Ivanhoe Mines completes construction of Kamoa-Kakula’s Phase 3 concentrator ahead of schedule and on budget

Mine Development & Operations

May 28, 2024

Ivanhoe Mines completes construction of Kamoa-Kakula’s

Phase 3 concentrator ahead of schedule and on budget

■

First ore to Phase 3 concentrator achieved on May 26; first

Phase 3 concentrate expected in early June

■

Phase 3 concentrator increases Kamoa-Kakula copper

production capacity to more than 600,000 tonnes per annum,

making Kamoa-Kakula the fourth-largest copper mining

complex globally

■

Further Kamoa-Kakula growth initiatives in progress, including

Project 95, de-bottlenecking of Phase 3 and potential

acceleration of Phase 4 expansion

■

Zero lost-time injuries recorded during the construction of the

Phase 3 concentrator

■

Phase 1 and 2 concentrators produced more than 63,000

tonnes of copper since start of April; a significant improvement

resulting from improved power stability

■

Kamoa-Kakula’s 2024 production guidance maintained at

440,000 to 490,000 tonnes of copper in concentrate

KOLWEZI, DEMOCRATIC REPUBLIC OF CONGO – Ivanhoe Mines (TSX: IVN;

OTCQX: IVPAF) Executive Co-Chair Robert Friedland and President Marna Cloete

announce today that on May 26, 2024, first ore was fed into the Phase 3

concentrator at the Kamoa-Kakula Copper Complex in the Democratic Republic of

the Congo (DRC). First ore marks the completion of construction of the Phase 3

concentrator, which has been achieved months ahead of schedule and also on

budget. First concentrate is expected in early June, while ramp-up to commercial

production is targeted for early in the third quarter.

2

Ivanhoe Mines’ Founder and Executive Co-Chairman Robert Friedland

commented:

“The Kamoa-Kakula operations team continues its industry-leading execution

with the early and on-budget delivery of the Phase 3 concentrator and

underground mining operations ... a rare feat in an industry plagued by cost

overruns and delays when it comes to complex, world-scale projects. Meanwhile,

we have experienced much-improved power stability over the second quarter

following our team's proactive response to grid instability experienced in the

southern DRC grid. As a result, we've seen materially higher head grades and

improved production over the past two months. We expect a stronger second

quarter from Kamoa-Kakula's operations, reinforcing our confidence that

production will align with annual guidance.

“Given the outperformance of Kamoa-Kakula's operations to date, including

higher than expected throughput and recoveries at the Phase 1 and Phase 2

concentrators, we are now studying options to boost copper production towards

our next goal of 800,000 tonnes per annum ... a production rate that would propel

the Kamoa-Kakula Copper Complex towards being one of the two largest copper

producers on our planet. In addition to the de-bottlenecking of the Phase 3

concentrator and increasing recoveries to 95% via our 'Project 95' initiative, we

are now also studying options to accelerate the Phase 4 expansion at Kamoa-

Kakula to target a throughput rate of at least 20 million tonnes annually. Given the

current copper market, and the expansive copper resources and reserves in

proximity of the milling complex, we believe this expanded throughput rate would

unlock substantial value for our stakeholders and shareholders in the near and

long term.

“It is only early days in terms of the broader copper growth story at Ivanhoe

Mines, with our aggressive 70,000-metre drill program at our adjoining, majority-

owned Western Foreland licenses … which is now ramping up into the dry

season with 10 drill rigs active. Given that our current Western Foreland

resources already total nearly 5 million tonnes contained copper, we also intend

to assiduously advance the Makoko, Kiala and Kitoko discoveries towards early

production to underpin the further expansion of our copper business.”

3

Kamoa-Kakula celebrated the first feed of ore into the ball mills of the new

Phase 3 concentrator on May 26, 2024.

Kamoa Copper’s projects and operations team standing in front of the new

Phase 3 concentrator. The Phase 3 operations team have been trained on

Phase 1 and 2 concentrators, which have a similar process design.

4

The Phase 3 concentrator will process ore from the adjacent Kamoa 1 and 2

underground mines, as well as the connecting Kansoko underground mine. The

design capacity of the Phase 3 concentrator is 30% larger than the original design

capacities of the Phase 1 and 2 concentrators, which are located approximately

10 kilometres to the south. The process design of all three concentrators is

comparable, therefore the bulk of the equipment is the same or similar, resulting

in a commonality of spare parts, while also leveraging operational and

maintenance experience.

The Phase 3 concentrator increases the total design processing capacity of the

Kamoa-Kakula Copper Complex to 14.2 million tonnes per annum (Mtpa). Phase 3

is expected to increase annualized copper production to more than 600,000

tonnes, positioning Kamoa-Kakula as the world’s fourth-largest copper mining

complex, and the largest copper mine on the African continent. See Figure 1.

Figure 1. World’s top 10 copper mines estimated for 2025, by paid copper

production per annum

Source: Wood Mackenzie, 2023 (based on public disclosure and the Kamoa-Kakula Phase 3 annualized

production estimate of approx. 600,000 tonnes copper. (The Kamoa-Kakula data has not been reviewed

by Wood Mackenzie).

As of April 30, 2024, a total of 2.25 million tonnes of ore at a grade of 3.1% copper

is stored in surface run-of-mine (ROM) stockpiles adjacent to the Phase 3

concentrator. The stockpiled ore from the Kamoa 1 and Kansoko mines,

containing approximately 70,000 tonnes of copper, with the copper price trading

at well over $10,000 per tonne, is being used to de-risk the ongoing wet

commissioning and ramp-up of the new 5-Mtpa concentrator.

0

200

400

600

800

1,000

1,200Paid Copper Production (kt)

5

Dry commissioning commenced in early April, with first ore from the ROM

stockpiles being fed through the front-end (crushing and screening plant) of the

Phase 3 concentrator. A crushed ore stockpile has been created on the high-

pressure grinding rolls (HPGR) feed stockpile area, at the end of the crushing and

screening circuit. Wet commissioning commenced with first feed into the ball

mills and the flotation plant on May 26. First concentrate is expected to be

produced in early June, with commercial production targeted for early in the third

quarter.

Concentrate produced by the Phase 3 concentrator will be partially sold (via toll-

smelting at the Lualaba Copper Smelter) to generate cash flow, as well as

partially stockpiled in preparation for the commissioning of the on-site, direct-to-

blister smelter. Concentrate produced by the Phase 3 concentrator has a higher

sulphur content than the Phase 1 and 2, which requires less external energy input

into the smelter during start-up. Approximately, 70,000 tonnes of Phase 3

concentrate is planned to be stockpiled on-site ahead of the start-up of the

smelter.

Kamoa-Kakula’s Phase 3 concentrator expansion was completed months

ahead of schedule and will boost production to over 600,000 tonnes of

copper per annum once fully ramped up early in Q3 2024.

6

Kamoa-Kakula’s Phase 3 concentrator has a nameplate throughput of 5

Mtpa. Once ramped-up, study work will commence on de-bottlenecking the

milling circuit. The de-bottlenecking at the Phase 1 and Phase 2

concentrators, completed in February 2023, increased throughput by over

20% above the original design capacity.

Kamoa-Kakula's Phase 3 ROM stockpile. As of April 30, 2024, Kamoa 1 and

Kansoko surface stockpiles adjacent to the Phase 3 concentrator totalled

2.25 million tonnes of ore, at a combined average grade of 3.1% copper.

7

Significant growth opportunities to further increase copper

production with ‘Project 95’, Phase 3 de-bottlenecking program and

accelerating Phase 4 expansion

Basic engineering of the previously announced “Project 95” is expected to be

completed in the coming weeks. Project 95 is an initiative targeting an increased

overall metallurgical copper recovery rate of Kamoa-Kakula’s Phase 1 and 2

concentrators of approximately 95%, up from the current rate of approximately

87%.

Once the Phase 3 concentrator has achieved commercial production, Kamoa-

Kakula’s engineering team will gather operating data with the view to initiating a

de-bottlenecking program to further increase the Phase 3 concentrator

processing capacity above 5 Mtpa. The Phase 1 and 2 concentrators completed a

de-bottlenecking program in February 2023, which increased processing capacity

by approximately 20% above the original design throughput.

Following the completion of Phase 3, and given current market conditions,

Kamoa-Kakula’s engineering team is investigating the acceleration of the

project’s planned Phase 4 expansion. The Phase 4 concentrator will be

positioned adjacent to the Phase 3 concentrator, with a minimum processing

capacity of 5 Mtpa, and will share common infrastructure with Phase 3, including

the front end (crushing and screening plant), which will reduce capital costs.

An updated life-of-mine integrated development plan for the Kamoa-Kakula

Copper Complex, including the Phase 3 expansion, smelter and Project 95, as

well as further optimization initiatives and the planned Phase 4 expansion is

expected to be completed by the end of 2024.

55 MW of imported power significantly improving production from

Phase 1 and 2 concentrators; installation of further on-site backup-

power generation capacity well underway

Since mid-March, 15 megawatts (MW) of imported power have been reliably

supplied to Kamoa-Kakula from Zambia. In addition, since May 1, 2024, an

additional 20 MW of power is being imported from Mozambique via the Zambian

interconnector. The supplemental imported power has had a significant, positive

effect on the stability of Kamoa-Kakula’s operations. Total production from April

1, 2024 to date, totals more than 63,000 tonnes of copper in concentrate. This is a

notable improvement from the first quarter, which was impacted by power

instability. In addition, head grades have improved in the second quarter in part

due to increased underground pumping capacity. Imported power from

Mozambique is expected to increase by a further 20 MW imminently.

8

Kamoa Copper’s engineering team continues to expand its on-site, backup

generation capacity to ensure there is on-site redundancy for the current Phase 1

and 2 operations, as well as mining and concentrator operations for Phase 3.

On-site backup-power generator capacity is scheduled to increase, via a phased

roll-out, to more than 200 MW by the end of 2024. The generator farm sites are

being built adjacent to the Phase 1 and 2 concentrators, and smelter at Kakula, as

well as adjacent to the Phase 3 concentrator at Kamoa.

As of May 27, 2024, 63 MW of on-site backup generation capacity is installed at

Kamoa-Kakula and that is expected to increase to a total of 123 MW by July. Peak

on-site power demand from Phase 1 and 2 operations is approximately 105 MW.

The Phase 3 concentrator will add an additional requirement of approximately 45

MW once fully ramped. In addition, the smelter will require a further 75 MW of

power once fully ramped up throughout 2025.

Industry-leading health and safety performance achieved during the

construction of the Phase 3 concentrator, with zero lost time injuries

During the 10 million man-hours worked on the construction of the Phase 3

concentrator, not a single lost time injury (LTI) was recorded; a rare industry

accomplishment. Therefore, the lost time injury frequency rate (LTIFR) and total

recordable injury frequency rate (TRIFR) for the project were both zero.

Including the smelter and other associated infrastructure projects included in the

Phase 3 expansion, over the total 40-million-man hours worked to date, only four

LTIs have been recorded and nine recordable injuries. The health and safety

performance set by the engineering and contractor teams is industry-leading with

a LTIFR and TRIFR of 0.10 and 0.22 per 1,000,000-man hours worked,

respectively. For comparison, the 2022 International Council on Mining and

Metals (ICMM) mining industry average was 2.66 per 1,000,000 man-hours

worked.