Saturday, September 26, 2026
MiningNewsTerminal
Saturday, September 26, 2026 Admin

IVN.TO ·

Ivanhoe Mines provides 2024 production results, 2025 production guidance

Production Results

January 8, 2025

Ivanhoe Mines provides 2024 production results, 2025

production guidance

■

Kamoa-Kakula produced record 437,061 tonnes of copper in

concentrate in 2024

■

Kamoa-Kakula quarterly production record of 133,819 tonnes

of copper, a quarter-on-quarter increase of 15%, and monthly

production record of 47,058 tonnes in December

■

Kamoa-Kakula sets 2025 production guidance at between

520,000 and 580,000 tonnes of copper

■

Smelter commissioning may be delayed by up to three months

following limited fire damage to back up generation capacity,

expedited repairs underway

■

Kipushi produced 50,307 tonnes of zinc in concentrate in 2024,

including a monthly record 14,900 tonnes in December as

ramp-up approaches nameplate capacity

■

Kipushi sets 2025 production guidance at between 180,000 and

240,000 tonnes of zinc

■

Ivanhoe Mines provides update to 2025 capital expenditure

guidance

■

Ivanhoe Mines to issue 2024 financial results after market close

on February 19, host conference call for investors

on February 20

2

JOHANNESBURG, SOUTH AFRICA – Ivanhoe Mines’ (TSX: IVN; OTCQX: IVPAF)

Executive Co-Chair Robert Friedland and President Marna Cloete announced

today the company’s fourth quarter and full-year production results for the

Kamoa-Kakula Copper Complex in the Democratic Republic of the Congo (DRC)

and the ultra-high-grade Kipushi zinc mine, also in the DRC. In addition, the

company has announced its 2025 production guidance for Kamoa-Kakula and

Kipushi, as well as updated 2025 group capital expenditure guidance.

Watch the video summarizing Kamoa-Kakula’s 2024 operational

highlights and future production guidance:

https://vimeo.com/1044780723/a114ecda2d?share=copy

Kamoa-Kakula delivers another record-breaking year with 437,061

tonnes of copper produced in 2024, a year-on-year increase of 12%

Kamoa-Kakula delivered record production in 2024 of 437,061 tonnes of copper in

concentrate, a 12% year-on-year increase, following the ramp up of the Phase 3

concentrator in the second half of 2024.

Production for the fourth quarter of 133,819 tonnes of copper in concentrate, a

15% increase from the third quarter, is also a record. This was a result of strong

performance from the Phase 1 and 2 concentrators, delivering record throughput

with improved grade and recovery, as well as the Phase 3 concentrator reaching

and at times exceeding nameplate design parameters.

Kamoa-Kakula summary of quarterly and annual production data

Q1 2024 Q2 2024 Q3 2024 Q4 2024 FY 2024

Phase 1 & 2

Ore tonnes milled (000’s tonnes) 2,061 2,288 2,215 2,329 8,893

Copper ore grade processed (%) 4.80% 5.04% 4.86% 5.08% 4.95%

Copper recovery (%) 87.4% 87.0% 86.6% 87.0% 87.0%

Copper in concentrate produced (tonnes) 86,117 99,706 94,214 102,042 382,078

Phase 3

Ore tonnes milled (000’s tonnes) - 93 1,050 1,326 2,469

Copper ore grade processed (%) - 1.67% 2.64% 2.82% 2.70%

Copper recovery (%) - 83.3% 79.9% 85.1% 82.9%

Copper in concentrate produced (tonnes) - 1,106 22,099 31,777 54,983

3

Combined Phase 1, 2 and 3

Ore tonnes milled (000’s tonnes) 2,061 2,381 3,266 3,655 11,362

Copper ore grade processed (%) 4.80% 4.91% 4.14% 4.26% 4.46%

Copper recovery (%) 87.4% 86.9% 85.3% 86.6% 86.5%

Copper in concentrate produced (tonnes) 86,117 100,812 116,313 133,819 437,061

Numbers in red denote a quarterly record

During the month of December, Kamoa-Kakula delivered record production of

47,058 tonnes of copper in concentrate. The Phase 3 concentrator milled at an

annualized rate of 5.7 million tonnes per annum during the month, 13% above

design capacity, and achieved an average recovery rate of 86.6%, in line with

design parameters.

Kamoa-Kakula’s high- and medium-grade ore surface stockpiles totaled

approximately 4.19 million tonnes at an estimated, blended average grade of

3.18% copper. Contained copper in the stockpiles at the end of December totaled

approximately 133,000 tonnes.

At year-end, there were approximately 30,000 tonnes of unsold copper in

inventory, up from 16,000 tonnes of unsold copper in concentrate at the end of

the third quarter. The inventory of unsold copper is largely undergoing toll

treatment at Lualaba Copper Smelter (LCS) and is expected to reduce during the

first quarter.

Figure 1: Kamoa-Kakula’s monthly growth in 2024 copper production

4

Figure 2: Kamoa-Kakula’s total annual copper production growth since first

production in May 2021.

A limited portion of Kamoa-Kakula’s on-site back up generator

capacity damaged by fire; expedited repairs underway

On January 2, 2025, a fire occurred at an on-site generator bank near the Kakula

operations. The fire was rapidly contained and extinguished by Kamoa-Kakula’s

emergency response team. There were no injuries reported, no damage to other

infrastructure, and production operations were not impacted.

Prior to the fire, Kamoa-Kakula had over 190 megawatts (MW) of on-site diesel-

generated back up power installed, supplementing the grid-supplied domestic

and imported hydroelectric power. On-site back up power increased during the

fourth quarter, following the installation of 48 MW of new diesel-generated power.

36 MW of Kamoa-Kakula’s onsite, diesel-generated back up power was damaged

by the recent fire. Initial estimates indicate that 34 MW, out of the total 36 MW of

damaged capacity, are repairable. It will take between three and six months to

return the back up units to operation. An insurance claim will be made based on

existing policies in place. A full assessment of the damage is expected to be

completed within the coming weeks.

Kamoa-Kakula’s engineering team is conducting a full investigation into the

cause of the fire to assess the need for additional preventative measures across

the generator farms. In the meantime, surveillance of the back up generators has

increased, including the deployment of dedicated fire crews at each bank of

generators.

105,884

333,500

393,551

437,061

FY2021 FY2022 FY2023 FY2024

5

Approximately 160 MW of diesel-generated back up power remains available,

which is distributable across the Kakula and Kamoa operating sites. Currently,

Kamoa-Kakula is drawing 90 MW of domestic and imported hydropower. Kamoa-

Kakula’s management are in discussions to secure increased domestic and

imported hydropower as soon as possible. Even in the extremely unlikely event

that all grid-supplied power were to completely fail, there is sufficient onsite back

up generator capacity available to run Kamoa-Kakula’s Phase 1, 2, and 3

operations, excluding the smelter.

Total power required to operate the Phase 1, 2, and 3 operations, as well as the

smelter at full capacity, is approximately 240 MW. Kamoa-Kakula’s smelter

operations team is considering delaying the heat-up of the on-site copper smelter

by up to three months, while the damaged generators are being repaired or

additional domestic or imported hydropower is secured.

In addition, wet commissioning of Turbine #5 at Inga II, with a hydroelectric

generation capacity of 178 MW, is now expected to commence in the second

quarter. Kamoa-Kakula is expected to be allocated an initial, additional 70 MW of

hydropower from the grid in the second quarter, which will increase over time to

178 MW as grid improvement initiatives are completed.

The blasting and painting team from Prezioso Congo SA inside the spiral

case of the new 178-MW Turbine #5 at Inga II hydroelectric facility.

6

In December, the new turbine runner was lowered into place and installed

inside Turbine #5 at Inga II. Wet commissioning of Turbine #5 at Inga II is

expected to commence in the second quarter and will provide Kamoa-

Kakula with 178 MW of clean, hydropower by year-end.

Ivanhoe Mines exploring options for future hydropower imports from

Angola

On July 4, 2024, Trafigura Group of Geneva, Switzerland and ProMarks of Luanda,

Angola signed a Memorandum of Understanding (MOU) with the Government of

Angola to study the technical and economic viability of building a 2,000 MW high-

voltage electricity “interconnector” (a high-voltage direct current transmission

line) to export surplus green electricity to the DRC Copperbelt and Zambia. The

project enables electricity generated by hydroelectric dams located in the north

of Angola to be connected to the Southern Africa Power Pool. A joint venture will

be formed between ProMarks and Trafigura to develop, finance, construct and

operate the electricity “interconnector”. The project is intended to be financed

through a combination of equity capital and third-party debt. Planning, approvals

and construction would take around four years after the final investment decision

is made.

7

Kipushi produced 50,307 tonnes of zinc during inaugural year,

including a monthly record 14,900 tonnes in December as ramp-up

approaches nameplate capacity

In 2024, the Kipushi concentrator milled 228,293 tonnes of ore at an average

grade of 29% zinc, producing 50,307 tonnes of zinc in concentrate at a grade of

approximately 50%.

Following slower than anticipated ramp up progress in the third quarter,

operations at the Kipushi concentrator significantly improved during the fourth

quarter, with several processing records achieved. 135,285 tonnes of ore were

milled at an average grade of 28%, producing a record 32,323 tonnes of zinc. This

includes a record 14,900 tonnes produced during December, which is equivalent

to an annualized production rate of approximately 175,000 tonnes of zinc.

In addition, during the last day of the year, a record 750 tonnes of zinc were

produced over 24 hours, exceeding nameplate capacity. Over the same period,

2,200 tonnes of ore were milled by the concentrator, in line with the design rate.

The Kipushi concentrator is expected to consistently achieve its nameplate

milling rate during the first quarter.

At the end of December, Kipushi’s high- and medium-grade ore surface

stockpiles totaled approximately 344,000 tonnes at an estimated average grade of

23% zinc. Contained zinc in the stockpiles totaled approximately 79,500 tonnes.

Kipushi’s 800,000 tonnes per annum concentrator set several milling and

production records in December 2024.

8

2025 Production Guidance

Ivanhoe Mines’ 2025 production guidance is based on several assumptions and

estimates as of December 31, 2024. The guidance provided involves estimates of

known and unknown risks, uncertainties, and other factors that may cause the

actual results to differ materially.

In recent months, imported power available to Kamoa-Kakula has been reduced

due to drought conditions affecting hydroelectric capacity in Zambia and

Mozambique. Although the rainy season has begun, it is too early to predict the

degree to which reservoirs that provide hydropower in Zambia and Mozambique

will be recharged. Given this uncertainty, 2025 production guidance will be

reviewed at the end of the rainy season in the second quarter.

Kamoa-Kakula is targeting a production rate of approximately 600,000 tonnes of

copper in concentrate for 2026, following power generation and grid improvement

initiatives in progress, together with optimization projects for improved Phase 1

and 2 recoveries (Project 95) and increased Phase 3 throughput underway.

Kipushi is targeting a production rate of over 250,000 tonnes of zinc in

concentrate for 2026, following the completion of ramp-up and debottlenecking

activities targeted for Q3 2025.

Ivanhoe Mines will provide C1 cash cost (C1) per pound of payable copper and

payable zinc guidance for 2025 in its 2024 year-end financial results release.

Guidance on Platreef’s production and C1 cash costs will be provided after ramp-

up, which is expected to commence in H2 2025.

2025 Production Guidance

Kamoa-Kakula 520,000 – 580,000 Contained copper in concentrate (tonnes)

Kipushi 180,000 – 240,000 Contained zinc in concentrate (tonnes)

All figures are on a 100%-project basis and metal reported in concentrate is before refining losses or

payability deductions associated with smelter terms.