Friday, September 18, 2026
MiningNewsTerminal
Friday, September 18, 2026 Admin

ISO.TO ·

IsoEnergy Initiates Bulk Sample Program at the Tony M Uranium Mine in Utah, a Key Step Toward a Potential Restart Decision

Exploration Programs Metallurgy & Processing

IsoEnergy Initiates Bulk Sample Program at the Tony M Uranium Mine in Utah,

a Key Step Toward a Potential Restart Decision

Toronto, ON, January 7, 2026 – IsoEnergy Ltd. (“IsoEnergy” or the “Company”) (NYSE American:

ISOU; TSX: ISO) is pleased to announce a bulk sample program (the “ Bulk Sample”) at its 100%-

owned Tony M uranium mine in Utah (“Tony M” or the “Mine”). The Bulk Sample is designed to

collect key technical, operational, and economic data required as one of the steps to support a

potential production restart decision at one of the few fully permitted, past -producing

conventional uranium mines in the United States.

The Bulk Sample program will involve the extraction of up to 2,000 tons of mineralized material

over a 12–14-week period (which commenced late December 2025) and will be executed using

contract mining services provided by GenX Mining Contractors, LLC of Spring Creek , Nevada.

Mineralized material recovered during the program will be transported to the White Mesa Mill in

Utah, owned by Energy Fuels Inc., for processing.

With U.S. utilities increasingly focused on securing domestic uranium supply and limited near -

term production capacity available, IsoEnergy believes Tony M represents a rare opportunity to

advance a permitted, infrastructure -ready uranium mine toward poten tial restart without the

need for costly and timely mill construction/refurbishment or major permitting initiatives. The

Bulk Sample is a critical step in defining the scope and economics of a future production plan at

Tony M. This work aligns with U.S. federal initiatives focused on rebuilding domestic nuclear fuel

supply chains and enhancing energy security through increased domestic uranium production.

Upon completion of the Bulk Sample, IsoEnergy expects to evaluate the results alongside ongoing

optimization studies to determine next steps, which may include advancing detailed mine

planning, finalizing restart sequencing, and assessing the timing of a p otential production

decision.

Highlights

• Bulk Sample Designed as a Decision Gate Toward Potential Restart

o Low-risk, limited -scope program structured to generate real -world mining,

processing, and cost data required to evaluate a potential restart decision.

o Results expected to inform mine planning, sequencing, and commercial

production assumptions.

• De-Risking Mining Methods and Cost Structure Under Operating Conditions

o Establishes actual contract mining costs and validates assumptions used in

economic models.

o Refines mineral material- control strategies to minimize dilution and maximize

delivered grade, including testing dilution-control techniques in a production-style

environment.

• Processing Pathway Established Through Existing Toll Milling Agreement

o Mineralized material to be processed at the White Mesa Mill, eliminating the need

for new mill construction and materially reducing capital intensity and execution

risk.

o Enables IsoEnergy to focus capital and effort on mine restart and optimization

rather than downstream infrastructure.

• Production-Ready Underground Systems and Execution Tested

o Trials ventilation, ground-control, and underground operating procedures ahead

of full-scale mining.

Philip Williams, CEO and Director of IsoEnergy, commented, “ The Bulk Sample at Tony M is a

major milestone in advancing one of the few restart -ready uranium mines in the United States.

This program is designed to generate the real -w orld da t a w e n eed t o e v alua t e a p ot en tial full

scale production restart under current market conditions. With permitting, infrastructure, and

toll milling already in place, Tony M has the potential to be among the next conventional uranium

mines in the U.S. to return to productio n as demand for secure domestic supply continues to

grow.”

Figure 1: Scooptram mucking underground at the Tony M Mine

Figure 2: Haul truck in the Tony M Mine

Progress on Tony M Mine Work Programs

During 2025, IsoEnergy advanced a series of initiatives designed to strengthen the operating and

economic profile of Tony M including, reducing the uranium production royalty on the Utah Trust

Lands Administration (SITLA) lease from 8% to 3%, High -Pressure Slurry Ablation testing , which

has demonstrated the potential to recover more than 90% of the uranium into roughly 25% of

the original mass and mineralized material- sorting testwork completed in October which

achieved over 90% recovery into roughly 50% of the original mass for material amenable to

sorting. In parallel, an enhanced evaporation study has shown that Landshark evaporators

eliminate the need for evaporation -pond expansion and reduc e both permitting timelines and

capital requirements. Together, these work programs support the Company’s strategy of

systematically de-risking Tony M and improving the economic framework for a future production

decision.

About Tony M Mine

The Tony M Mine is located in eastern Garfield County, southeastern Utah, approximately 66 air

miles (107 kilometers) west northwest of the town of Blanding and 215 miles (347 kilometers)

south-southeast of Salt Lake City. The project is the site of the Tony M underground uranium mine

that was developed by Plateau Resources, a subsidiary of Consumer Power Company, in the mid-

1970s.

Uranium and vanadium mineralization at the Tony M mine is hosted in sandstone units of the Salt

Wash Member of the Jurassic age Morrison Formation, one of the principal hosts for uranium

deposits in the Colorado Plateau region of Utah and Colorado.

Tony M has the following current mineral resource estimate:

Table 1: Summary of Mineral Resources – Effective Date September 9, 2022

Classification

Tons

(short tons)

Grade

(% eU3O8)

Contained Metal

(lbs. eU3O8)

Indicated 1,185,000 0.28 6,606,000

Inferred 404,000 0.27 2,218,000

Notes:

1. Reported in the Technical Report on the Tony M Project, Utah, USA Report for NI 43-101,

prepared for Consolidated Uranium Inc. by SLR International Corporation; Mark B.

Mathisen, Qualified Person, Effective Date September 9, 2022.

2. CIM (2014) definitions were followed for all Mineral Resource categories.

3. Uranium Mineral Resources are estimated at a cut-off grade of 0.14% U3O8.

4. The cut-off grade is calculated using a metal price of $65/lb U3O8.

5. No minimum mining width was used in determining Mineral Resources.

6. Mineral Resources are based on a tonnage factor of 15 ft3/ton (Bulk density 0.0667

ton/ft3 or 2.14 t/m3).

7. Mineral Resources are not Mineral Reserves and do not have demonstrated economic

viability.

8. Past production (1979-2008) has been removed from the Mineral Resource.

9. Totals may not add due to rounding.

10. Mineral Resources are 100% attributable to IsoEnergy and are in situ.

Qualified Person Statement

The scientific and technical information contained in this news release was reviewed and

approved by Dean T. Wilton: PG, CPG, MAIG, a consultant of IsoEnergy who is a “Qualified Person”

(as defined in National Instrument 43-101 - Standards of Disclosure for Mineral Projects).

About IsoEnergy Ltd.

IsoEnergy (NYSE American: ISOU; TSX: ISO) is a leading, globally diversified uranium company with

substantial current and historical mineral resources in top uranium mining jurisdictions of Canada,

the U.S. and Australia at varying stages of development, providing near-, medium- and long-term

leverage to rising uranium prices. IsoEnergy is currently advancing its Larocque East project in

Canada’s Athabasca basin, which is home to the Hurricane deposit, boasting the world’s highest-

grade indicated uranium mi neral resource. IsoEnergy also holds a portfolio of permitted past -

producing, conventional uranium and vanadium mines in Utah with a toll milling arrangement in

place with Energy Fuels. These mines are currently on standby, ready for rapid restart as market

conditions permit, positioning IsoEnergy as a near-term uranium producer .

For further information, please contact:

Philip Williams

CEO and Director

[email protected]

1-833-572-2333

X: @IsoEnergyLtd

www.isoenergy.ca

Cautionary Statement Regarding Forward-Looking Information

This press release contains “forward -looking information” within the meaning of applicable

Canadian securities legislation and “forward- looking statements” within the meaning of U.S.

securities laws (collectively, “forward -looking statements”). Generally, forward-looking

statements can be identified by the use of forward-looking terminology such as “plans”, “expects”

or “does not expect”, “is expected”, “budget”, “scheduled”, “estimates”, “forecasts”, “intends”,

“anticipates” or “does not anticipate”, or “believes”, or variations of such words and phrases or

state that certain actions, events or results “may”, “could”, “would”, “might” or “will be taken”,

“occur” or “be achieved”. These forward- looking statements may relate to details of the Bulk

Sample program and planned processing activities and the results thereof; expectations with

respect to any potential restart decision with respect to the Company’s US projects and the

anticipated timing thereof; permitting, development or other work that may be required to bring

any of the projects into development or production; the completion of planned technical studies

and the expected results thereof; expectations regarding completion of technical and economic

assessments; expectations regarding the Company’s enhanced U.S. market presence;

expectations regarding the Company’s engagement with institutional and retail investors;

increased demand for and interest in nuclear power and uranium; potential changes in US nuclear

policy; and any other activities, events or developments that the Company expects or anticipates

will or may occur in the future.

Forward-looking statements are necessarily based upon a number of assumptions that, while

considered reasonable by management at the time, are inherently subject to business, market

and economic risks, uncertainties and contingencies that may cause actual results, performance

or achievements to be materially different from those expressed or implied by forward- looking

statements. Such assumptions include, but are not limited to, assumptions that the results of

planned exploration and development activities are as anticipated; assumptions that the results

of planned technical work programs and technical and economic assessments are as anticipated;

the anticipated mineralization of IsoEnergy’s projects being consistent with expectations and the

potential benefits from such projects and any upside from such projects; the price of uranium;

assumptions regarding uranium market conditions and policy shifts; that general business and

economic conditions will not change in a materially adverse manner; that financing will be

available if and when needed and on reasonable terms; and that third party contractors,

equipment and supplies and governmental and other approvals required to conduct the

Company’s planned activities will be available on reasonable terms and in a timely manner.

Although IsoEnergy has attempted to identify important factors that could cause actual results to

differ materially from those contained in forward-looking statements, there may be other factors

that cause results not to be as anticipated, estimated or intended. There can be no assurance that

such statements will prove to be accurate, as actual results and future events could differ

materially from those anticipated in such statements. Accordingly, readers should not place undue

reliance on forward-looking statements.

Such statements represent the current views of IsoEnergy with respect to future events and are

necessarily based upon a number of assumptions and estimates that, while considered reasonable

by IsoEnergy, are inherently subject to significant business, economic, competitive, political and

social risks, contingencies and uncertainties. Risks and uncertainties include, but are not limited

to the following: negative operating cash flow and dependence on third party financing;

uncertainty of additional financing; no known mineral reserves; aboriginal title and consultation

issues; reliance on key management and other personnel; actual results of technical work

programs and technical and economic assessments being different than anticipated; changes in

development and production plans based upon results; availability of third party contractors;

availability of equipment and supplies; failure of equipment to operate as anticipated; accidents,

effects of weather and other natural phenomena; other environmental risks; changes in laws and

regulations; regulatory determinations and delays; stock market conditions generally; demand,

supply and pricing for uranium; other risks associated with the mineral exploration industry; and

general economic and political conditions i n Canada, the United States and other jurisdictions

where the Company conducts business. Other factors which could materially affect such forward-

looking statements are described in the risk factors in IsoEnergy’s most recent annual

management’s discussion and analysis and annual information form and IsoEnergy’s other filings

with securities regulators which are available under the Company’s profile on SEDAR+ at

www.sedarplus.ca and on EDGAR at www.sec.gov. IsoEnergy does not undertake to update any

forward-looking statements, except in accordance with applicable securities laws.

Cautionary Note to United States Investors Regarding Presentation of Mineral Resource

Estimates

The mineral resource estimates included in this press release have been prepared in accordance

with the requirements of the securities laws in effect in Canada, which differ in certain material

respects from the disclosure requirements promulgated by the U .S. Securities and Exchange

Commission (the “SEC”). Accordingly, information contained in this press release may not be

comparable to similar information made public by U.S. companies reporting pursuant to SEC

disclosure requirements.