Saturday, September 26, 2026
MiningNewsTerminal
Saturday, September 26, 2026 Admin

IVN.TO ·

Copper ore grading 8% currently being mined and stockpiled at the Kakula Mine, with underground development approximately 4.4 kilometres ahead of schedule Early implementation of extraordinary COVID-19 prevention measures has allowed development of the

Mine Development & Operations

May 13, 2020

Copper ore grading 8% currently being mined and

stockpiled at the Kakula Mine, with underground

development approximately 4.4 kilometres ahead

of schedule

Early implementation of extraordinary COVID-19

prevention measures has allowed development of the

flagship Kakula Copper Mine in D.R. Congo to continue

uninterrupted; initial production on track for third quarter

of 2021

Management and corporate optimization targets company-

wide cash savings of up to US$75 million to strengthen

the current treasury of approximately US$600 million

Ivanhoe issues first quarter financial results

and review of mine construction progress and exploration

activities

TORONTO, CANADA ‒ Ivanhoe Mines (TSX: IVN; OTCQX: IVPAF) today

announced its financial results for the quarter ended March 31, 2020. Ivanhoe

Mines is a Canadian mining company advancing its three mining projects in

Southern Africa: the Kamoa-Kakula copper discovery in the Democratic

Republic of Congo (DRC); the Platreef palladium-platinum-nickel-copper-gold-

rhodium discovery in South Africa; and the extensive upgrading of the

historic Kipushi zinc-copper-lead-germanium mine, also in the DRC.

The company also is exploring for new copper discoveries on its wholly-

owned Western Foreland exploration licences, adjacent to the Kamoa-Kakula

mining licence. All figures are in U.S. dollars unless otherwise stated.

2

HIGHLIGHTS

 Development of the Kakula Copper Mine, the first of multiple, planned

mining areas at the Kamoa-Kakula Project, is making excellent progress.

The first underground access drives intersected Kakula’s initial high-grade

ore zone (+8% copper) in April. Ivanhoe and its joint-venture partner Zijin

Mining are advancing rapidly on construction of the 3.8 million-tonne-per-

annum (Mtpa) processing plant and other surface infrastructure. Initial

copper concentrate production is scheduled for the third quarter of 2021.

 In parallel with the construction of the Kakula Copper Mine, the

independent Kakula definitive feasibility study (DFS) and an updated

Integrated Development Plan for the entire Kamoa-Kakula mining complex

also remain on schedule for Q3 2020. The Kakula DFS will provide a high

level of accuracy for the project economics for Kakula’s initial phase of

mine development, as most construction contracts and orders for

significant capital items have been placed at fixed prices. The Integrated

Development Plan will include details on the planned expansion phases for

the entire Kamoa-Kakula mining complex.

 In early March, Ivanhoe in conjunction with its joint-venture partners

implemented strict quarantine and lock-down procedures to ensure the

well-being of its employees and mitigate the impact of COVID-19 on its

operations. The Kamoa-Kakula minesite has been locked down and all key

personnel are on site; as a result, mine development at Kamoa-Kakula has

continued uninterrupted. Mine development work at the Platreef Project

was temporarily suspended in late March in compliance with the country-

wide lock down imposed by the South African Government. Operations at

Platreef resumed in late April with reduced staffing levels and stringent

safety protocols. Mine development operations at Kipushi remain

temporarily suspended in order to reduce the risk to the workforce and

local communities.

 Also in early March, following the guidelines outlined by the World Health

Organization, the company appointed a task team with overall

responsibility for COVID-19 response planning. Ivanhoe’s response team is

led by Dr. Nicolette Du Plessis, a specialist in Pediatric Infectious Diseases

and a Professor at the University of Pretoria, and includes specialist

doctors, paramedics, nurses, as well as counsel from several external,

world-leading epidemiologists.

 On March 11, 2020, the company announced that it had promoted its Chief

Financial Officer, Marna Cloete, to the position of President, in addition to

her role as Chief Financial Officer. The company’s new Executive

Committee, led by Marna Cloete, President and CFO, includes Dr. Patricia

Makhesha, Executive Vice President, Sustainability & Special Projects;

3

Matthieu Bos, Executive Vice President, Africa; Peter Zhou, Executive Vice

President, China; and Pierre Joubert, who was recently promoted to

Executive Vice President, Technical Services.

 Ivanhoe is in a strong financial position with cash and cash equivalents of

$603 million at the end of March 2020 and no significant debt.

 In April, Ivanhoe announced cost-reduction initiatives to generate cash

savings of up to $75 million through 2021, including reducing discretionary

spending at the company’s projects, lowering general and administrative

costs, voluntary salary reduction for senior management, and deferral of

certain exploration activities. The savings will be directed towards

developing the Kakula Mine to commercial production on schedule and on

budget.

 Underground development at the Kakula Copper Mine continues to

advance ahead of schedule and more than 14.4 kilometres of underground

development now has been completed ─ 4.4 kilometres ahead of plan. The

pace of development is expected to continue to accelerate as additional

mining crews are mobilized.

 In April, crews at Kakula began mining ore in areas with a grade of greater

than 8% copper. This ore is being stockpiled on a dedicated high-grade

surface stockpile, which is forecast to contain 105,000 tonnes grading

5.95% copper by the end of May, 2020. Kakula’s medium-grade ore

stockpile is forecast to contain an additional 250,000 tonnes at 3.01%

copper. The high-grade stockpile is projected to significantly expand in the

coming months as the majority of Kakula’s underground development will

be in mining zones grading +5% copper.

 Construction of Kakula’s processing plant is progressing well with more

than 9,000 cubic metres of concrete poured. Fabrication of structural

steel, processing plant components, and the ball mills is underway. Long-

lead-time items for the processing plant have started to arrive on site, and

the ball mills are scheduled for arrival in mid-2020.

 Refurbishment of six turbines at the Mwadingusha hydro-electric power

plant and associated 220-kilovolt infrastructure, to supply the Kakula Mine

with clean hydropower, is progressing. Four turbines are expected to be

operational by December 2020, and the remaining two in Q1 2021. The

refurbished plant is projected to deliver approximately 72 megawatts of

power to the national grid.

 On February 5, 2020, an updated independently verified Indicated Mineral

Resource increased the combined Kamoa-Kakula Project Indicated Mineral

Resource to 423 million tonnes grading 4.68% copper, at a 3% cut-off. The

4

combined Kamoa-Kakula Project Indicated Mineral Resource now stands

at 1.4 billion tonnes grading 2.7% copper, at a 1% cut-off.

 The initial Indicated Mineral Resource estimate for the Kamoa North

Bonanza Zone includes 1.5 million tonnes grading 10.7% copper, at a 5%

cut-off. Drilling in the first quarter continued to target additional resources

in the vicinity of the ultra-high-grade Bonanza Zone and the Far North

Zone. Given the shallow depth, remarkable thickness and massive copper

sulphide mineralization discovered within the Kamoa North Bonanza Zone,

Kamoa-Kakula’s engineers are evaluating potential opportunities to

accelerate the development of this discovery.

 The controlling east-west striking structure, thought to be responsible for

the massive copper sulphide mineralization in the Kamoa North Bonanza

Zone, is visible as a lineament on airborne magnetic images and can be

traced over a distance of up to 20 kilometres. It trends west onto the

adjacent Western Foreland exploration licences that are 100%-owned by

Ivanhoe Mines. Ivanhoe now controls more than 2,500 square kilometres of

highly-prospective land holdings in the vicinity of the Kamoa-Kakula

mining licence.

 Drilling also has confirmed the extension of the Kamoa North high-grade

copper structure for at least 800 metres in the Kiala Discovery area, part of

Ivanhoe’s 100%-owned Western Foreland licences that adjoin the Kamoa-

Kakula mining licence to the north.

 At the Platreef mine development project in South Africa, the project’s first

shaft (Shaft 1) has been sunk to a depth of more than 975 metres below

surface. Completion of the shaft to a final depth of approximately 1,000

metres is planned for Q3 2020.

 Ivanhoe is investigating a phased development production plan for the

Platreef Project. The plan would target significantly lower initial capital, to

accelerate first production by using Shaft 1 as the mine’s initial production

shaft, followed by expansions to the production rate as outlined in the 2017

definitive feasibility study (DFS). Concurrently, Ivanhoe is updating the

Platreef Project’s 2017 DFS to take into account development schedule

advancement since 2017 when the DFS was completed, updated costs and

refreshed metal prices and foreign exchange assumptions.

 At the end of March 2020, Kamoa-Kakula had reached 2.01 million work

hours free of a lost-time injury; Platreef had reached 528,416 work hours

free of a lost-time injury; and Kipushi had reached 2.27 million work hours

free of a lost-time injury.

5

COVID-19 Response Initiatives

In early April, Ivanhoe provided further details on the rigorous protective measures it

has implemented to protect the health and well-being of its employees, contractors

and local communities while ensuring business continuity at the Kamoa-Kakula

Project.

In response to government-imposed travel restrictions and emergency protocols

introduced worldwide, strict quarantine and lock-down procedures have been

implemented at all three of the company’s projects ─ Kamoa-Kakula, Platreef and

Kipushi ─ to prevent the corona virus from spreading to the minesites. To date, no

COVID-19 cases have been discovered at Ivanhoe’s projects.

At Kamoa-Kakula, the minesite has been locked down and all key personnel are on

site. The supply of food and critical equipment continues under strict delivery

protocols. At present, more than 3,450 employees and contractors are based at the

minesite, which ensures operational continuity and minimizes the impact on the

development schedule.

Platreef temporarily suspended its shaft-sinking operations in compliance with the

country-wide lock down imposed by the South African Government on March 26th.

In late April, mine development operations resumed at Platreef with reduced staffing

levels and strict COVID-19 preventative procedures. Mine development operations

at Kipushi are temporarily suspended to reduce the risk to the workforce and local

communities.

Following the guidelines outlined by the World Health Organization, the company

appointed a task team from senior management with overall responsibility for

COVID-19 response planning. The team is led by Dr. Nicolette Du Plessis, a

specialist in Pediatric Infectious Diseases and a Professor at the University of

Pretoria, and includes specialist doctors, paramedics, nurses, as well as counsel

from several external, world-leading epidemiologists. Dr. Du Plessis is president of

the Southern African Society of Pediatric Infectious Diseases and president-elect of

the Federation of Infectious Diseases Societies of Southern Africa.

The task team, together with its Kamoa-Kakula Project medical response team and

its medical service provider, Medical Support Solutions of the United Kingdom, has

access to some of the best advice from medical experts from around the globe and

has implemented key procedures across the business to ensure minimal disruption

to operations.

6

In response to the COVID-19 pandemic, Ivanhoe postpones its annual

general meeting of shareholders and the date for sending out the

company’s executive compensation disclosure

Due to restrictions on public gatherings enacted by both the Federal and Provincial

governments in Canada in response to the COVID-19 pandemic and to help protect

the health and well-being of its shareholders, colleagues, communities and other

stakeholders, Ivanhoe has made the decision to postpone its annual and special

meeting (AGM) of shareholders to a date no later than the end of September 2020.

As the COVID-19 situation evolves and advice from government and medical

authorities is updated, Ivanhoe will set the new AGM date and file a notice of

meeting and record date on SEDAR (www.sedar.com).

Given the postponement of the company’s AGM, Ivanhoe also intends to postpone

the date when it will send shareholders the management information circular for the

annual general meeting, which includes the company’s executive compensation

disclosure. The company is relying on BC Instrument 51-516 ─ Temporary

Exemptions from Certain Requirements to File or Send Securityholder Materials ─

published on May 1, 2020, that is providing public companies with temporary

blanket relief from certain filing and delivery requirements related to the sending of

materials for annual general meetings.

Once a new AGM date is determined, Ivanhoe will provide shareholders with the

same disclosure documents they would normally receive ahead of an annual

meeting, including the executive compensation disclosure, in accordance with

applicable legislation.

Principal projects and review of activities

1. Kamoa-Kakula Project

39.6%-owned by Ivanhoe Mines

Democratic Republic of Congo

The Kamoa-Kakula Project, a joint venture between Ivanhoe Mines and Zijin Mining,

has been independently ranked as the world’s fourth largest copper deposit by

international mining consultant Wood Mackenzie. The project is approximately 25

kilometres west of the town of Kolwezi and about 270 kilometres west of

Lubumbashi.

Ivanhoe sold a 49.5% share interest in Kamoa Holding Limited (Kamoa Holding) to

Zijin Mining in December 2015 for an aggregate consideration of $412 million. In

addition, Ivanhoe sold a 1% share interest in Kamoa Holding to privately-owned

Crystal River for $8.32 million - which Crystal River will pay through a non-interest-

bearing, 10-year promissory note. Since the conclusion of the Zijin transaction in

7

December 2015, each shareholder has been required to fund expenditures at the

Kamoa-Kakula Project in an amount equivalent to its proportionate shareholding

interest in Kamoa Holding.

A 5%, non-dilutable interest in the Kamoa-Kakula Project was transferred to the

DRC government on September 11, 2012 for no consideration, pursuant to the 2002

DRC mining code. Following the signing of an agreement with the DRC government

in November 2016, in which an additional 15% interest in the Kamoa-Kakula Project

was transferred to the DRC government, Ivanhoe and Zijin Mining now each hold an

indirect 39.6% interest in the Kamoa-Kakula Project, Crystal River holds an indirect

0.8% interest and the DRC government holds a direct 20% interest. Kamoa Holding

holds an 80% interest in the project.

Members of Kamoa-Kakula’s development team at Kakula’s growing high-

grade ore stockpile.

(L-R) Magloire Kashiba (Production Manager), Jinha Numbi (Surveyor

Assistant), Nadege Muzala (Explosive Master), Joel Maweji (Surveyor), Daniel

Jila (Data Clerk), Dorcas Tabitha (JMMC Explosive Master), Amisi Mwanana

(Safety Officer), Didier Masengo (Senior Mine Geologist), Haram Kazadi

(Ventilation observer), Wivine Mutango (Ventilation Observer Assistant),

Reagan Ngandu (Surveyor Assistant) and Pontien Kalala (Mine Overseer).

8

Health and safety at Kamoa-Kakula

At the end of March 2020, the Kamoa-Kakula Project reached 2,014,404 work hours

free of a lost-time injury. A fatality occurred on February 7, 2020 when a contractor's

employee passed away due to fat embolism syndrome following a broken bone

incurred in a workplace accident on January 21, 2020. The Kamoa-Kakula Project

continues to strive toward its workplace objective of zero harm to all employees and

contractors. Since the fatality in February a number of additional safety interventions

have been implemented.

As part of the company’s the COVID-19 response initiatives, the Kamoa-Kakula

minesite has been locked down and strict isolation procedures have been

implemented in the event of higher-risk personnel, or potential COVID-19 cases.

Ten intensive care units, each equipped with a ventilator, and 20 high-care units will

be available to treat potential patients, in addition to a quarantine facility for up to 60

potential patients. The project has procured abundant critical protective supplies for

its minesite medical professionals, including surgical gloves and N95 face masks.

Definitive Feasibility Study nearing completion for the Kakula Mine

An independent definitive feasibility study (DFS) for the Kakula Mine is underway

with an expected completion date of Q3 2020. At the same time, Ivanhoe expects to

issue an updated preliminary economic assessment (PEA) for the expanded

Kamoa-Kakula combined production scenarios, incorporating Kansoko, Kakula

West and Kamoa North mining areas. The updated PEA will include the updated

Mineral Resource estimate for Kamoa North which includes the initial Mineral

Resource estimate for the Kamoa North Bonanza Zone. The updated resource

estimate technical report was filed under the company’s SEDAR profile at

www.sedar.com on March 27, 2020.

The forthcoming Kakula DFS will incorporate detailed design, engineering and

procurement, which is largely complete. A separate DFS for an on-site smelter is

underway in parallel, and will be incorporated into the integrated Kamoa-Kakula

PEA.