Ivanhoe Mines files new NI 43-101 technical report for the Platreef palladium, rhodium, nickel, platinum, copper and gold project in South Africa

Resource Estimates Technical Reports (NI 43-101)

March 11, 2022

Ivanhoe Mines files new NI 43-101 technical report

for the Platreef palladium, rhodium, nickel, platinum, copper and

gold project in South Africa

MOKOPANE, SOUTH AFRICA – Ivanhoe Mines (TSX: IVN; OTCQX: IVPAF) announced today

that the company has filed a new National Instrument 43-101 (NI 43-101) technical report

covering the Platreef 2022 Feasibility Study.

The updated NI 43-101 technical report includes an independent feasibility study for the initial

two phases of development for the Platreef Mine to a steady state production rate of 5.2 million

tonnes of ore per annum.

The Platreef 2022 Feasibility Study Technical Report was independently prepared by OreWin

Pty Ltd. of Adelaide, Australia; Mine Technical Services of Reno, USA; SRK Consulting Inc. of

Johannesburg, South Africa; DRA Global of Johannesburg, South Africa; and Golder

Associates Africa of Midrand, South Africa.

Ivanhoe Mines indirectly owns 64% of the Platreef Project through its subsidiary, Ivanplats,

and is directing all mine development work. The South African beneficiaries of the approved

broad-based, black economic empowerment structure have a 26% stake in the Platreef

Project. The remaining 10% is owned by a Japanese consortium of ITOCHU Corporation;

Japan Oil, Gas and Metals National Corporation; ITC Platinum Development Ltd., an ITOCHU

affiliate; and Japan Gas Corporation.

The technical report titled “Platreef 2022 Feasibility Study” has been filed on the SEDAR