Saturday, September 26, 2026
MiningNewsTerminal
Saturday, September 26, 2026 Admin

IVN.TO ·

Ivanhoe Mines completes construction of Kipushi concentrator ahead of schedule

Mine Development & Operations

July 2, 2024

Ivanhoe Mines completes construction of Kipushi concentrator

ahead of schedule

■

First ore to Kipushi concentrator achieved on May 31; first

concentrate produced on June 14

■

Kipushi sets 2024 production guidance at between 100,000 and

140,000 tonnes of zinc in concentrate

■

Kipushi zinc production capacity to average 278,000 tonnes

per annum over first five years, making Kipushi the fourth-

largest zinc mine globally

■

Basic engineering underway to increase processing capacity

of concentrator by 20% to 960,000 tonnes per annum

■

Off-take agreements signed with CITIC Metal and Trafigura,

plus $170 million in financing facilities agreed

■

Kipushi reconfirmed as the world’s lowest carbon-emission

intensive zinc mine on a Scope 1 and 2 basis

KIPUSHI, DEMOCRATIC REPUBLIC OF CONGO – Ivanhoe Mines (TSX: IVN;

OTCQX: IVPAF) Executive Co-Chair Robert Friedland and President Marna Cloete

announce today the completion of construction and the restart of the historic

ultra-high-grade Kipushi zinc-copper-lead-germanium mine in the Democratic

Republic of the Congo (DRC), 100 years after it first operated, and 31 years since

it was placed on care and maintenance. First feed of ore into the new

concentrator was achieved on May 31, 2024, with first concentrate subsequently

produced on June 14, 2024.

Off-take agreements for Kipushi’s high-grade zinc concentrate have been signed

with CITIC Metal (HK) Limited of Hong Kong and Trafigura Asia Trading of

Singapore. Further off-take agreements are expected to be signed in the coming

months. In addition, financing facilities totaling $170 million provided by CITIC

2

Metal, Trafigura and First Bank DRC of Kinshasa, DRC have been arranged, with

$50 million drawn to date.

Kipushi Corporation SA (KICO) is 68% owned by Kipushi Holding, a wholly owned

subsidiary of Ivanhoe Mines, with the remaining 32% of KICO owned by

Gécamines. As per the terms of the Joint-Venture Agreement between Kipushi

Holding, KICO, and Gécamines, as announced on January 16, 2024, Gécamines

will acquire an increasing percentage of the share capital and voting rights in

KICO over time, subject to completing conditions precedent.

Watch a video showing the completion of the Kipushi concentrator

and production of first concentrate:

https://vimeo.com/960461099/60827dd468?share=copy

Ivanhoe Mines’ Founder and Executive Co-Chairman Robert Friedland

commented:

"Returning the historic Kipushi zinc-copper-lead-germanium-gallium mine to

production alongside our DRC state-owned joint-venture partner Gécamines

marks a century after Kipushi’s first operations. The rebirth of the mine is a major

and state-of-the-art achievement for our operations team, the people of the

Democratic Republic of the Congo and the local community in Kipushi Town. We

commend and congratulate everyone involved, especially the hardworking

Congolese workforce, for their exceptional contributions towards this example of

industry-leading execution ... with the construction and first concentrate

milestones delivered substantially ahead of schedule. Kipushi will be one of the

3

world's leading producers of high-grade, low-emissions zinc and associated

metals. The mine will follow Kamoa-Kakula's example of being a leading employer

and social driver for the region where we operate while maintaining Ivanhoe's

focus on strong community relations and sustainability.

"The Kipushi mine is a significant example of the growing importance of the

Democratic Republic of the Congo as a provider of high-quality, vital strategic

minerals for global markets. The mine also demonstrates the tier-one quality of

the ore body and workforce that make the Central African Copperbelt the best

place on our planet to build world-leading mining operations. We are very proud

to witness the rebirth of this legendary mining operation for the first time in three

decades. Kipushi joins Kamoa-Kakula as a major addition to Ivanhoe's rapidly

growing green metals business. We celebrate this significant step on our

aggressive journey to become the world's next great, diversified major mining

company."

Gécamines’ Chairman, Guy-Robert Lukama Nkunzi commented:

“The resumption of operations at the Kipushi Mine, after more than three decades

of inactivity, is a source of great pride for Gécamines and of renewed joy among

the Province of Haut-Katanga’s population. This outcome is yet another

indication of Gécamines’ efforts for the revival of mining activity and community

development in Haut-Katanga.

“It is not only high zinc grades that make Kipushi an extraordinary mine. Whilst at

this stage only the Big Zinc deposit has been certified, the mine shows great

potential for other metals that are critical to meet today’s global industrial needs.

Through the renewed KICO project, achieved in cooperation with our partner

Ivanhoe Mines, whose unwavering commitment and expert skills led to the site’s

revival, Gécamines will be in a position to play a greater role than in the past.

Concurrently with the mine’s reconstruction, our partnership has been

significantly restructured in terms of the project’s governance. As a result,

Gécamines’ shareholding in the project has been reinforced, which gives us

increased power to influence key decisions, the possibility of acquiring KICO’s

products to ensure local processing and, above all, the prospect of becoming a

majority shareholder again after the Big Zinc is depleted.

“All of these achievements are in line with the wish of His Excellency the

President of the Republic, Mr Félix-Antoine Tshisekedi Tshilombo, that the

Democratic Republic of Congo enters into balanced mining partnerships that will

make our country a key player in the revolutionary transition to green energy.”

4

(L-R) Ivano Manini, General Manager, KICO; Olivier Binyingo, Executive

Vice President, DRC, Ivanhoe Mines and Chairman, KICO; and, Gaetan

Luabeya, Deputy General Manager, KICO holding first concentrate from the

Kipushi Concentrator on June 14, 2024.

The Kipushi ball mill rotating with the first feed of ore during the night of

May 31, 2024, with the historic, headframes (P1, P2 and P3) in the

background. The restart of the Kipushi mine has taken place 100 years

after it was originally opened, in 1924.

5

2024 Production Guidance for the Kipushi Mine

Kipushi’s 2024 production guidance is based on several assumptions and

estimates as of July 2, 2024, including among other things, assumptions about

the timing of ramp-up of the new 800,000-tonne-per-annum Kipushi concentrator.

Guidance involves estimates of known and unknown risks, uncertainties and

other factors that may cause the actual results to differ materially.

Kipushi Mine 2024 Guidance

Contained zinc in concentrate (tonnes) 100,000 - 140,000

All figures are on a 100%-project basis and metal reported in concentrate is before treatment losses or

payability deductions associated with smelter terms.

Ivanhoe Mines will provide 2024 guidance ranges for C1 cash cost (C1) per pound

of payable zinc once ramp-up to steady-state production has been achieved.

As per the 2022 Kipushi Feasibility study, released on February 14, 2022, over the

first five years annualized production is expected to average 278,000 tonnes of

zinc in concentrate, positioning Kipushi as the world’s fourth-largest zinc mine

and the largest on the African continent. See Figure 1.

Figure 1. World’s top 10 zinc mines estimated for 2025, by paid zinc

production per annum (‘000 tonnes) with head grade (% zinc).

Source: Wood Mackenzie, 2024, Ivanhoe Mines. Production and grade assumptions for Kipushi are the

first five-year average as stated in the 2022 Feasibility Study.

0.0%

5.0%

10.0%

15.0%

20.0%

25.0%

30.0%

35.0%

40.0%

0

100

200

300

400

500

600

Zn Head Grade %

Paid Zn Production Kt

Paid Zn Production

Head Grade

6

Dry commissioning of the new 800,000-tonne-per-annum Kipushi concentrator

commenced in early May, with first ore from the surface run-of-mine (ROM)

stockpiles fed through the ball mill during the evening of May 31, 2024. The first

batch of concentrate production was achieved on June 14, 2024. Ramp-up to

steady-state production is expected in the third quarter.

Basic engineering underway to increase processing capacity of

Kipushi concentrator by 20% to 960,000 tonnes per annum

Basic engineering of a de-bottlenecking program is underway, targeting a 20%

increase in processing capacity of the newly constructed Kipushi concentrator.

The debottlenecking program is expected to increase the processing capacity to

960,000 tonnes per annum. Since mining commenced in late 2023, there is

sufficient capacity to increase mining and hoisting rates to support an upsized

concentrator. The de-bottlenecking program is expected to take approximately

nine months, based on the ready availability of equipment.

Run-of-mine stockpiles to support ramp-up to steady-state

production, with mining rates to increase throughout H2 2024

As of June 30, 2024, a total of approximately 336,000 tonnes of ore at an average

grade of 23.4% zinc was stored in surface ROM stockpiles adjacent to the Kipushi

concentrator. This includes approximately 150,000 tonnes of “high-grade” ore at

an average grade of over 30% zinc. The stockpiled ore, which contains nearly

80,000 tonnes of zinc that is currently trading at approximately $3,000 per tonne,

is now being used for the ongoing hot commissioning and ramp-up of the Kipushi

concentrator.

Underground mining rates are expected to significantly increase throughout the

second half of the year to match the steady-state processing rate of the Kipushi

concentrator. Year-to-date underground mining rates have averaged just over

20,000 tonnes per month, with rates expected to increase to 75,000 tonnes per

month, at an average grade of over 40% zinc, by year-end.

Off-take agreements for Kipushi concentrate signed, plus $170 million

in financing facilities secured

Ivanhoe Mines has recently established a wholly-owned subsidiary, Ivanhoe

Marketing (Pty) Ltd (“Ivanhoe Marketing”), to manage the in-land logistics across

the African continent. Ivanhoe Marketing will be responsible for arranging the

transportation of zinc concentrate from mine gate to the point of delivery. Initially,

it is expected that approximately 50% of Kipushi’s concentrate will be delivered to

Europe for smelting on a Cost, Insurance and Freight (CIF) basis, exported via the

port of Walvis Bay. The remaining 50% will be a Delivered at Place (DAP) to the

port of Durban.

7

Ivanhoe Marketing has entered into off-take agreements with CITIC and Trafigura

for the sale of Kipushi concentrate. The Kipushi concentrate is expected to

contain approximately 55% zinc, with low levels of impurities. To date, off-take

agreements for approximately two-thirds of Kipushi’s zinc concentrates over a

five-year term have been agreed. The off-take agreements contain standard,

international commercial terms, including payables and treatment charges based

on the zinc industry’s annual benchmark. The 2024 annual treatment charge

benchmark is currently $165 per tonne of concentrate. Given an international

shortage of clean zinc concentrates to feed the world’s zinc smelters, the current

spot rate for zinc treatment charges is significantly lower than the $165 per tonne

benchmark rate. Off-take agreements for the remaining concentrate are expected

to be placed in the coming months.

In addition to the off-take agreements, Trafigura and CITIC Metal will each provide

a loan facility to KICO for $60 million over the term of the off-take contract, at a

rate of interest SOFR, plus 6%. A bank facility has also been signed with

domestic lender FirstBank DRC for $50 million at SOFR plus 4.5%.

Kipushi is the world’s lowest carbon-emitting major zinc mine on a

Scope 1 and 2 basis

2023 Scope 1 & 2 zinc GHG emissions intensity curve, highlighting Kipushi

and the top 10 largest zinc mining operations in 2023.

Notes: Kipushi and industry peer Scope 1 and 2 GHG emissions data are estimates by Skarn Associates. Estimates

include all direct and indirect emissions to produce contained zinc from ore to mine gate. The horizontal width of each

bar represents the quantity of each operation’s 2023 zinc production in ‘000 tonnes. 2025 Kipushi production is

estimated to be 278,000 tonnes of payable zinc in concentrate, based on the 2022 feasibility study. 2025 zinc

production is not forward guidance. It is estimated that operations will emit a total of 5,047 equivalent tonnes of CO2,

thereby producing 0.019 equivalent tonnes of CO2 per tonne of zinc produced. Chart sources: Skarn Associates,

Ivanhoe Mines.

8

The updated Greenhouse Gas emissions assessment recently completed by

Skarn Associates confirms that Kipushi will be the lowest carbon emitter per unit

of zinc production in the world.

The fact that Kipushi will be the lowest greenhouse gas emitter per tonne of zinc

produced is partially due to the ultra-high-grade Big Zinc orebody, which has an

average head grade of over 36% zinc over the first five years of operation. The

Kipushi head grade is more than 6.5 times higher than the average head grade of

the top 20 zinc mining operations in 2023. A high head grade means significantly

less rock is mined, hauled and milled for the same tonne of zinc produced. The

total peak power required by the mining and milling operation is only 23

megawatts (MW).

The low carbon emissions intensity is also a function of the DRC grid being

among the world’s cleanest, with 99.5% of grid power generated from

hydroelectricity, according to the U.S. Energy Information Administration.

On a Scope 1 and 2 basis (reported from ore to mine gate), Kipushi’s greenhouse

gas (GHG) emissions intensity for 2025 is expected to be 0.019 equivalent tonnes

of carbon dioxide per tonne of contained zinc produced (t CO2-e / t Zn). This

comfortably ranks Kipushi near the bottom of the Scope 1 and 2 GHG emissions

curve, as shown in Figure 1. For comparison, the 2022 Scope 1 and 2 GHG

emissions intensity for Kamoa-Kakula, which is the lowest carbon-intensive

major copper mine globally, was 0.16 equivalent tonnes of carbon dioxide per

tonne of contained copper produced (t CO2-e / t Cu).

Industry-leading health and safety performance achieved during the

construction of Kipushi

During the 3.3 million man-hours worked on the construction of the Kipushi

concentrator, not a single lost time injury (LTI) was recorded. Therefore, the lost

time injury frequency rate (LTIFR) for the concentrator during construction was

zero. The recently completed Phase 3 concentrator at Kamoa-Kakula also

completed construction with an LTIFR of zero, a rare industry achievement.

Zinc’s role is vital in supporting the energy transition

Zinc’s primary use is for protecting steel against corrosion, which accounts for

over 60% of the metal’s worldwide use. In 2023, according to Worldsteel data,

global crude steel production was approximately 19 billion tonnes. Zinc’s use in

the energy transition is primarily in the generation and transmission

infrastructure, as well as in the emerging battery storage technology.

Zinc is vital in the protection of solar panel fixtures and wind turbine structures

from extreme weather and in preventing rust. Each 100 MWh solar installation is

estimated to use approximately 230 tonnes of zinc and each 100 MWh offshore

wind turbine installation is estimated to require approximately 40 tonnes of zinc.