Saturday, September 26, 2026
MiningNewsTerminal
Saturday, September 26, 2026 Admin

IVN.TO ·

Ivanhoe Mines reports Q1 2023 production of 93,603 tonnes of copper from Kamoa-Kakula Copper Complex

Production Results

April 5, 2023

Ivanhoe Mines reports Q1 2023 production of 93,603 tonnes

of copper from Kamoa-Kakula Copper Complex

■

Kamoa-Kakula produced record 34,915 tonnes of copper in

March

■

Kamoa-Kakula reported weekly production record of 9,016

tonnes of copper and daily production record of 1,563 tonnes

of copper in March

■

Phase 1 and 2 concentrators reached new daily average

milling record of over 29,000 tonnes

■

Kamoa-Kakula achieved record average copper recoveries

exceeding 88% in March

■

Kamoa-Kakula milled approximately 1.93 million tonnes of

ore during the quarter at average grade of 5.4% copper

■

Ivanhoe Mines to issue sixth annual Sustainability Report

on April 13, highlighting the company’s commitment to

mining with a greater purpose

KOLWEZI, DEMOCRATIC REPUBLIC OF CONGO – Ivanhoe Mines (TSX: IVN;

OTCQX: IVPAF) Executive Co-Chair Robert Friedland and President Marna Cloete

are pleased to announce that the Kamoa-Kakula Copper Complex in the

Democratic Republic of Congo (DRC) produced 93,603 tonnes of copper in

concentrate during the first quarter of 2023.

The Phase 1 and 2 concentrators are now regularly operating at the increased

processing rate of 9.2 million tonnes per annum (Mtpa), following the completion

of the debottlenecking program. The $50-million Phase 1 and 2 concentrator

debottlenecking program was completed on-budget and ahead of schedule in late

2

February, increasing production capacity up to 450,000 tonnes of copper in

concentrate per annum.

Following the completion of the debottlenecking, Kamoa-Kakula’s Phase 1 and 2

concentrators had a record-breaking March. A production record of 34,915 tonnes

of copper in concentrate was achieved during the month, in addition to a weekly

production record of 9,016 tonnes in mid-March, and a daily production record of

1,563 tonnes on March 25. These records were achieved following two scheduled

plant shutdowns during the first quarter to tie in the new debottlenecking

equipment.

Kamoa-Kakula's Phase 1 and 2 concentrators milled approximately 1.93 million

tonnes of ore during the first quarter at an average feed grade of 5.4% copper.

This included approximately 255,000 tonnes of ore from the surface stockpiles.

The Phase 1 and Phase 2 concentrators also substantially outperformed design

specifications in terms of copper recovery during the month, with copper

recoveries averaging 88.3% and periodically achieving 90%, significantly above

Kamoa-Kakula’s nameplate 86% recovery rate.

The record monthly production in March was also achieved despite previously

reported instability within the DRC’s southern power grid. Ivanhoe Mines

maintains its 2023 annual production guidance for Kamoa-Kakula at between

390,000 to 430,000 tonnes of copper in concentrate.

Ivanhoe Mines’ Founder and Executive Co-Chairman, Robert Friedland

commented:

“The operating performance at Kamoa-Kakula continues to impress as the team

focuses on optimizing the concentrator plant following the successful completion

of the Phase 1 and Phase 2 debottlenecking program, once again ahead of

schedule and on budget, during the first quarter. We're particularly excited about

the improving trends in copper recovery, which saw the concentrator plants

operating at recoveries as high as 90% in March ... driving record production

numbers into the end of the month.

“With the Phase 3 expansion well on track for 2024, Kamoa-Kakula represents a

truly rare, high-margin growth story across the copper industry. Kamoa-Kakula is

one of the world's largest, highest-grade copper complexes, and a major

economic engine that generates leading returns on capital and exceptional free

cash flow. As the rainy season in the Democratic Republic of Congo ends our

geological team will also be ramping up exploration activities on Ivanhoe’s 90-

100%-owned Western Foreland Exploration Project next door, where we expect to

drill around 75,000 metres this year. We’re looking forward to the many

successes to come with our partners and shareholders in 2023 and beyond.”

3

All figures are on a 100% project basis and metal reported in concentrate is

before refining losses or deductions associated with smelter terms.

Kamoa-Kakula produced 93,603 tonnes of copper during the first

quarter of 2023, compared to 92,761 tonnes of copper in the fourth

quarter of 2022.

Ivanhoe Mines announced the ahead-of-schedule and on-budget completion of

Kamoa-Kakula's Phase 1 and Phase 2 debottlenecking program on February 27,

2023. The debottlenecking program increased the nameplate ore processing

capacity by 22% from 7.6 to 9.2 million tonnes of ore per annum, increasing

production capacity up to approximately 450,000 tonnes per annum of copper in

concentrate.

Following the subsequent ramp-up, several operational records were achieved

during March, including a record daily milling rate of 29,003 dry metric tonnes on

March 18; a record daily production rate of 1,563 tonnes of copper on March 25; a

weekly production record of 9,016 tonnes of copper between March 24 and 30;

and a monthly production record of 34,915 tonnes of copper in concentrate.

Two scheduled plant shutdowns were completed during the first quarter to tie in

the new debottlenecking equipment. The shutdown of the Phase 1 concentrator

took place in late January 2023, and the shutdown of the Phase 2 concentrator

plant was completed in late February 2023. The new debottlenecking equipment

consists of new hydrocyclones, new scavenger-cleaner flotation cells, a new

concentrate thickener and a new Larox filter press, as well as upsized piping and

pumping capacity.

The Phase 1 concentrator started operating at its new, sustained nameplate

capacity of 580 dry tonnes per hour on January 25, 2023. On February 25, 2023,

within 12 hours of restarting, the Phase 2 concentrator also ramped up to its new,

sustained nameplate capacity of 580 dry tonnes per hour. Thereby, achieving the

targeted combined throughput of 9.2 million tonnes per annum. Subsequently,

both concentrators have been able to deliver, over limited periods, in excess of

600 dry tonnes per hour.

Kamoa-Kakula milled approximately 1.93 million tonnes of ore during the first

quarter at an average feed grade of 5.4% copper.

While the ongoing expansion of underground infrastructure at the Kakula Mine

takes place, ore continues to be drawn as required from surface stockpile to

maximize copper production.

4

Kamoa-Kakula’s high- and medium-grade ore surface stockpiles totaled

approximately 4.2 million tonnes at an estimated grade of 3.9% copper as of the

end of March 2023. The operation mined 2.0 million tonnes of ore grading 5.2%

copper in Q1 2023, which was comprised of 1.8 million tonnes grading 5.6%

copper from the Kakula mine, including 0.8 million tonnes grading 6.7% copper

from the mine’s high-grade centre.

(L-R) Rachelle Museka, Mill Operator; Linda Malumda, Senior Larox Filter

Operator and Fancy Katuma, Sand Filter Operator standing in front the

debottlenecked Phase 2 concentrator. The additional Larox filter capacity,

as part of the debottlenecking program, increases Kamoa-Kakula’s

production capacity up to 450,000 tonnes per annum.

Copper recoveries from the Phase 1 and Phase 2 concentrators also improved

during the quarter. The average recovery rate for the quarter was approximately

87%; however, concentrator recoveries in late March averaged 88.3% and

periodically reached 90%, well above Kamoa-Kakula’s 86% design rate. The

Kamoa Copper process engineering team, together with several internationally-

recognized external metallurgy specialists, continue to investigate the feasibility

of new technologies to further increase overall processing recoveries.

5

The recently commissioned concentrate thickener that was constructed as

part of the debottlenecking program, was completed ahead-of-schedule

and on-budget in late February. Kamoa-Kakula’s Phase 1 and 2

concentrators set a monthly production record of 34,915 tonnes of copper

in concentrate during March 2023.

Kamoa-Kakula is working closely with the DRC’s state-owned power utility, La

Société Nationale d’Electricité (SNEL) in identifying potential improvements to the

regional grid infrastructure. Kamoa-Kakula is also assisting with the delivery of

these improvements.

In addition, Kamoa Copper is independently installing sufficient redundancy to

isolate Kamoa-Kakula’s Phases 1, 2 and 3 operations from any potential future

power intermittencies. In the near term, a phased increase of on-site, installed

backup generation capacity is planned, from 32 megawatts (MW) to 132 MW. An

additional 11 MW is expected to be commissioned in the second quarter, with a

further 73 MW to be installed towards the end of 2023. Concurrently, discussions

are advancing to secure additional power via the Zambian interconnector. Longer

term, the total power redundancy capacity is expected to be up to 200MW.

6

Surface earthworks for Phase 3 concentrator plant and associated

infrastructure well advanced, with first flotation cells delivered in

March

Kamoa-Kakula's Phase 3 expansion will consist of two new underground mines

known as Kamoa 1 and Kamoa 2, located approximately 10 kilometres north of

the existing Kakula underground mine, and the Phase 1 and Phase 2

concentrators. A new, 5-million-tonne-per-annum concentrator is under

construction adjacent to the new Kamoa mines, which are also under

development.

The concrete foundations under construction for the Phase 3 concentrator

flotation cells. Construction of Phase 3 concentrator is advancing on

schedule.

First production from the Phase 3 concentrator is scheduled and expected by the

fourth quarter of 2024. Overall work on the Phase 3 concentrator was

approximately 24% complete as at the end of March.

In late March, Kamoa Copper took onsite delivery of the first of its Phase 3

flotation cells, manufactured by Metso Outotec of Espoo, Finland. Initial steel

deliveries have arrived in South Africa and are en route to the project site. In

addition, the cyclones and electrical motors have been shipped from their

respective manufacturers, while the first of the two ball mills, manufactured by

CITIC Heavy Industries, is now ready for shipment from China.

7

The concrete foundations of the direct-to-blister furnace building, as part of

the 500,000 tonnes per annum direct-to-blister flash copper smelter. The

construction of the smelter is advancing on schedule.

3D rendering of the furnace and off-gas handling building (RHS), and acid

production facility (LHS). All smelter off-gas streams, including the acid

plant tail gas, will be treated through the de-sulphurisation plant. The plant

will produce 650,000 to 800,000 tonnes of high-strength sulphuric acid per

annum, which will be sold domestically within the DRC Copperbelt.

8

Construction activities on the direct-to-blister flash copper smelter are advancing

on schedule and are approximately 36% complete. Earthworks are 100% complete

and civil works now well underway. The direct-to-blister and electric slag-

cleaning furnaces foundation construction is complete, with structural steel

installation having commenced in March. Foundation construction for the

smelting building, as well as the anode-refining furnace building are also

principally complete.

The smelter site is adjacent to Kamoa-Kakula’s Phase 1 and Phase 2 concentrator

plants and will be fed by a mix of copper concentrate produced from Phase 1, 2

and 3 concentrators.

3D rendering of the 100-hectare smelter project site. The smelter will be

constructed to meet the highest environmental and safety standards, as set

by the International Finance Corporation (IFC) Performance Standards and

the World Bank Group Environmental Health and Safety (EHS) Guidelines.

Qualified Persons

Disclosures of a scientific or technical nature at the Kamoa-Kakula Mining

Complex in this news release have been reviewed and approved by Steve Amos,

who is considered, by virtue of his education, experience and professional