Ivanhoe Mines files an updated NI 43-101 technical report for the Kamoa-Kakula Copper Project
March 22, 2019
Ivanhoe Mines files an updated NI 43-101 technical report
for the Kamoa-Kakula Copper Project
VANCOUVER, CANADA – Ivanhoe Mines (TSX: IVN; OTCQX: IVPAF) announced today that,
further to its news release of February 6, 2019, the company has filed an updated National
Instrument 43-101 (NI 43-101) technical report covering the independent pre-feasibility studies
for the development of the Kakula and Kansoko copper mines at the Kamoa-Kakula Project in
the Democratic Republic of Congo (DRC).
The technical report also includes an updated, expanded preliminary economic assessment for
the overall integrated development plan for the Kamoa-Kakula Project.
The Kamoa-Kakula Copper Project is a joint venture between Ivanhoe Mines, Zijin Mining
Group, Crystal River Global Limited and the DRC government. All figures in the NI 43-101
technical report are on a 100%-project basis unless otherwise stated.
The NI 43-101 technical report was independently prepared by OreWin Pty Ltd. of Adelaide,
Australia; Amec Foster Wheeler E&C Services Inc. (a division of Wood PLC) of Reno, USA;
SRK Consulting Inc. of Johannesburg, South Africa; KGHM Cuprum R&D Centre Ltd. of
Wroclaw, Poland; Stantec Consulting International LLC of Arizona, USA; DRA Global of
Johannesburg, South Africa; Golders Associates of Vancouver, Canada and Johannesburg,
South Africa; and Epoch Resources (Pty) Ltd. of Johannesburg, South Africa.
The report – titled Kamoa-Kakula Integrated Development Plan 2019 – has been filed on
the SEDAR website at www.sedar.com and on the Ivanhoe Mines website at
www.ivanhoemines.com.
Information contacts
Investors
Bill Trenaman +1.604.331.9834
Media
North America: Kimberly Lim +1.778.996.8510
South Africa: Jeremy Michaels +27.82.772.1122
Website www.ivanhoemines.com