Ivanhoe Mines reports 71,266 tonnes of copper produced by Kamoa-Kakula in Q3 2025; recovery efforts advancing well

Corporate Updates

October 7, 2025

Ivanhoe Mines reports 71,266 tonnes of copper produced by

Kamoa-Kakula in Q3 2025; recovery efforts advancing well

■

Stage Two dewatering advancing on schedule; approximately

20% complete

■

Start-up of Africa’s largest copper smelter to commence in

early November

■

Kipushi produced a record 57,200 tonnes of zinc in Q3 2025, a

quarterly increase of 37%

■

First platinum-palladium-nickel-gold-rhodium-copper

production from Platreef Phase 1 expected in Q4 2025; Phase 2

development underway

■

Ivanhoe Mines to issue Q2 2025 financial results after market

close on October 29; host conference call for investors on

October 30

JOHANNESBURG, SOUTH AFRICA – Ivanhoe Mines’ (TSX: IVN; OTCQX: IVPAF)

Executive Co-Chair Robert Friedland and President and Chief Executive Officer

Marna Cloete announced today the company’s third-quarter production results

and an update on operational and project activities.

During the third quarter, Kamoa-Kakula’s Phase 1, 2, and 3 concentrators milled a

total 3.46 million tonnes of ore, producing 71,226 tonnes of copper. Copper

production year to date totaled 316,393 tonnes. Production guidance of 370,000

tonnes to 420,000 tonnes of copper in concentrate is maintained, with mining of

higher-grade areas on the western side of the Kakula Mine expected from mid-

November.

Stage Two dewatering activities are over 20% complete, with underground water

levels on the eastern side of the Kakula Mine having declined by over 20 metres

since the beginning of September. Stage Two dewatering is expected to be

completed by the end of November.

2

Smelter start-up is scheduled to commence in early November, as the installation

of a 60 MW uninterruptible power supply (UPS) unit nears completion. The UPS

will safeguard the smelter complex from potential power interruptions during the

ramp-up period.

Production rates from Kipushi notably improved during the quarter following the

completion of the debottlenecking program in August. In the third quarter, the

Kipushi concentrator milled a record 168,862 tonnes of ore at an average milled

grade of 37.8%, producing a record 57,200 tonnes of zinc in concentrate. The

record quarterly production represented a 37% increase compared to Q2 2025.

Phase 1 operations at the Platreef Mine are expected to commence shortly, with

the first feed of ore into the concentrator expected in the coming weeks. Project

development work on the Phase 2 expansion is already underway, with the

appointment of the engineering, procurement and construction management

(EPCM) contractor in the fourth quarter. First production from the Phase 2

concentrator is targeted for Q4 2027.

Founder and Co-Chairman Robert Friedland commented:

"Our recovery efforts at the Kakula Mine are advancing well due to exceptional

execution from our operating teams under a decisive plan of action put in place

by our management team and joint-venture employees. We are on track to restore

Kamoa-Kakula towards its previous copper production levels as we rehabilitate

the existing workings and develop new high-grade areas across this Tier-One ore

body. Insights gathered during the dewatering efforts will be combined with input

from our world-class team of independent experts to design an updated mine

plan that will chart Kamoa-Kakula's bright future as a leading producer in the

copper industry.

"This quarter should mark a turning point in operations, as we anticipate higher

grades from Kakula's western side from next month, with selective mining of the

existing workings on the eastern side of Kakula planned from Q1 2026. We're also

on the cusp of starting operations at Africa's largest and greenest, direct-to-

blister copper smelter, which is expected to drive lower cash costs as we

complete its ramp-up.

"In addition, we're extremely excited for imminent first production at the Platreef

Mine, which is on schedule for later this month. Given rising prices and interest in

platinum-group metals, we are bringing the world's next great precious metals

complex online at an exceptionally opportune moment. Platreef's major

endowment of nickel, copper, and gold makes it one of the lowest-cost and

scalable producers of platinum, palladium, nickel, gold, rhodium and copper on

our planet ... and we are already at work on a Phase 2 expansion that will propel

Platreef into a Top 10 producer globally."

3

In preparation for the heat-up of Kamoa-Kakula’s state-of-the-art, 500,000-

tonne-per-annum, direct-to-blister copper smelter, an operator oversees a

training exercise on the slag cleaning furnace blister ladles.

Summary of quarterly production data from Kamoa-Kakula

Q3 2024 Q4 2024 Q1 2025 Q2 2025 Q3 2025

Phase 1 & 2

Ore tonnes milled (000’s tonnes) 2,215 2,329 2,211 1,991* 1,838

Feed grade of ore processed (% copper) 4.86% 5.08% 5.01% 4.12%* 2.50%

Copper recovery (%) 86.6% 87.0% 88.3% 85.4%* 81.3%

Copper in concentrate produced (tonnes) 94,214 102,042 97,575 71,401* 37,744

Phase 3

Ore tonnes milled (000’s tonnes) 1,050 1,326 1,512 1,631 1,618

Feed grade of ore processed (% copper) 2.64% 2.82% 2.76% 2.92% 2.44%

Copper recovery (%) 79.9% 85.1% 85.1% 85.5% 84.2%

Copper in concentrate produced (tonnes) 22,099 31,777 35,545 40,608 33,522

Combined Phase 1, 2, and 3

Ore tonnes milled (000’s tonnes) 3,266 3,655 3,723 3,622 3,456

Feed grade of ore processed (% copper) 4.14% 4.26% 4.10% 3.58% 2.47%

Copper recovery (%) 85.3% 86.6% 87.4% 85.4% 82.7%

Copper in concentrate produced (tonnes) 116,313 133,819 133,120 112,009 71,266

Data in red denotes a quarterly record

*Phase 1 & 2 production was impacted in the second quarter by seismic activity at the Kakula

Mine as announced on May 20, 2025.

4

Kakula head grades to improve in Q4 2025 as dewatering activities

open up higher-grade mining areas

During the third quarter, the Phase 1, 2, and 3 concentrators milled 3.46 million

tonnes of ore, producing 71,226 tonnes of copper. Total copper production year

to date is 316,393 tonnes.

As announced on June 11, 2025, mining operations on the western side of the

Kakula Mine restarted on June 7, 2025. Since mid-June, the mining rate has

increased to an average rate of 350,000 tonnes per month (4.2 million tonnes on

an annualized basis). To assist with the increase in the mining rates from the

western side of the Kakula Mine, the cut-off grade has been lowered to 1.5%

copper (previously 2.0%).

Mining on the western side of the Kakula Mine has been focused on higher-

elevation areas in the north and southwest, where copper grades are lower than

those of the higher-grade centre, which is currently submerged. From mid-

November, mining crews plan to advance towards the centre of the western side

of the Kakula Mine, improving head grades to between 3.5% and 4.5%.

The Phase 1 and 2 concentrators will continue to process ore from the western

side of the Kakula Mine, as well as surface stockpiles, until Q1 2026, when the

stockpiles are depleted. Thereafter, selective mining will commence within the

existing workings on the eastern side of the Kakula Mine, which will augment

rising production from higher-grade areas on Kakula’s western side to underpin

improved underground mining rates.

The Phase 3 concentrator milled 1.62 million tonnes of ore in the third quarter,

producing 33,522 tonnes of copper. For a second consecutive quarter, the Phase

3 concentrator averaged a milling rate equivalent to 6.5 million tonnes annualized,

which is 30% higher than design capacity of 5.0 million tonnes per annum. The

average quarterly feed grade for the Phase 3 concentrator was 2.44% copper. The

cut-off grade was also lowered to 1.5% copper at the Kamoa Mine to achieve

higher mining rates, providing sufficient feed for the Phase 3 concentrator and

supplementary feed for the Phase 1 and 2 concentrators. For the foreseeable

future, it is expected that the feed grade into the Phase 3 concentrator will

continue to average approximately 2.5% copper.

Stage Two dewatering of the Kakula Mine is advancing to plan at over

20% complete

The four Stage Two high-capacity submersible pumps were commissioned over

the course of two weeks between the end of August and mid-September. The four

pumps are operating at the total design rate of approximately 2,600 litres per

second. Including the mobile Stage One pump stations located underground, the

total pumping rate at the Kakula Mine, has the potential to pump up to 6,400 litres

per second, or 550 megalitres per day, subject to available underground access.

5

Stage Two dewatering of the Kakula Mine is over 20% complete and is expected

to be completed by the end of November 2025, at which point the underground

water level is anticipated to be near the bottom of the Stage Two dewatering

shafts.

To date, approximately 13 kilometres of lateral development has been

rehabilitated. As the water level declines, the mining crews are primarily focused

on rehabilitating the access drives required for repositioning the Stage One

underground pumping infrastructure, as well as the access towards the Stage

Three pump stations, which are currently submerged.

Stage Three pumping will complete the remaining dewatering below the water

level accessible by the Stage Two high-capacity submersible pumps, as shown in

Figure 1. The mining crews expect to start gaining access to the existing Stage

Three pumping infrastructure from November. Each pump station will be refitted

and recommissioned with new pump motors and associated electrical

infrastructure. Stage Three pumping is expected to be complete in Q1 2026.

Aerial view looking south over the two adjacent sites where the four Stage

Two high-capacity, submersible pumps were installed, in pairs, at the bottom

of two existing 400-metre deep shafts.

6

Figure 1. A schematic of the projected decrease in underground water levels

at the Kakula Mine from the end of September (light blue) to the end of

November 2025 (dark blue). Dewatering of the entire Kakula mine is expected

to be completed in February 2026.

Water pumped out from the Kakula Mine is fed into nearby settling ponds .

Stage Two dewatering of the Kakula Mine is expected to be complete at the

end of November 2025.

7

The two sites where the Stage Two dewatering infrastructure is located. Both

sites were established , with all pumping infrastructure installed and

commissioned within just 6 weeks.

Mine planning and scheduling is well advanced to support the ramp-up of

underground mining activities from both the Kakula and Kamoa mines, with a

medium-term target of returning the milling rate to 17 million tonnes per year, and

ultimately targeting annualized copper production of over 550,000 tonnes

Copper production guidance for 2026 and 2027 will be released once sufficient

physical inspection of the newly dewatered areas of the Kakula Mine has been

completed. The new life-of-mine plan is expected to be released in Q1 2026.

Smelter start-up scheduled for early November; installation nearing

completion of 60-megawatt, battery-powered, uninterruptible power

supply facility

Heat-up of Kamoa-Kakula’s on-site, direct-to-blister copper smelter is expected to

commence in early November 2025. Kamoa-Kakula’s management team expects

to prioritize the processing of all concentrates produced by the Phase 1, 2, and 3

concentrators through the on-site smelter, with any excess concentrate

continuing to be toll-treated at the nearby Lualaba Copper Smelter (LCS), in

Kolwezi.

The smelter start-up will commence as the installation of the uninterruptible

power supply (UPS) facility nears completion later this month. The 60 MW UPS is

designed to provide up to 2 hours of instantaneous back-up power to the smelter,

protecting the operation from voltage fluctuations in the DRC grid. In addition to

8

the UPS, there is a further 60 MW of dedicated diesel-powered, back-up generator

capacity.

There is sufficient on-site copper concentrate inventory for the smelter start-up in

early November. As of September 30, 2025, Kamoa-Kakula’s unsold copper in

concentrate inventory totaled 59,000 tonnes, which includes 7,300 tonnes located

at LCS. The first feed of concentrate into the smelter is expected approximately

four to six weeks after heat-up commences.

Members of the smelter team are inspecting the sulphuric acid plant ahead

of the furnace heat-up. The smelter is expected to produce up to 700,000

tonnes per annum of high-strength sulphuric acid, which is in high demand

across the Central African Copperbelt.