Ivanhoe Mines Announces Exceptional Results of Independent 2022 Feasibility Study for Tier- one Platreef Palladium, Rhodium, Nickel, Platinum, Copper and Gold Project in South Africa Platreef ranks as world's largest precious metals deposit under development

Economic Studies

Ivanhoe Mines Announces Exceptional Results

of Independent 2022 Feasibility Study for Tier-

one Platreef Palladium, Rhodium, Nickel,

Platinum, Copper and Gold Project in South

Africa

Platreef ranks as world's largest precious metals deposit under development

Phase 1 mine in construction, advancing towards first production in Q3 2024

2022 Feasibility Study yields an after-tax NPV

8%

of US$1.7 billion and IRR of 18.5% at long-term

consensus metal prices

After-tax NPV

8%

of US$4.1 billion and IRR of 29.3% at current spot metal prices

Shaft 2 accelerated to 2027, advancing Phase 2 expansion with annual forecast production of

greater than 590,000 ounces of palladium, platinum, rhodium, gold and more than 40 million

pounds of nickel and copper

2022 Feasibility Study confirms Platreef's potential to be the industry's largest and lowest-cost

primary PGM producer

Fort Lauderdale, Florida--(Newsfile Corp. - February 28, 2022) - Ivanhoe Mines (TSX: IVN) (OTCQX:

IVPAF) Co-Chair Robert Friedland announced today at the 31

st

BMO Global Metals & Mining

Conference that the company's South African subsidiary, Ivanplats, and its partners, welcome the

outstanding positive findings of an independent

Platreef 2022 Feasibility Study

for the tier-one Platreef

palladium, rhodium, nickel, platinum, copper and gold project in South Africa.

The 2022 Feasibility Study provides the blueprint for the ongoing development of Platreef and builds on

the excellent results of the preliminary economic assessment (PEA) for a phased-development scenario

to expedite production, announced in November 2020, alongside the 2020 Feasibility Study. The

Platreef 2022 Feasibility Study is based on a steady state production rate of 5.2 million tonnes per

annum (Mtpa), as well as an accelerated ramp up to steady state through the earlier development of

Shaft 2. The 2022 Feasibility Study is based on the detailed design and engineering scenario first

presented in the 2020 PEA, confirming the viability of a new phased development pathway to fast-track

Platreef into production by Q3 2024.

The Platreef 2022 Feasibility Study first phase of production includes an initial 700,000 tonnes per

annum (700 ktpa) underground mine and 770-ktpa-capacity concentrator, targeting high-grade mining

areas close to the project's recently completed Shaft 1 (Figure 1).

Platreef's Phase 2, 5.2-Mtpa steady state production rate would rank it as the world's fifth largest primary

platinum-group metals (PGM) mine on a palladium equivalent basis, with annual forecast production of

more than 590,000 ounces of palladium, platinum, rhodium and gold, plus more than 40 million pounds

of nickel and copper (Figure 8).

The Platreef 2022 Feasibility Study reflects the initial two phases of development for the Platreef Mine.

Previous studies have demonstrated the resource base for future expansions up to 12 Mtpa, which

would position Platreef among the very largest PGM producing mines in the world (Figure 8).

Watch a new video showcasing Platreef:

https://vimeo.com/682603861/dce81b5e3a

Construction activities at the Platreef Project site, including Shaft 1 on the left, and the hitch-to-collar

advancement for Shaft 2 on the right

To view an enhanced version of this graphic, please visit:

https://orders.newsfilecorp.com/files/3396/115055_dc4a96bb34cc28e8_002full.jpg

Platreef poised to complete journey from tier-one discovery to one of the world's largest and

lowest-cost PGM producers

The Platreef Project, which includes an underground deposit of thick, high-grade PGE-nickel-copper-

gold mineralization discovered by Ivanhoe's geologists, is in the northern limb of the Bushveld Complex

approximately 11 kilometres from Mokopane, and 280 kilometres northeast of Johannesburg.

PGE-nickel-copper-gold mineralization in the northern limb is primarily hosted within the Platreef, a

mineralized sequence which is traced more than 30 kilometres along strike. The Platreef Project is

situated in the southern sector of the Platreef on two contiguous properties, Turfspruit and

Macalacaskop, which comprise, in aggregate, approximately 7,842 hectares. The northernmost

property, Turfspruit, is contiguous with and along strike from Anglo Platinum Limited's Mogalakwena

group of properties and mining operations.

Ivanplats acquired a prospecting permit for Macalacaskop and Turfspruit in February 1998. In 1999,

Ivanhoe began a series of drilling campaigns, totalling more than 726,000 metres, to advance Platreef

from a greenfield exploration project focused on shallow mineralized zones through to focusing on

deeper underground targets. At the height of the drilling campaign, 30 diamond drill rigs were producing

more than 10,000 metres of core a week.

Since 2007, Ivanplats has focused its Platreef exploration and development activities on defining and

advancing the thick, high-grade, down-dip extension of its original discovery at Platreef, now known as

the Flatreef Deposit. In 2012, the Merensky Reef analogue was recognized.

The Flatreef Deposit lies entirely on the Turfspruit and Macalacaskop properties that form part of

Ivanhoe's mining right. The thickness of the mineralized reef (T1 & T2 mineralized zones) intersected in

Shaft 1 is 29 metres, with average grab sample grade of 6.35 grams per tonne (g/t) platinum, palladium

and rhodium plus gold (3PE+Au), ranging up to 9.6 g/t 3PE+Au, as well as significant quantities of nickel

and copper. This thickness is exceptional when compared to the typical, approximately one-metre-thick

reefs being mined elsewhere on South Africa's Bushveld Complex.

A Japanese consortium led by JOGMEC, a Japanese government entity, and including Itochu and Japan

Gas Corporation, acquired a 10% interest in the Platreef Project for approximately US$290 million.

The thick, high-grade, flat-lying Flatreef deposit was discovered in 2010. Ivanplats conducted an

exploration program with 30 drill rigs totalling over 260,000 metres in 2011. Platreef has excellent

exploration upside for further expansion and discovery.

To view an enhanced version of this graphic, please visit:

https://orders.newsfilecorp.com/files/3396/115055_dc4a96bb34cc28e8_003full.jpg

In June 2020, Ivanplats completed the sinking of Platreef's initial shaft, Shaft 1, to its final depth of 996

metres below surface. Shaft 1 is located approximately 450 metres away from a high-grade area of the

Flatreef orebody, which will provide initial mining areas for Phase 1 production in 2024.

The thick Flatreef orebody also is flat-lying, which is ideal for safe, bulk-scale, mechanized mining and

processes optimized for maximum ore extraction. Flatreef is characterized by its high-grade

mineralization and a palladium-to-platinum ratio of approximately 1:1, which is considerably higher than

other PGMs discoveries on the Northern Limb of the Bushveld.

Through phased development, Platreef is projected to become one of the world's largest and lowest-cost

producers of palladium, platinum, rhodium, nickel, copper and gold. The 2022 Feasibility Study

considers Phase 1 and Phase 2 development, including only one third of Platreef's Indicated Resources

above an US$80/tonne Net Smelter Return (NSR) cut-off.

2022 Feasibility Study re-affirms outstanding economics of phased development at Platreef

with an accelerated ramp up to 5.2 Mtpa

Mr. Friedland commented: "The Platreef discovery remains the world's greatest precious metals deposit

under development, with a peerless endowment of palladium, rhodium, platinum, and gold; as well as

highly significant quantities of strategic 'electric' metals such as nickel and copper. These outstanding

economic results define our commitment to advance Platreef to first production, alongside our local

communities and Japanese partners. We are counting down to less than 30 months from now. This

achievement will only mark the first milestone, as we plan to expand this world-scale operation into one

of the largest and lowest-cost, integrated PGM producers on the planet … all while generating

outstanding returns on capital for a major, disruptive mine.

"PGMs have an integral role to play in the global transition to clean technologies, specifically the

adoption of hydrogen energy systems; as well as the international push for lower emissions, which is led

by developed economies … but let us not forget that emerging markets are catching up quickly …

Platreef will be a responsible, industry leading, long-life supplier of palladium, rhodium, nickel, platinum,

copper and gold … as well as a leading economic driver for South Africa. Ivanhoe Mines remains

committed to 're-inventing mining' and will continue to leverage the most sustainable technologies

available … as evidenced by our commitment to zero-emission, battery-powered equipment, and the

adoption of the safest possible tailings method utilizing dry-stack technology, which has the added

benefit of minimizing water consumption.

"Palladium and rhodium have reached all-time highs in recent years, currently trading at approximately

$2,480 an ounce and $18,750 an ounce respectively, as progressively stricter air-quality rules increase

demand for the metals used in vehicle pollution-control devices. Meanwhile, copper and nickel will

continue to realize historic and sustained rallies due to underinvestment in new mine supply and massive

growing demand tied to electric vehicles and global clean-energy initiatives."

Platreef's Indicated Mineral Resources contain an estimated 18.9 million ounces of palladium, 18.7

million ounces of platinum, 3.1 million ounces of gold, and 1.2 million ounces of rhodium (a combined

41.9 million ounces PGMs plus gold), plus 2.4 billion pounds of nickel and 1.2 billion pounds of copper,

at a 2.0 g/t 3PE+Au cut-off.

Platreef's Inferred Mineral Resources contain an additional 23.8 million ounces of palladium, 23.2 million

ounces of platinum, 4.3 million ounces of gold, and 1.6 million ounces of rhodium (a combined 52.8

million ounces PGMs plus gold), plus 3.4 billion pounds of nickel and 1.78 billion pounds of copper, also

at a 2.0 g/t 3PE+Au cut-off.

Mr. Friedland added: "The thick and flat-lying nature of the high-grade mineralization of the Flatreef

deposit allows for the use of state-of-the-art, automated, electric mining machinery, including cutting-

edge battery driven underground vehicles.

"For Ivanhoe Mines, achieving first production at Platreef will mark the next milestone in the journey to

become a new-age, major diversified mining company ..... we intend to build on the achievements of the

Kamoa-Kakula Copper Joint Venture in the Democratic Republic of Congo, and leverage the countless

lessons we have learned during phased development at our tier-one copper asset … and let us not

forget, Platreef still has vast potential to significantly expand the already enormous resource base … as

well as a plethora of new nickel-sulphide exploration opportunities, many of which are near surface."

Phase 1 construction underway, with first production expected in Q3 2024

Detailed engineering studies are underway on the initial 770-ktpa mine and concentrator, in parallel with

the changeover of Shaft 1 into a production shaft, with expected completion in March 2022. First delivery

of the initial battery-electric underground fleet is expected imminently, and the first blast on the 950-metre

level is anticipated in April 2022. The initial underground development focus from Shaft 1 will be the on

the first ventilation raise and ore passes connecting the 750-metre level to the 950-metre level.

Earthworks for the first concentrator are planned to begin in Q2 2022, followed by civil works and the

ordering of long-lead-time items in H2 2022. First ore feed to the concentrator is planned for Q3 2024.

Phase 1 average annual production is estimated at 113,000 ounces (oz.) of platinum, palladium,

rhodium and gold (3PE+Au), plus 5 million pounds of nickel and 3 million pounds of copper.

Figure 1: Production and timeline schematic of Platreef 2022 Feasibility Study.

To view an enhanced version of this graphic, please visit:

https://orders.newsfilecorp.com/files/3396/115055_dc4a96bb34cc28e8_004full.jpg

William Mamashela (left) and William Mello, with local contractor Somuthwa Construction, assisting with

construction of the Platreef Mine.

To view an enhanced version of this graphic, please visit:

https://orders.newsfilecorp.com/files/3396/115055_dc4a96bb34cc28e8_005full.jpg

Shaft 2 commissioning accelerated to 2027, expediting Phase 2 expansion

While the 700-ktpa initial mine is operating using Shaft 1, the sinking of the project's second, larger shaft

(Shaft 2), that drives the Phase 2 expansion to 5.2 Mtpa, will progress at the same time. The 2022

Feasibility Study envisions Shaft 2 equipped for hoisting in 2027, an accelerated schedule by

approximately 18 months compared to the 2020 PEA, coming online just over three years from first

production of Phase 1.

Once Shaft 2 is complete, two 2.2-Mtpa concentrator modules will be commissioned, and the initial

concentrator will be ramped up to its full capacity of 770-ktpa; increasing the steady-state production to

5.2 Mtpa (Figure 1).

The Phase 2 expansion would result in Platreef becoming the world's fifth largest primary platinum-group

metals (PGM) mine on a palladium equivalent basis, with annual forecast production of more than

590,000 ounces of palladium, rhodium, platinum, and gold, plus more than 40 million pounds of nickel

and copper (Figure 6).

Construction at Shaft 2, which now is expected to be commissioned by 2027.

To view an enhanced version of this graphic, please visit:

https://orders.newsfilecorp.com/files/3396/115055_dc4a96bb34cc28e8_006full.jpg

Platreef's immense mineral endowment supports future expansions

The 2022 Feasibility Study considers Platreef's Phase 1 and Phase 2 development, including only one

third of the Indicated Resources above an US$80/tonne Net Smelter Return (NSR) cut-off. If the

remainder of the Indicated Resources were to be converted to reserves, it would provide an opportunity

to massively expand production.

As development of the project progresses, additional drilling from underground will be undertaken with

the goal of increasing the confidence of the current mineral resources, as well as to expand the resource

base. Additional studies will follow up on the previous work that envisaged further phased expansions

based on updated reserves.

Figure 2: World's largest precious metal deposits under development ranked by contained metal in

Measured & Indicated Resources.

To view an enhanced version of this graphic, please visit:

https://orders.newsfilecorp.com/files/3396/115055_dc4a96bb34cc28e8_007full.jpg

Source: Company filings, S&P Global Market Intelligence. Notes: Chart ranks the largest undeveloped

primary palladium, platinum, gold, silver and rhodium projects from the S&P Global Market Intelligence

database based on measured and indicated palladium equivalent resource. Palladium equivalent

calculation includes palladium, platinum, gold, silver and rhodium ounces and has been calculated using

spot price metal price assumptions (February 23, 2022) of US$1,095/oz platinum, US$2,480/oz

palladium, US$18,750/oz rhodium, US$1,909/oz gold and US$24.55/oz silver. Measured and Indicated

resources for Platreef correspond to palladium, platinum, gold and rhodium ounces at a 1 g/t cut-off

grade.

Tshifhiwa Netshirando, Platreef's Production Manager, is focused on equipping Shaft 1 for first

production within just over two years.

To view an enhanced version of this graphic, please visit:

https://orders.newsfilecorp.com/files/3396/115055_dc4a96bb34cc28e8_009full.jpg

Aerial view from February 2022 of current construction at the Platreef site, including Shaft 1 (right) and

progress at Shaft 2 (left).

To view an enhanced version of this graphic, please visit:

https://orders.newsfilecorp.com/files/3396/115055_dc4a96bb34cc28e8_008full.jpg

Platreef will positively transform mining and community development in Limpopo Province

Ivanhoe Mines' President, Marna Cloete, commented: "Ivanhoe Mines is excited to become a disruptive,

cornerstone participant in the future of South Africa's platinum-group-metals mining industry. We have

established a strong strategic foothold on the giant polymetallic Northern Limb of the renowned Bushveld

Complex. We look forward to sharing the benefits of this truly unique orebody with our partners and local

communities, as well as all the people of South Africa … Platreef represents an important, long-life

economic driver for the nation, and we have only just begun to tap into the potential of this amazing

discovery.

"We are pleased to be building the cutting-edge transformation in future underground platinum-group-

metals mining operations in South Africa. We are charting a new path in the empowerment of the local

people in Limpopo Province and in the training of women in the mining industry. We are focused on

creating a vibrant local economy that's not just going to be mining, as we are enabling entrepreneurs to

create and expand a plethora of new businesses.

Dr. Patricia Makhesha, Ivanhoe's Executive Vice President, Sustainability and Special Projects, added:

"The agreement with the Mogalakwena Local Municipality to recycle wastewater is an important

milestone in Platreef's development. Recycling locally treated water is a cost-effective and sustainable

approach to securing water for the Platreef Project."

Ivanhoe Mines indirectly owns 64% of the Platreef Project through its subsidiary, Ivanplats, and is

directing all mine development work. The South African beneficiaries of the approved broad-based,

black economic empowerment structure have a 26% stake in the Platreef Project. The remaining 10% is

owned by a Japanese consortium of ITOCHU Corporation; Japan Oil, Gas and Metals National

Corporation; ITC Platinum Development Ltd., an ITOCHU affiliate; and Japan Gas Corporation.

The Platreef 2022 Feasibility Study was independently prepared by OreWin Pty Ltd. of Adelaide,

Australia; Mine Technical Services of Reno, USA; SRK Consulting Inc. of Johannesburg, South Africa;

DRA Global of Johannesburg, South Africa; and Golder Associates Africa of Midrand, South Africa.

A National Instrument 43-101 technical report will be filed on SEDAR at

www.sedar.com

and on the

Ivanhoe Mines website at

www.ivanhoemines.com

within 45 days of the issuance of this news release.

Platreef's thick mineralization, which will be mined with highly-productive mechanized methods,