Ivanhoe Mines announces completion of Platreef's Production Shaft 1 at the tier-one palladium, rhodium, nickel, platinum, copper and gold project in South Africa

Corporate Updates

May 9, 2022

Ivanhoe Mines announces completion of Platreef's Production Shaft 1

at the tier-one palladium, rhodium, nickel, platinum, copper and gold

project in South Africa

■

Platreef Phase 1 production on schedule for Q3 2024

■

First blast on Platreef’s 950-metre level completed on April 22, lateral

mine development toward Flatreef orebody commences

■

Ivanplats takes delivery of first battery-electric mining fleet, planning of

Platreef’s initial solar power plant well underway

CAPE TOWN, SOUTH AFRICA – Ivanhoe Mines (TSX: IVN; OTCQX: IVPAF) Executive Co-

Chair Robert Friedland and President, Marna Cloete, announced today at the African

Mining Indaba Conference, the completion of the Shaft 1 production changeover at the

company’s tier-one Platreef palladium, rhodium, nickel, platinum, copper and gold

project in South Africa.

Shaft 1 will serve as Platreef's initial production shaft and is approximately 450 metres

away from the first high-grade area of the Flatreef orebody scheduled to be mined during

Phase 1 production. On April 22, 2022, Ivanplats celebrated the first blast at Platreef’s

950-metre level, marking the commencement of lateral mine development, with first

production anticipated in the third quarter of 2024.

Underground mine development will use battery-electric M2C drill rigs and 14-tonne load

haul dumpers being manufactured by Epiroc, a leading mining equipment manufacturer,

at its facilities in Örebro, Sweden. The partnership with Epiroc for emissions-free mining

equipment is an important first step toward reducing the carbon footprint of the mine,

with learnings to be applied across all of Ivanhoe Mines’ operations.

Watch a May video highlighting mine development activites at Platreef:

https://vimeo.com/707495611/caee06c0d1

2

On April 22, 2022, Ivanplats celebrated the first blast on Platreef’s 950-metre level,

marking the commencement of lateral mine development toward the high-grade

Flatreef ore body.

“The completion of changeover is another noteworthy milestone in the growth of Ivanhoe

Mines into a major, diversified miner; one with top ESG credentials and an industry-

leading portfolio of tier-one assets,” said Ms. Cloete. “Given our string of successes at

Kamoa-Kakula, Platreef, Kipushi, and Western Foreland, it is a great time to be part of the

exceptional Ivanhoe team, and continue our track record of delivering world-scale

projects on schedule and on budget. I’m extremely proud of how we all work together to

keep things on the right track.”

“Platreef is very scalable. The Phase 1 mine is only the beginning of a multi-stage, multi-

generational mining complex underpinned by an enormous, high-grade resource and

vast exploration upside. Future expansions to 12 million tonnes of ore per annum and

beyond, as demonstrated in previous studies, would position Platreef among the world’s

largest and lowest-cost nickel and PGM mines: producing more than 24,000 tonnes of

nickel and 1.1 million ounces of palladium, rhodium, platinum and gold per year. We

expect Platreef to join Kamoa-Kakula in our portfolio as a long-life, leading producer of

critical metals that provides outstanding returns for our shareholders and local

communities.”

3

"Platreef is well on track for historic first PGM and base metal production by the third

quarter of 2024," Mr. Friedland said. "Since acquiring the Macalacaskop and Turfspruit

prospecting permits in 1998, Ivanplats has successfully advanced Platreef to where it is

today – the world's greatest precious metals deposit under development, with a peerless

endowment of palladium, rhodium, platinum, and gold; as well as highly significant

quantities of strategic 'electric' metals such as nickel and copper. We are counting down

to production less than 30 months from now, and this achievement will only mark our

first milestone. We plan to expand this tier-one operation into one of the largest and

lowest-cost, integrated PGM operations on the planet … all while creating a world-scale,

long-life economic driver for South Africa, and generating outstanding returns on capital

for a major, disruptive mine.

"Platreef will align with our goal of 're-inventing mining' and leverage the most

sustainable technologies available … as evidenced by our commitment to zero-emission,

battery-powered equipment, green solar power, and the adoption of the safest possible

tailings method utilizing dry-stack technology, which has the added benefit of minimizing

water consumption. We will build on our achievements at the Kamoa-Kakula Copper

Complex in the Democratic Republic of Congo, and leverage the valuable experiences

from its industry leading phased development model, to build South Africa's next great

PGM complex.

Finally, let us also not forget ... Platreef still has vast potential to significantly expand an

already enormous resource base … as well as a plethora of new nickel-sulphide

exploration opportunities, many of which are near surface.”

Platreef’s Shaft 1 headframe on the left and Shaft 2 construction, raising the

headframe from the hitch to the collar, on the right.

4

Shaft 1 changeover enables underground mining to commence; first blast

on Platreef’s 950-metre level complete on April 22

Three development stations on Shaft 1 have been completed on the 750-, 850-, and 950-

metre levels. Underground development now is focused on completing the mine’s first

ventilation raise, as well as the ore and waste-rock passes connecting the 750-metre level

to the 950-metre level.

With the completion of the first blast on Platreef’s 950-metre level on April 22, 2022,

Ivanplats has started lateral mine development towards the high-grade Flatreef orebody,

which is approximately 450 metres from the 950-metre-level station.

The thick Flatreef orebody is flat lying, which is ideal for safe, bulk-scale, mechanized

mining optimized for maximum ore extraction. Flatreef is characterized by its high-grade

mineralization and a palladium-to-platinum ratio of approximately 1:1, which is

considerably higher than other PGMs discoveries on the Northern Limb of the Bushveld.

Newly designed rock chutes on surface will connect the conveyors feeding the

concentrator plant and the waste-rock area. The waste rock will be crushed and used as

cemented backfill underground for maximum ore extraction, as well as for protection

berms to contain storm water and to reduce noise emissions.

The Ivanplats team preparing for the first blast on Platreef’s 950-metre level.

5

Installation of the conveyor belt for the waste-rock conveyor system leading from

Shaft 1.

Detailed engineering studies are well underway on Platreef’s initial 700,000-tonnes-per-

annum (700-ktpa) mine and concentrator.

Earthworks for the first concentrator plant are planned to begin in the second quarter of

2022, followed by civil works and the ordering of long-lead-time items in the second half

of 2022. First ore feed to the concentrator is planned for the third quarter of 2024.

Phase 1 average annual production is estimated at 113,000 ounces (oz.) of platinum,

palladium, rhodium and gold (3PE+Au), plus five million pounds of nickel and three

million pounds of copper.

Early-works surface construction for Shaft 2, including the excavation of a surface box-

cut to a depth of approximately 29 metres below surface and construction of the concrete

hitch for the 103-metre-tall concrete headframe, has been completed. The Shaft 2

headframe construction, from the hitch to the collar level, is progressing well. Ten civil

lifts are to be constructed in total, including a ventilation plenum and personnel access

tunnel, with targeted completion in May 2022.

6

Shaft 2 headframe construction, from the hitch to the collar level, which is

progressing well.

Ivanplats takes delivery of initial battery-electric vehicles, construction of

first solar power plant now underway

Ivanplats initial order with Epiroc of Stockholm, Sweden, for its primary mining fleet

includes emissions-free, battery-electric jumbo face drill rigs, 14-tonne battery

scooptrams, battery-electric bolting rigs and 42-tonne battery dump trucks. Ivanplats has

received Platreef’s first battery powered underground equipment; a ST14 scooptram and

a Manitou MHTX 790 telehandler, which have successfully been slung down to the 950-

metre level.

Construction of Platreef’s initial solar-power plant is scheduled to commence in August

2022, with commissioning expected in 2023. The solar-generated power from the initial

plant will be used for mine development and construction activities, as well as for

charging Platreef’s battery-powered underground mining fleet.

“Ivanhoe Mines is committed to being an ESG leader and the implementation of electric

vehicles and solar-generated power at Platreef aligns with our goals of limiting emissions

and environmental impacts,” commented Executive Vice President, Technical Services,

Pierre Joubert. “We plan to continue to assess and implement leading-edge renewable

technologies across our world-scale mineral portfolio.”

7

Ivanplats’ first Epiroc ST14 battery Scooptram removing blasted rock from the

initial access drive on the 950-metre level.

2022 Feasibility Study envisions Platreef becoming one of the world's

largest and lowest-cost PGM producers

Platreef’s Phase 2, 5.2-million-tonnes-per-annum steady state production rate would rank

it as the world’s fifth largest primary platinum-group metals mine on a palladium

equivalent basis, with annual forecast production of more than 590,000 ounces of

palladium, platinum, rhodium and gold, plus more than 40 million pounds of nickel and

copper.

The Platreef 2022 Feasibility Study reflects the initial two phases of development for the

Platreef Mine. Previous studies have demonstrated the resource base for future

expansions up to 12 million tonnes per annum.

Through phased development, Platreef is projected to become one of the world’s largest

and lowest-cost producers of palladium, rhodium, nickel, platinum, copper and gold. The

2022 Feasibility Study considers Phase 1 and Phase 2 development, including only one

third of Platreef’s Indicated Resources above an US$80/tonne Net Smelter Return (NSR)

cut-off.

As development and stoping of the project progresses, additional drilling from

underground will be undertaken with the goal of increasing the confidence of the current

mineral resources, as well as to expand the resource base.

8

Riggers Paul Matjekane and Innocent Nchabeleng preparing Platreef's first

battery-electric ST14 Scooptram Loader for delivery to the 950-metre level.

Platreef’s thick mineralization, which will be mined with highly productive mechanized

methods, combined with higher nickel and copper grades, contribute to lower cash costs

compared to other primary platinum-group-metal producers. Among global primary

platinum-group-metals producers, Platreef’s estimated net total cash cost of US$514 per

3PE+Au ounce, net of copper and nickel by-product credits and including sustaining

capital costs, ranks at the bottom of the cash-cost curve.

Platreef’s Indicated Mineral Resources contain an estimated 18.9 million ounces of

palladium, 18.7 million ounces of platinum, 3.1 million ounces of gold, and 1.2 million

ounces of rhodium (a combined 41.9 million ounces PGMs plus gold), plus 2.4 billion

pounds of nickel and 1.2 billion pounds of copper, at a 2.0 g/t 3PE+Au cut-off.

Platreef’s Inferred Mineral Resources contain an additional 23.8 million ounces of

palladium, 23.2 million ounces of platinum, 4.3 million ounces of gold, and 1.6 million

ounces of rhodium (a combined 52.8 million ounces PGMs plus gold), plus 3.4 billion

pounds of nickel and 1.78 billion pounds of copper, also at a 2.0 g/t 3PE+Au cut-off.