20,000 tonnes of the

increase in unsold copper inventory over the past three months was newly stored

concentrate at the smelter ahead of its start-up. The majority of the remaining

unsold inventory is stored at the nearby Lualaba Copper Smelter (LCS) awaiting

toll treatment. Once fully ramped up, Kamoa-Kakula’s on-site copper smelter is

expected to hold approximately 17,000 tonnes of copper within its circuit.

6

Kamoa-Kakula’s smelter off-gas conversion plant. Gas captured from

the smelting process will be converted into high-strength sulphuric

acid and sold to mining operations in the DRC Copperbelt.

The storage and blending of Kamoa-Kakula concentrate inside the

Concentrate Blending Facility has commenced, prior to first feed of the

concentrate into the smelter, which is expected in July.

7

Aerial view of the smelter’s acid production plant. The state-of-the-art

smelter was designed to incorporate advanced technology supplied by

Metso Outotec of Espoo, Finland, and compliant with the International

Finance Corporation's (IFC) emissions standards.

Phase 3 concentrator feed grades primed to improve throughout

2025, as development at Kamoa 1 and Kamoa 2 underground mines is

completed

The majority of the ore processed by the Phase 3 concentrator continues to be

from underground development. The crews at the Kamoa and Kansoko

underground mines are focused on underground development, opening up

approximately 18 months of ore reserves prior to the commencement of primary

mining. Opening up a large accessible underground reserve base provides

operational flexibility for the underground mining crews, similar to that which has

already been achieved at the Kakula Mine.

The flat-lying nature of the Kamoa and Kakula orebodies means that underground

development can be carried out in ore, albeit at lower grades. Underground

development of the Kamoa mines is expected to continue until Q4 2025, after

which Phase 3 concentrator feed grades are expected to rise up to approximately

3% copper.

8

Kamoa-Kakula’s Project 95 is 25% complete and advancing on

schedule

Civil works for Project 95 are advancing well, as shown in the foreground,

with the adjacent Phase 1 and 2 concentrator storage shed in the

background.

The “Project 95” initiative on Kamoa-Kakula’s Phase 1 and 2 concentrators is

expected to increase concentrator recoveries to 95%, from the design recovery

rate of 87%. The initiative, with a capital expenditure of approximately $180

million, is expected to increase annualized production by up to 30,000 tonnes of

copper, at an industry-leading capital intensity of $6,000 per tonne of copper.

Kamoa-Kakula’s Project 95 is advancing well at 25% complete and is on schedule

for completion in Q1 2026.

Power purchase agreement signed to build a 30 megawatts on-site

solar facility with battery storage at Kamoa-Kakula

Kamoa Copper has signed a power purchase agreement (PPA) with

CrossBoundary Energy of Nairobi, Kenya, to install a 220 MWp Solar Photovoltaic

(PV) system and a 123 MVA / 526 MWh battery energy storage system (BESS) to

provide a continuous 30 MW at the facility. The installation will result in a 30 MW

baseload of additional green power for Kamoa-Kakula’s operations.

CrossBoundary Energy will fund, own, and operate the plant, and Kamoa Copper

will be the sole offtaker of the electricity produced.