Debottlenecking of Kamoa-Kakula’s Phase 1 and Phase 2 concentrators now complete ahead of schedule

Corporate Updates

February 27, 2023

Debottlenecking of Kamoa-Kakula’s Phase 1 and Phase 2

concentrators now complete ahead of schedule

■

Milling operations increased by 22% to 9.2 million tonnes of

ore per annum

■

Copper production capacity increases to 450,000 tonnes per

annum

HOLLYWOOD, FLORIDA — Ivanhoe Mines (TSX: IVN; OTCQX: IVPAF) Executive

Co-Chair Robert Friedland and President Marna Cloete, announced today at the

32nd BMO Global Metals & Mining Conference that the debottlenecking of the

Kamoa-Kakula Copper Complex’s Phase 1 and 2 concentrators has been

completed ahead of schedule. The ongoing final installation and commissioning

of a fourth Larox filter press is the final step in the overall debottlenecking

program, which is expected to be completed in March 2023.

Mr. Friedland commented: "The operations team at Kamoa-Kakula continues to

exceed expectations ... once again delivering an important expansion project

ahead of schedule and on budget. We intend to reach a sustainable, annualized

production rate of 450,000 tonnes of copper during the second quarter, which is

an exceptional achievement considering we declared Phase 1 production at

Kamoa-Kakula, alongside our joint venture partners, Zijin Mining, less than two

years ago."

"Our dedicated team of engineers are determined to continue this record of

operational excellence as we execute the Phase 3 expansion. The project will

include the integration of Africa's largest direct-to-blister smelter complex and

will drive annualized production to over 600,000 tonnes of copper by early 2025 ...

continuing Kamoa-Kakula’s distinction as the fastest-growing, highest-grade

copper complex on our planet."

The debottlenecking program of Kamoa-Kakula's Phase 1 and Phase 2

concentrators is designed to increase the nameplate ore processing capacity by

22% from 7.6 to 9.2 million tonnes of ore per annum, increasing production

capacity up to approximately 450,000 tonnes per annum of copper in concentrate.

For comparison, Kamoa-Kakula produced 333,497 tonnes of copper in

concentrate in 2022.

2

Two scheduled plant shutdowns, to tie in the new debottlenecking equipment, are

now complete. The shutdown of the Phase 1 concentrator took place in January

2023, and the shutdown of the Phase 2 concentrator plant was completed on

February 22, 2023. The new equipment consists of new hydrocyclone systems,

new scavenger-cleaner flotation cells, a new concentrate thickener, as well as

upsized piping and pumping capacity.

The last outstanding action is the installation and commissioning of the fourth

Larox filter press, which sits at the end of the processing circuit. The filter press

has been lowered into position in the concentrate storage and dispatch

warehouse, and its installation and commissioning are anticipated to be complete

in March. The Phase 1 and Phase 2 concentrators are expected to be able to

sustain the new nameplate capacity of 9.2 million tonnes of ore per annum prior

to the fourth Larox filter press commissioning. The total capital cost for the

debottlenecking program was approximately US$50 million.

The Phase 1 concentrator has been operating at its new, sustained nameplate

capacity of 580 dry tonnes per hour since January 25, 2023; and at times

delivering as high as 590 dry tonnes per hour.

On February 25, 2023, within 12 hours of restarting, the Phase 2 concentrator has

also ramped up to its new, sustained nameplate capacity of 580 dry tonnes per

hour, or 9.2 million tonnes per annum.

The final installation of the Phase 2 concentrator’s scavenger-cleaner

flotation cell was completed on February 22. The commissioning of the

scavenger-cleaner flotation cell on the Phase 1 concentrator complete was

completed in January.

3

Yannick Mwanampuku, Metso Outotec Automation Engineer, with the

recently delivered fourth Larox filter press. This is the final piece of

equipment to be installed in the Kamoa-Kakula Phase 1 and Phase 2

debottlenecking program.

Kamoa-Kakula’s concentrate storage and dispatch warehouse (in the

foreground) has been expanded to accommodate the larger,

debottlenecked Phase 1 and Phase 2 production capacity of approximately

450,000 tonnes of copper in concentrate per annum.

4

Disclosure of technical information

Disclosures of a scientific or technical nature in this news release regarding the

Kamoa-Kakula Copper Complex (other than stockpiles estimation) have been

reviewed and approved by Steve Amos, who is considered, by virtue of his

education, experience and professional association, a Qualified Person under the

terms of NI 43-101. Mr. Amos is not considered independent under NI 43-101 as he

is the Executive Vice President, Projects, at Ivanhoe Mines. Mr. Amos has verified

the technical data related to the foregoing disclosed in this news release.

Ivanhoe has prepared an independent, NI 43-101-compliant technical report for

the Kamoa-Kakula Copper Complex, which is available on the company’s website

and under the company’s SEDAR profile at www.sedar.com:

Kamoa-Kakula Integrated Development Plan 2020 dated October 13, 2020,

prepared by OreWin Pty Ltd., China Nerin Engineering Co., Ltd., DRA Global,

Epoch Resources, Golder Associates Africa, KGHM Cuprum R&D Centre Ltd.,

Outotec Oyj, Paterson and Cooke, Stantec Consulting International LLC, SRK

Consulting Inc., and Wood plc.

The technical report includes relevant information regarding the assumptions,

parameters and methods of the mineral resource estimates on the Kamoa-Kakula

Copper Complex cited in this news release, as well as information regarding data

verification, exploration procedures and other matters relevant to the scientific

and technical disclosure contained in this news release.

About Ivanhoe Mines

Ivanhoe Mines is a Canadian mining company focused on advancing its three

principal projects in Southern Africa; the expansion of the Kamoa-Kakula Copper

Complex in the DRC, the construction of the tier-one Platreef palladium-rhodium-

platinum-nickel-copper-gold project in South Africa; and the restart of the historic

ultra-high-grade Kipushi zinc-copper-germanium-silver mine, also in the DRC.

Ivanhoe Mines also is exploring for new copper discoveries across its circa

2,400km2 of 90-100% owned exploration licences in the Western Foreland, which

are located adjacent to, or in close proximity to, the Kamoa-Kakula Copper

Complex in the DRC.

Information contact

Follow Robert Friedland (@robert_ivanhoe) and Ivanhoe Mines (@IvanhoeMines_)

on Twitter.

Investors

Vancouver:

Matthew Keevil +1.604.558.1034

London:

5

Tommy Horton +44 7866 913 207

Media

Tanya Todd +1.604.331.9834

Website www.ivanhoemines.com

Cautionary statement on forward-looking information

Certain statements in this news release constitute “forward-looking statements” or “forward-

looking information” within the meaning of applicable securities laws. Such statements and

information involve known and unknown risks, uncertainties and other factors that may cause

the actual results, performance or achievements of the company, its projects, or industry results,

to be materially different from any future results, performance or achievements expressed or

implied by such forward-looking statements or information. Such statements can be identified by

the use of words such as “may”, “would”, “could”, “will”, “intend”, “expect”, “believe”, “plan”,

“anticipate”, “estimate”, “scheduled”, “forecast”, “predict” and other similar terminology, or state

that certain actions, events or results “may”, “could”, “would”, “might” or “will” be taken, occur or

be achieved.

Such statements include without limitation (i) statements regarding the planned completion of

the debottlenecking program with the final installation of the fourth Larox filter in March; (ii)

statements regarding the new production capacity is expected to increase to 450,000 tonnes of

copper in concentrate per annum in Q2 2023; and, (iii) statements regarding Kamoa-Kakula's

Phase 3 expansion, including the integration of Africa's largest direct-to-blister smelter complex,

which will drive annualized production over 600,000 tonnes of copper by early 2025.

Readers are cautioned not to place undue reliance on forward-looking information or

statements.

Forward-looking statements and information involve significant risks and uncertainties, should

not be read as guarantees of future performance or results and will not necessarily be accurate

indicators of whether or not such results will be achieved. A number of factors could cause

actual results to differ materially from the results discussed in the forward-looking statements or

information, including, but not limited to, the factors discussed under “Risk Factors” and

elsewhere in the company’s MD&A, as well as the inability to obtain regulatory approvals in a

timely manner; the potential for unknown or unexpected events to cause contractual conditions

to not be satisfied; unexpected changes in laws, rules or regulations, or their enforcement by

applicable authorities; the failure of parties to contracts with the company to perform as agreed;

social or labour unrest; changes in commodity prices; and the failure of exploration programs or

studies to deliver anticipated results or results that would justify and support continued

exploration, studies, development or operations.

Although the forward-looking statements contained in this news release are based upon what

management of the company believes are reasonable assumptions, the company cannot

assure investors that actual results will be consistent with these forward-looking statements.

These forward-looking statements are made as of the date of this news release and are

expressly qualified in their entirety by this cautionary statement. Subject to applicable securities

laws, the company does not assume any obligation to update or revise the forward-looking

statements contained herein to reflect events or circumstances occurring after the date of this

news release.

The company’s actual results could differ materially from those anticipated in these forward-

looking statements as a result of the factors outlined in the “Risk Factors” section and elsewhere

6

in the company’s MD&A for the period ended September 30, 2022, and its Annual Information

Form.