Integra Receives Federal Permitting Schedule FOR Delamar Heap Leach Project; Clear and Accelerated Pathway Targeting a Record of Decision IN 2027

Permits & Approvals Metallurgy & Processing

INTEGRA RECEIVES FEDERAL PERMITTING SCHEDULE FOR DELAMAR

HEAP LEACH PROJECT; CLEAR AND ACCELERATED PATHWAY

TARGETING A RECORD OF DECISION IN 2027

TSXV: ITR; NYSE American: ITRG

www.integraresources.com

VANCOUVER, BC

,

Jan. 12, 2026

/CNW/ -

Integra Resources Corp. ("Integra" or the "Company")

(TSXV: ITR) (NYSE American: ITRG) is pleased to

announce that the United States Bureau of Land Management ("BLM") has formally established a federal permitting schedule under the National Environmental

Policy Act ("NEPA") for the Company's DeLamar Heap Leach Project ("DeLamar" or the "Project") located in southwestern

Idaho

. For the first time, DeLamar

benefits from a clearly defined, fact-based NEPA pathway endorsed by the BLM, providing enhanced visibility into the federal permitting process and materially

reducing permitting uncertainty.

The BLM-defined schedule contemplates publication of a Notice of Intent ("NOI") in the second quarter of 2026, followed by an anticipated 15-month NEPA review

period, culminating in the issuance of an Environmental Impact Statement ("EIS") and Record of Decision ("ROD") in the third quarter of 2027. This timeline is

materially more efficient than previously contemplated permitting scenarios and represents a significant advancement in the Project's development trajectory.

When combined with the recently released Feasibility Study, demonstrating robust gold- and silver-driven economics, DeLamar is now materially de-risked and

advancing toward a shovel-ready development profile from both a technical and permitting perspective. DeLamar stands out as one of a limited number of

advanced-stage gold-silver development projects in

the United States

currently benefiting from a defined and expedited federal permitting timeline.

George Salamis, President, CEO and Director of Integra, commented:

"The establishment of a BLM-defined federal permitting timeline marks a

transformational milestone for both DeLamar and Integra. For the first time, the Project has a clear, accelerated, and fact-based pathway through the NEPA

process, materially reducing one of the most significant barriers to mine development in

the United States

. This schedule is meaningfully shorter than previously

anticipated and substantially improves project certainty, capital efficiency, and time-to-value for our shareholders.

Combined with the recently released DeLamar Feasibility Study, this milestone positions the Project among the most advanced and de-risked large-scale precious

metals development opportunities in

the United States

. With strong economics, early free cash flow potential, and a defined federal permitting runway, we believe

DeLamar is approaching a build-ready profile and is well positioned to deliver long-term value in a constructive gold and silver market environment."

Permitting Schedule Details and Next Steps

Since the Company's acquisition of the DeLamar Project, nearly a decade of comprehensive environmental baseline data collection, exploration, engineering

studies, and mine plan development have been completed. This extensive work has resulted in a Project that is well advanced and well prepared for rigorous

environmental review. Ongoing engagement with surrounding communities and regional Tribal Nations has provided valuable input and helped inform multiple

iterations of Project refinement as it has progressed through successive review cycles.

Now that the federal permitting schedule has been established, the BLM will move to publish a NOI in the Federal Register to notify government agencies and the

public of the proposed action at DeLamar. The NOI formally announces the BLM's intent to prepare an EIS in accordance with NEPA. Following publication of the

NOI, a public scoping process will be conducted to engage federal, state, and local agencies, Tribal Nations, and the general public to identify issues and

concerns associated with the Project. These issues will guide the development of reasonable alternatives designed to minimize adverse effects and prevent undue

degradation.

Once scoping is complete, environmental impact analyses of the Project and a reasonable range of alternatives will be undertaken, culminating in preparation of

the EIS. Through this process, elements of the Project may be refined and mitigation measures developed to reduce potential environmental impacts. In the EIS

and accompanying ROD, anticipated in the third quarter of 2027, the BLM will identify a Preferred Alternative and any mitigation measures required for Project

implementation. This mitigation is expected to include continued engagement with Tribal Nations and the development of a Programmatic Agreement ("PA"), a

formal framework established among the Company, governmental agencies, and Tribal Nations to identify, manage, and mitigate potential impacts to culturally

sensitive areas and historic properties.

Following completion of the NEPA process, a final revised

Mine Plan

of Operations ("MPO") will be prepared that incorporates the Preferred Alternative and all

required mitigation measures.

While the EIS process is underway, the Company will continue to work with federal, state, and local regulatory agencies to advance the various permits required

prior to construction and operation. These permits include a groundwater Point of Compliance Permit to protect beneficial uses of groundwater; an Idaho Pollution

Discharge Elimination System Permit governing treated industrial wastewater discharges; a Cyanidation Permit for heap leach operations; an Air Quality Permit to

Construct; and a Section 404 Clean Water Act Permit issued by the U.S. Army Corps of Engineers to assess impacts to aquatic resources and implement

compensatory mitigation where required. An approved Reclamation Plan, supported by appropriate financial assurance, will also be required. Upon receipt of all

necessary permits and posting of required bonding, the Project may proceed to construction.

DeLamar Project Overview

(All amounts in

United States

("U.S.") dollars unless otherwise stated)

The past producing DeLamar Project, which includes the adjacent

DeLamar and Florida Mountain

gold and silver deposits, is located in

Owyhee County

in

southwest

Idaho

. Since acquiring the Project in 2017, the Company has demonstrated significant resource growth and conversion while providing robust economic

studies in its maiden Preliminary Economic Assessment, Pre-feasibility Study, and Feasibility Study ("FS") in late-2025. The 2025 FS for DeLamar confirmed

robust economics for a low-cost, large-scale, conventional open pit oxide heap leach operation, with competitive operating costs and high rate of return. The FS

outlines total production of 1.1 million ounces of gold equivalent ("AuEq") over a 10-year operating mine life (plus two years of residual leaching), resulting in an

average annual production profile of 106,000 ounces AuEq per annum at a co-product mine-site All-in Sustaining Cost of

$1,480

per ounce ("/oz") AuEq. The

Project generates an after-tax Net Present Value ("NPV5%") of

$774 million

with an after-tax Internal Rate of Return ("IRR") of 46% at base case gold and silver

prices of

$3,000

/oz and

$35

/oz, respectively. After-tax NPV5% improves to

$1.7 billion

and after-tax IRR to 89% using recent gold and silver prices of

$4,250

/oz

and

$60

/oz, respectively. Refer to the 2025 DeLamar Feasibility Study announcement news release from

December 17, 2025

here

.

1

.

Gold equivalent calculated using base case metal prices:

$3,000

/oz Au and

$35

/oz Ag

2

.

See Cautionary Note Regarding Non-GAAP Measures

The FS technical report will be filed on SEDAR+ at

www.sedarplus.ca

and EDGAR at

www.sec.gov

by

February 2, 2026

.

About Integra

Integra is a growing precious metals producer in the Great Basin of the

Western United States

. Integra is focused on demonstrating profitability and operational

excellence at its principal operating asset, the Florida Canyon Mine, located in

Nevada

. In addition, Integra is committed to advancing its flagship development-

stage heap leach projects: the past producing DeLamar Project located in southwestern

Idaho

and the Nevada North Project located in western

Nevada

. Integra

creates sustainable value for shareholders, stakeholders, and local communities through successful mining operations, efficient project development, disciplined

capital allocation, and strategic M&A, while upholding the highest industry standards for environmental, social, and governance practices.

ON BEHALF OF THE BOARD OF DIRECTORS

George Salamis

President, CEO and Director

CONTACT INFORMATION

Corporate Inquiries:

[email protected]

Company website:

www.integraresources.com

Office phone: 1 (604) 416-0576

Qualified Person

The scientific and technical information contained in this news release has been reviewed and approved

by

James Frost

, P.Eng., Director, Technical Services of Integra, who is a "Qualified Person" as defined in National Instrument 43-101 – Standards of Disclosure

for Mineral Projects ("NI 43-101").

Forward Looking Statements

Certain information set forth in this news release contains "forward

looking statements" and "forward

looking information" within the meaning of applicable

Canadian securities legislation and in applicable

United States

securities law (referred to herein as forward

looking statements). Forward-looking statements are

often identified by the use of words such as "may", "will", "could", "would", "anticipate", "believe", "expect", "intend", "potential", "estimate", "budget", "scheduled",

"plans", "planned", "forecasts", "goals" and similar expressions. Except for statements of historical fact, certain information contained herein constitutes forward

looking statements which includes, but is not limited to, statements with respect to: the future financial or operating performance of the Company, the Project and

its mineral properties; results from work performed to date; the estimation of mineral resources and reserves; the realization of mineral resource and reserve

estimates; the development, operational and economic results of the FS for the Project, including cash flows, revenue potential, development, expenditures, and

timing thereof, extraction rates, life-of-mine projections and cost estimates; timing of completion of a technical report summarizing the results of the FS; magnitude

or quality of mineral deposits; anticipated advancement of the Project mine plan; exploration expenditures, costs and timing of the development of new deposits;

costs and timing of future exploration; permitting; construction and optimization planning; estimates of metallurgical recovery rates; anticipated advancement of the

Project, future prospects and prospective inclusion of Mineral Resources in future mining activities; requirements for additional capital; the future price of metals;

government regulation of mining operations; environmental risks; the timing and possible outcome of pending regulatory matters; the realization of the expected

economics of the Project; future growth potential of the Project; and future development plans.

Forward-looking statements are based on a number of factors and assumptions made by management and considered reasonable at the time such statement

was made. Assumptions and factors include: the Company's ability to complete its planned exploration and development programs; the absence of adverse

conditions at the Project and the Company's mineral properties; satisfying ongoing covenants under the Company's loan facilities; no unforeseen operational

delays; no material delays in obtaining necessary permits; results of independent engineer technical reviews; the possibility of cost overruns and unanticipated

costs and expenses; the price of gold remaining at levels that continue to render the Project and the Company's mineral properties economic; the Company's

ability to continue raising necessary capital to finance operations; and the ability to realize on the mineral resource and reserve estimates. Forward

looking

statements necessarily involve known and unknown risks and uncertainties, which may cause actual performance and financial results in future periods to differ

materially from any projections of future performance or result expressed or implied by such forward

looking statements. These risks and uncertainties include,

but are not limited to: general business, economic and competitive uncertainties; the actual results of current and future exploration activities; conclusions of

economic evaluations; meeting various expected cost estimates; benefits of certain technology usage; changes in project parameters and/or economic

assessments as plans continue to be refined; future prices of metals; possible variations of mineral grade or recovery rates; the risk that actual costs may exceed

estimated costs; geological, mining and exploration technical problems; failure of plant, equipment or processes to operate as anticipated; accidents, labor

disputes and other risks of the mining industry; delays in obtaining governmental approvals or financing; risks related to local communities; the speculative nature

of mineral exploration and development (including the risks of obtaining necessary licenses, permits and approvals from government authorities); title to properties;

and other factors beyond the Company's control and as well as those factors included herein and elsewhere in the Company's public disclosure. Although the

Company has attempted to identify important factors that could cause actual actions, events or results to differ materially from those described in the forward-

looking statements, there may be other factors that cause actions, events or results not to be as anticipated, estimated or intended. Readers are advised to study

and consider risk factors disclosed in Integra's Annual Information Form dated

March 26, 2025

for the fiscal year ended

December 31, 2024

, which is available on

the SEDAR+ issuer profile for the Company at

www.sedarplus.ca

and available as Exhibit 99.1 to Integra's Form 40-F, which is available on the EDGAR profile

for the Company at

www.sec.gov

.

Investors are cautioned not to put undue reliance on forward-looking statements. The forward-looking statements contained herein are made as of the date of

this news release and, accordingly, are subject to change after such date. The Company disclaims any intent or obligation to update publicly or otherwise revise

any forward-looking statements or the foregoing list of assumptions or factors, whether as a result of new information, future events or otherwise, except in

accordance with applicable securities laws. Investors are urged to read the Company's filings with Canadian securities regulatory agencies, which can be viewed

online under the Company's profile on SEDAR+ at

www.sedarplus.ca

.

Cautionary Note Regarding Non-GAAP Financial Measures

Alternative performance measures in this news release such as "cash cost", "AISC" and "free cash flow" are furnished to provide additional information. These

non-GAAP performance measures are included in this news release because these statistics are used as key performance measures that management uses to

monitor and assess performance of DeLamar, and to plan and assess the overall effectiveness and efficiency of mining operations. These performance measures

do not have a standardized meaning within International Financial Reporting Standards ("IFRS") and, therefore, amounts presented may not be comparable to

similar data presented by other mining companies. These performance measures should not be considered in isolation as a substitute for measures of

performance in accordance with IFRS.

Cash Costs

Cash costs include site operating costs (mining, processing, site G&A), refinery costs and royalties, but excludes head office G&A and exploration expenses.

While there is no standardized meaning of the measure across the industry, the Company believes that this measure is useful to external users in assessing

operating performance.

All-In Sustaining Cost

Site level AISC includes cash costs and sustaining and expansion capital, but excludes head office G&A and exploration expenses. The Company believes that this

measure is useful to external users in assessing operating performance and the Company's ability to generate free cash flow from potential operations.

Free Cash Flow

Free cash flows are revenues net of operating costs, royalties, capital expenditures and cash taxes. The Company believes that this measure is useful to the

external users in assessing the Company's ability to generate cash flows from the Project.

Cautionary Note for U.S. Investors Concerning Mineral Resources and Reserves

National Instrument 43-101 Standards of Disclosure for Mineral Projects ("NI 43-101") is a rule of the Canadian Securities Administrators which establishes

standards for all public disclosure an issuer makes of scientific and technical information concerning mineral projects. Technical disclosure contained in this news

release has been prepared in accordance with NI 43-101 and the Canadian Institute of Mining, Metallurgy and Petroleum Classification System. These standards

differ from the requirements of the U.S. Securities and Exchange Commission ("SEC") and resource and reserve information contained in this news release may

not be comparable to similar information disclosed by domestic

United States

companies subject to the SEC's reporting and disclosure requirements.

Neither the TSX Venture Exchange nor its Regulation Services Provider (as that term is defined in the policies of the TSX Venture Exchange) accepts

responsibility for the adequacy or accuracy of this release.

View original content to download multimedia:

https://www.prnewswire.com/news-releases/integra-receives-federal-permitting-schedule-for-delamar-heap-leach-project-clear-and-accelerated-pathway-targeting-a-record-of-decision-in-2027-302658850.html

SOURCE

Integra Resources Corp.