Ivanhoe Mines and Zijin virtually triple hydroelectric output to support the Kamoa-Kakula Copper Project Fresh Kakula resource estimate being prepared based on drilling completed to the end of December 2017

Exploration Programs

January 8, 2018

Ivanhoe Mines and Zijin virtually triple hydroelectric output

to support the Kamoa-Kakula Copper Project

Fresh Kakula resource estimate being prepared based on drilling

completed to the end of December 2017

KOLWEZI, DEMOCRATIC REPUBLIC OF CONGO – Ivanhoe Mines (TSX: IVN; OTCQX:

IVPAF) Executive Chairman Robert Friedland and Chief Executive Officer Lars-Eric

Johansson announced today that ongoing upgrading work at the Mwadingusha

hydropower plant in the Democratic Republic of Congo (DRC) has almost tripled the

plant’s interim power output from 11 to 32 megawatts (MW).

This represents 45% of the plant’s designed capacity. Three of Mwadingusha’s six

generators now have been modernized; the remaining three generators are due to be

upgraded and fully operational by the end of 2019 – restoring the plant to its installed

output capacity of approximately 71 MW of power.

The work at Mwadingusha, part of a program to eventually overhaul and boost output

from three hydropower plants, is being conducted by engineering firm Stucky, of

Lausanne, Switzerland, under the direction of Ivanhoe Mines and its joint-venture

partner, Zijin Mining Group, in conjunction with the DRC’s state-owned power company,

La Société Nationale d’Electricité (SNEL). Once fully reconditioned, the three plants will

have installed capacity of approximately 200 MW of electricity for the national grid, which

is expected to be more than sufficient for the Kamoa-Kakula Copper Project.

Mr. Friedland said a long-term, sustainable supply of electricity is essential to Ivanhoe’s

vision to develop Kamoa-Kakula in an environmentally and socially responsible manner.

“The upgrading program underway at Mwadingusha is a significant private-public

partnership venture between SNEL, Ivanhoe and Zijin, which is vital to secure

sustainable, clean electricity for the Congolese people and for the development of a Tier

One copper mine at Kamoa-Kakula,” Mr. Friedland added.

“Hydropower, with its virtues of being clean and renewable, is the best energy solution to

support our development priorities as we continue to look for ways to reduce our impact

on the environment and produce the copper the world requires.”

2

Mwadingusha hydroelectric power plant and distribution substation.

Mwadingusha is the first of three hydropower plants that Ivanhoe and Zijin plan to

upgrade.

Upgrading of the other two existing hydroelectric power plants – Koni and Nzilo 1 – is

expected to begin once Mwadingusha’s upgrading is completed.

The Mwadingusha and Koni plants are in cascade, with Koni directly downstream from

Mwadingusha on the Lufira River at the mouth of Lake Tshangalele, north of Likasi and

approximately 250 kilometres northeast of the Kamoa Mine development site.

The Nzilo 1 plant is on the Lualaba River, downstream of Nzilo Lake and north of the city

of Kolwezi, approximately 40 kilometres from Kamoa.

3

Interior of the Mwadingusha power plant, with one of the upgraded alternators.

Mwadingusha dam, upstream from power plant.

4

Kakula Mine development site now connected to national grid power

Mr. Johansson said that the Kakula Mine development site, approximately 10 kilometres

south of Kamoa’s initial Kansoko Mine site, began receiving power from the national grid

last month.

Kakula’s development is being fast-tracked, with a pre-feasibility study in progress. The

Kakula box cut was successfully completed in October 2017 and the first blast for the

twin declines at Kakula took place in November 2017.

The Kakula Copper Deposit is a gently-dipping blanket of thick, chalcocite-rich copper

mineralization. Initial mine development is planned to begin in the flat, near-surface zone,

which at a 3% cut-off is between 7.1 metres and 11.7 metres thick, with copper grades of

between 8.24% and 10.35% along the deposit’s axis.

Based on the results from an independent National Instrument 43-101 preliminary

economic assessment (PEA) released in November 2017, Kakula’s ultra-high copper

grade is expected to average 6.4% over the first 10 years of production.

Portals to declines being built to access the Kakula Deposit,

showing ventilation installed in the services decline.

5

Jumbo drill operating in the Kakula services decline.

New Kakula Mineral Resource estimate underway

An updated Mineral Resource estimate for Kakula, being prepared based on drilling

completed to the end of December 2017, is expected to result in a significant upgrade

and expansion of the Kakula Mineral Resources.

Results from drill holes completed to the end of December 2017 will form the basis of the

new estimate that will encompass the entire strike length of the Kakula Discovery, which

now extends beyond 12 kilometres. This represents an increase of approximately 60% in

the strike length that will be used to calculate the new resource estimate, compared to

the 7.7-kilometre strike length covered by Kakula’s current resource estimate.

The new resource estimate will enable Ivanhoe and Zijin to assess early and expanded

production scenarios by incorporating resources from Kakula West and Kansoko to

support the main Kakula development plan that was detailed in the November 2017

Kakula preliminary economic assessment.

6

About the Kamoa-Kakula Project

The Kamoa-Kakula Project is a very large, stratiform copper deposit with adjacent

prospective exploration areas within the Central African Copperbelt, located

approximately 25 kilometres west of the town of Kolwezi and about 270 kilometres west

of Lubumbashi. The Kamoa Copper Deposit was discovered by Ivanhoe Mines (then

named Ivanhoe Nickel & Platinum) in 2008, followed by the discovery of the Kakula

Deposit in early 2016.

In August 2012, the DRC government granted mining licences to Ivanhoe Mines for the

Kamoa-Kakula Project that cover a total of 397 square kilometres. The licences are valid

for 30 years and can be renewed at 15-year intervals.

The current Mineral Resource estimate for the Kamoa-Kakula Copper Deposit has an

effective date of November 27, 2017, and was prepared by George Gilchrist, Ivanhoe

Mines’ Mineral Resources Manager, under the direction of Dr. Harry Parker and Gordon

Seibel, of Amec Foster Wheeler. The combined Kamoa-Kakula Indicated Resources total

approximately 1.1 billion tonnes grading 2.78% copper, containing 67.9 billion pounds of

copper, plus another 261 million tonnes of Inferred Resources at 1.94% copper,

containing 11.2 billion pounds of copper, at a 1.0% copper cut-off grade. Details of the

current Mineral Resource estimate are contained in Ivanhoe Mines’ November 28, 2017,

news release.

Ivanhoe Mines and Zijin Mining each hold an indirect 39.6% interest in the Kamoa-Kakula

Project, Crystal River Global Limited holds an indirect 0.8% interest and the DRC

government holds a direct 20% interest.

Qualified Person

The scientific and technical information in this release has been reviewed and approved

by Stephen Torr, P.Geo., Ivanhoe Mines’ Vice President, Project Geology and Evaluation,

and a Qualified Person under the terms of National Instrument 43-101. Mr. Torr, who is

not independent of Ivanhoe Mines, has verified the technical data disclosed in this news

release.

For detailed information about assay methods and data verification measures used to

support the scientific and technical information, please refer to the Kakula 2017

Resource Update, June 2017 technical report available on the SEDAR profile of Ivanhoe

Mines at www.sedar.com or under technical reports on the Ivanhoe Mines website at

www.ivanhoemines.com. A new technical report is being prepared and will be filed within

45 days of the November 28, 2017 news release that announced the results of an

expanded, independent PEA for the development of the Kakula Discovery at the Kamoa-

Kakula Project.

7

About Ivanhoe Mines

Ivanhoe Mines is advancing its three principal projects in Southern Africa: 1) Mine

development at the Platreef platinum-palladium-gold-nickel-copper discovery on the

Northern Limb of South Africa’s Bushveld Complex; 2) mine development and

exploration at the Tier One Kamoa-Kakula copper discovery on the Central African

Copperbelt in the Democratic Republic of Congo; and 3) upgrading at the historic, high-

grade Kipushi zinc-copper-silver-germanium mine, also on the DRC’s Copperbelt. For

details, visit www.ivanhoemines.com.

Information contacts

Investors

Bill Trenaman +1.604.331.9834

Media

North America: Bob Williamson +1.604.512.4856

South Africa: Jeremy Michaels +27.82.772.1122

Cautionary statement on forward-looking information

Certain statements in this release constitute “forward-looking statements” or “forward-looking

information” within the meaning of applicable securities laws, including without limitation: (1) statements

regarding the remaining three generators at the Mwadingusha hydropower plant are scheduled to be

fully upgraded and operational by the end of 2019; (2) statements regarding the upgrading program is

expected to restore Mwadingusha to its installed output capacity of approximately 71 MW of power; (3)

statements regarding the upgrading of the other two existing hydroelectric power plants – Koni and Nzilo

1 – is expected to begin once upgrading work at Mwadingusha is completed; (4) statements regarding

the three plants, once fully reconditioned, will have installed capacity of approximately 200 MW of long-

term, electricity for the grid, which is expected to be more than sufficient for the Kamoa-Kakula Copper

Project; (5) statements regarding Kakula’s ultra-high copper grade is expected to average 6.4% over the

first 10 years of production; (6) statements regarding a new Mineral Resource estimate is expected to

result in a significant upgrade and expansion of the Kakula Mineral Resources; and (7) statements

regarding the new resource estimate will allow Ivanhoe and Zijin to assess early and expanded

production scenarios by incorporating resources from Kakula West and Kansoko to support the main

Kakula development plan that was laid out in the November 2017 Kakula PEA.

All such forward-looking information and statements are based on certain assumptions and analyses

made by Ivanhoe Mines’ management in light of their experience and perception of historical trends,

current conditions and expected future developments, as well as other factors management believe are

appropriate in the circumstances. These statements, however, are subject to a variety of risks and

uncertainties and other factors that could cause actual events or results to differ materially from those

projected in the forward-looking information or statements including, but not limited to, unexpected

changes in laws, rules or regulations, or their enforcement by applicable authorities; the failure of parties

to contracts to perform as agreed; social or labour unrest; changes in commodity prices; unexpected

failure or inadequacy of infrastructure, or delays in the development of infrastructure, and the failure of

exploration programs or other studies to deliver anticipated results or results that would justify and

support continued studies, development or operations. Other important factors that could cause actual

results to differ from these forward-looking statements also include those described under the heading

“Risk Factors” in the company’s most recently filed MD&A as well as in the most recent Annual

Information Form filed by Ivanhoe Mines. Readers are cautioned not to place undue reliance on forward-

looking information or statements. The factors and assumptions used to develop the forward-looking

information and statements, and the risks that could cause the actual results to differ materially are set

8

forth in the “Risk Factors” section and elsewhere in the company’s most recent Management’s

Discussion and Analysis report and Annual Information Form, available at www.sedar.com.

This news release also contains references to estimates of Mineral Resources. The estimation of Mineral

Resources is inherently uncertain and involves subjective judgments about many relevant factors.

Mineral Resources that are not Mineral Reserves do not have demonstrated economic viability. The

accuracy of any such estimates is a function of the quantity and quality of available data, and of the

assumptions made and judgments used in engineering and geological interpretation, which may prove to

be unreliable and depend, to a certain extent, upon the analysis of drilling results and statistical

inferences that may ultimately prove to be inaccurate. Mineral Resource estimates may have to be re-

estimated based on, among other things: (1) fluctuations in copper or other mineral prices; (2) results of

drilling; (3) results of metallurgical testing and other studies; (4) changes to proposed mining operations,

including dilution; (5) the evaluation of mine plans subsequent to the date of any estimates; and (6) the

possible failure to receive required permits, approvals and licences.

Although the forward-looking statements contained in this news release are based upon what

management of the company believes are reasonable assumptions, the company cannot assure

investors that actual results will be consistent with these forward-looking statements. These forward-

looking statements are made as of the date of this news release and are expressly qualified in their

entirety by this cautionary statement. Subject to applicable securities laws, the company does not

assume any obligation to update or revise the forward-looking statements contained herein to reflect

events or circumstances occurring after the date of this news release.