Saturday, September 26, 2026
MiningNewsTerminal
Saturday, September 26, 2026 Admin

IVN.TO ·

Ivanhoe Mines announces results of an independent NI 43-101 preliminary economic assessment (PEA) for expanded production options for its world-scale Kakula and Kamoa copper discoveries in the Democratic Republic of Congo

Economic Studies

November 28, 2017

Ivanhoe Mines announces results of an independent NI 43-101 preliminary

economic assessment (PEA) for expanded production options

for its world-scale Kakula and Kamoa copper discoveries

in the Democratic Republic of Congo

Based on current copper resources, the PEA analyzes an initial, two-stage,

modular, 12 million-tonne-per-annum operation – supplied by two adjacent

six million-tonne-per-annum mines and a direct-to-blister smelter

– yielding an after-tax NPV8% of US$7.2 billion and an IRR of 33%

over a 44-year mine life

An initial six million-tonne-per-annum copper mine at Kakula can

be developed for an estimated US$1.2 billion; subsequent expansions

and smelter can be funded from cash flows or project finance

Combined production of 12 Mtpa would rank Kamoa-Kakula among

the world’s five largest copper mines, with projected annual production

of more than 500,000 tonnes of copper

Ivanhoe to explore acceleration options for building the first two mines

at Kamoa-Kakula concurrently, and the potential for expanding production

to 18 Mtpa and beyond

Development of Kakula being fast-tracked with twin declines now underway;

pre-feasibility study in progress

Kakula’s ultra-high copper grade expected to average 6.4%

over the first 10 years, with mine-site copper cash costs of US$0.51/lb

Ongoing drilling expanding and upgrading high-grade copper resources,

particularly at the Kakula West Discovery

KOLWEZI, DEMOCRATIC REPUBLIC OF CONGO – Ivanhoe Mines (TSX: IVN; OTCQX:

IVPAF) Executive Chairman Robert Friedland and Chief Executive Officer Lars-Eric

Johansson today welcomed the positive findings of an expanded, independent

preliminary economic assessment (PEA) for the development of the Kakula Discovery at

the Kamoa-Kakula Project on the Central African Copperbelt, in the Democratic Republic

of Congo (DRC).

2 

Given the dramatic expansion and upgrading of the copper resources delineated at

Kamoa-Kakula during the past year, the new PEA incorporates potential increased mining

rates that are 50% higher than the rates used in the December 2016 PEA.

The Kamoa-Kakula Project – a joint venture between Ivanhoe Mines, Zijin Mining Group

and the DRC government – has been independently ranked as the world’s largest high-

grade, major copper discovery by international mining consultant Wood Mackenzie.

The three potential development scenarios examined include:

1. Initial mine development scenario. The Kakula 2017 PEA evaluates the development of

a six million-tonne-per-annum (Mtpa) underground mine and surface processing

complex at the Kakula Deposit – a discovery announced in early 2016 – as the

project’s first phase of development.

2. Expanded, two-mine development scenario. The Kakula 2017 PEA also includes an

option for an integrated, 12 Mtpa, two-stage development, beginning with initial

production from the Kakula Mine, to be followed by a subsequent, separate

underground mining operation at the nearby Kansoko Mine, along with the

construction of a smelter.

3. Kamoa 2017 pre-feasibility study (PFS). The Kamoa 2017 PFS evaluates the

development of the Kansoko Mine as a stand-alone six Mtpa underground mine and

surface processing complex that would be supplied with ore from the planned

development of the Kansoko Sud and Kansoko Centrale areas of the Kamoa Deposit,

which were discovered in 2008. The PFS refines the findings of the Kamoa March 2016

PFS, which envisaged a production rate of three Mtpa.

The Kakula 2017 PEA and Kamoa 2017 PFS were independently prepared by OreWin Pty.

Ltd., Amec Foster Wheeler E&C Services Inc., SRK Consulting Inc., Stantec Consulting

LLC, Golder Associates Ltd., KGHM Cuprum R&D Centre Ltd. and DRA Global.

The Kakula 2017 PEA is preliminary in nature and includes an economic analysis that is

based, in part, on Inferred Mineral Resources. Inferred Mineral Resources are considered

too speculative geologically for the application of economic considerations that would

allow them to be categorized as Mineral Reserves – and there is no certainty that the

results will be realized. Mineral Resources do not have demonstrated economic viability

and are not Mineral Reserves.

A NI 43-101 technical report will be filed on SEDAR at www.sedar.com and on the Ivanhoe

Mines website at www.ivanhoemines.com within 45 days of the issuance of this news

release.

While not evaluated in the new PEA, Ivanhoe and Zijin also are exploring potential

options to accelerate future production by building the Kakula and Kansoko mines

concurrently as well as expansions to 18 Mtpa and beyond as exploration progresses at

Kamoa-Kakula and on Ivanhoe’s 100%-owned exploration licences in the Western

Forelands area to the west of Kamoa-Kakula, where drilling recently started.

“Kamoa-Kakula is, without a shadow of a doubt, the most disruptive Tier One copper

project in the world today,” said Mr. Friedland.

3 

“The 12 million-tonne-per-annum development scenario clearly shows the economic

potential for a phased development plan for Kamoa-Kakula to become one of the largest

copper mines in existence. However, we are confident that there are more high-grade

copper discoveries to be made in the area and the ultimate scale of operations at Kamoa-

Kakula will be much larger.

“The exceptionally high copper grades, thickness and continuity of the Kakula Discovery

really distinguish this project from anything we have seen during our 35-plus years in the

industry. These unique characteristics should allow us to build a world-scale copper

mine with an initial capital cost expected to be far lower than other operations of this

size.”

Mr. Friedland noted that today’s PEA announcement does not factor in the Kakula West

Discovery, which is continuing to be expanded at a remarkable rate. The current study

also does not factor in the ongoing drilling programs on new targets at Kamoa-Kakula or

the company’s 100%-owned Western Forelands exploration area. Additional exploration

success could have a significant influence on the size, value and timing of the overall

development plan; as such, the Kamoa-Kakula development plans will be reassessed and

amended as the project moves forward to reflect ongoing exploration results.

“We remain focused on unlocking the full potential of the Kamoa-Kakula copper district

while expediting the development of the initial Kakula Mine.

“The world’s current top copper mines are aging and their head grades are declining.

Given the projected surge in demand for copper from the electric-vehicle revolution and

renewable energy technologies, Kamoa-Kakula will be of significant strategic importance

for auto makers and clean-energy companies looking to secure a long-term, reliable

supply of high-quality copper,” Mr. Friedland added.

Mr. Johansson said that implementation of community-support initiatives are central to

mine-planning considerations. “We will be working with our partners Zijin Mining and the

DRC government in developing Kamoa-Kakula into the world’s next great copper mine,

generating widely shared economic benefits that will help to uplift local communities,

and providing skills training to help ensure that area residents can qualify for the

thousands of meaningful direct and indirect jobs that will be created.

“It is highly unusual by industry standards that, despite being in the early exploration

and engineering phases of a project, Ivanhoe and Zijin are proud to be leading by

example and have invested heavily in community development initiatives. Our joint

efforts include the “KNOW FOR SURE” anti-malaria campaign utilizing revolutionary

technology developed by Fio Corporation of Toronto, Canada. Other initiatives include

fish and chicken farming, agricultural projects, and the construction of schools, roads

and power infrastructure.

“Everyone at Ivanhoe Mines looks forward to showcasing our three mine development

projects – Kamoa-Kakula, Kipushi and Platreef – to investors from around the world as

the official site visit of the 2018 Mining Indaba conference that will be held in Cape Town,

South Africa, in early February 2018. Those interested in attending our site visit should

apply to our investor relations department as soon as possible.”

4 

HIGHLIGHTS

Potential initial six Mtpa mine at Kakula

 The PEA analyzes the potential development of an initial six Mtpa Kakula Mine at the

Kakula Deposit in the southerly portion of the Kamoa-Kakula Project’s discovery area.

For this option, the PEA envisages an average annual production rate of 246,000

tonnes of copper at a mine site cash cost of US$0.45/lb copper and total cash cost of

US$1.08/lb copper for the first five years of operations, and copper annual production

of up to 385,000 tonnes by year four.

 An initial capital cost of US$1.2 billion for this option would result in an after-tax net

present value at an 8% discount rate (NPV8%) of US$4.2 billion. The internal rate of

return of 36.2% and project payback period of 3.1 years confirm the compelling

economics for Kamoa-Kakula’s initial phase of production.

 Kakula benefits from an ultra-high, average feed grade of 6.4% copper over the first 10

years of operations, and 5.5% copper on average over a 24-year mine life.

 A six Mtpa Kakula PFS is underway, with completion targeted for the second half of

2018. Kakula’s surface box cut was completed on October 26 this year. Development

of twin underground declines, similar to those at the nearby Kansoko Mine, has begun

and is expected to take about a year to complete. The first blast for the declines was

completed on November 16.

Modular, integrated potential development of Kakula and Kamoa deposits,

mining a combined total of 12 Mtpa

 The PEA also presents the development of a two-phase, sequential operation on

Kamoa-Kakula’s high-grade copper deposits.

 Initial production would occur at a rate of six Mtpa from the Kakula Mine, before

increasing to 12 Mtpa with ore from the Kansoko Mine. As resources at Kakula and

Kansoko are mined, the PEA envisages that production would begin at Kamoa North

to maintain 12 Mtpa throughput over a 44-year mine life.

 For the two-phase sequential operation, the PEA envisages US$1.2 billion in initial

capital costs. Future expansion at the Kansoko Mine and subsequent extensions

could be funded by cash flows from the Kakula Mine, resulting in an after-tax net

present value at an 8% discount rate (NPV8%) of US$7.2 billion and an internal rate of

return of 33%.

 Under this approach, the PEA also includes the construction of a direct-to-blister flash

copper smelter with a capacity of 690,000 tonnes of copper concentrate per annum to

be funded from internal cash flows. This would be completed in year five of

operations, achieving significant savings in treatment charges and transportation

costs.

 The 12 Mtpa scenario delivers average annual production of 370,000 tonnes of copper

at a total cash cost of US$1.02/lb copper during the first 10 years of operations and

production of 542,000 tonnes by year nine. At this future production rate, Kamoa-

Kakula would rank among the world’s five largest copper mines.

5 

A pre-feasibility study for a six Mtpa mine at Kansoko also has been examined

 In addition to the Kakula PEA, a PFS also has been completed for the development of

a six Mtpa Kansoko Mine at the Kamoa Deposit, the project’s original discovery area.

For this option, the PFS envisages an average annual production rate of 178,000

tonnes of copper for the first 10 years of operations, and annual copper production of

245,000 tonnes by year seven.

 The initial capital cost of US$1.0 billion to develop this mine would result in an after-

tax NPV8% of US$2.1 billion – an increase of 109% compared to the after-tax NPV8% of

US$986 million that was projected in the March 2016 Kamoa PFS. The internal rate of

return is 24%, with a project payback period of five years.

Potential phased mine developments to 18 Mtpa and beyond currently

under evaluation for Kamoa-Kakula

 Ivanhoe is continuing to explore options to increase Kamoa-Kakula production to 18

Mtpa and beyond. In light of the successful step-out drilling at Kakula West, as well as

the potential to find additional resources in high-priority targets located in the

untested parts of the Kamoa-Kakula Project, development plans will be reassessed

and amended as the project moves forward.

Figure 1 describes the potential development scenarios and Figure 2 shows an overview

of deposits included within Kakula 2017 PEA (six Mtpa and 12 Mtpa case) and Kamoa

2017 PFS (six Mtpa).

Figure 1. Kamoa-Kakula PEA long-term development plan.

Figure by OreWin 2017.

6 

Figure 2. Overview of deposits included within Kakula 2017 PEA

(six Mtpa and 12 Mtpa case) and Kamoa 2017 PFS (six Mtpa).

Figure by OreWin 2017.

Summary of the PEA’s key results for an initial Kakula Mine

1. Very-high-grade initial phase of production is projected to have a grade of 7.3%

copper in year four and an average grade of 6.4% copper over the initial 10 years of

operations, resulting in estimated average annual copper production of 284,000

tonnes.

2. Annual copper production is estimated at 385,000 tonnes in year four.

3. Initial capital cost, including contingency, is estimated at US$1.2 billion.

4. Average total cash cost of US$1.14/lb of copper during the first 10 years.

5. After-tax NPV, at an 8% discount rate, of US$4.2 billion.

6. After-tax internal rate of return (IRR) of 36.2%, and a payback period of 3.1 years.

7. Kakula is expected to produce a very-high-grade copper concentrate in excess of 50%

copper, with extremely low arsenic levels.

7 

Key initial projections from the Kakula 2017 PEA

The study assesses the potential development of the Kakula Deposit as a six Mtpa

mining and processing complex. The Kakula mill would be constructed in two smaller

phases of three Mtpa each as the mining operations ramp-up to full production of six

Mtpa. The life-of-mine production scenario provides for 108.4 million tonnes to be mined

at an average grade of 5.48% copper, producing 9.4 million tonnes of high-grade copper

concentrate, containing approximately 11.4 billion pounds of copper.

The economic analysis uses a long-term price assumption of US$3.00/lb of copper and

returns an after-tax NPV at an 8% discount rate of US$4.2 billion. It has an after-tax IRR of

36.2% and a payback period of 3.1 years.

The estimated initial capital cost, including contingency, is US$1.2 billion. The capital

expenditure for off-site power, which is included in the initial capital cost, includes a

US$71 million advance payment to the DRC state-owned electricity company, SNEL, to

upgrade two hydropower plants (Koni and Mwadingusha) to provide the Kamoa-Kakula

Project with access to clean electricity for its planned operations. Mwadingusha is being

upgraded first. The work is being led by Stucky Ltd., of Switzerland; the advance

payment will be recovered through a reduction in the power tariff.

The Kakula 2017 PEA is preliminary in nature and includes an economic analysis that is

based, in part, on Inferred Mineral Resources. Inferred Mineral Resources are considered

too speculative geologically for the application of economic considerations that would

allow them to be categorized as Mineral Reserves – and there is no certainty that the

results will be realized. Mineral Resources do not have demonstrated economic viability

and are not Mineral Reserves.

Key results of the Kakula 2017 PEA for a single six Mtpa mine are summarized in Table 1.

8 

Table 1. Kakula Mine results summary for six Mtpa production.

Item Unit Total

Total Processed

Quantity Milled kt 108,422

Copper Feed Grade % 5.48

Total Concentrate Produced

Copper Concentrate Produced kt (dry) 9,400

Copper Recovery % 86.86

Copper Concentrate Grade % 54.94

Contained Metal in Concentrate Mlb 11,385

Contained Metal in Concentrate kt 5,164

Peak Annual Recovered Metal Production kt 385

10-Year Average

Copper Concentrate Produced kt (dry) 517

Contained Metal in Concentrate kt 284

Mine-Site Cash Cost US$/lb 0.51

Total Cash Cost US$/lb 1.14

5-Year Average

Copper Concentrate Produced kt (dry) 448

Contained Metal in Concentrate kt 246

Mine-Site Cash Cost US$/lb 0.45

Total Cash Cost US$/lb 1.08

Key Financial Results

Peak Funding US$M 1,135

Initial Capital Costs US$M 1,231

Expansion Capital Costs US$M 318

LOM Average Mine Site Cash Costs US$/lb Cu 0.60

LOM Average Total Cash Costs US$/lb Cu 1.23

Site Operating Costs US$/t Milled 61.49

After-Tax NPV8% US$M 4,243

After-Tax IRR % 36.2

Project Payback Period Years 3.1

Initial Project Life Years 24