Iamgold Reports Preliminary 2025 Operating Results & 2026 Guidance
IAMGOLD REPORTS PRELIMINARY 2025 OPERATING RESULTS &
2026 GUIDANCE
All monetary amounts are expressed in U.S. dollars, unless otherwise indicated.
Toronto, Ontario, January 19, 2026 – IAMGOLD Corporation (TSX:IMG, NYSE:IAG) (“IAMGOLD” or the
“Company”) is pleased to report preliminary operating results for the fourth quarter and full year 2025. In addition,
the Company is providing operating guidance for 2026 which outlines production and cost targets for the year
ahead of the upcoming Côté Gold mine expansion study.
2025 Highlights
• 2025 attributable gold production of 765,900 ounces achieving the mid -point of the Company’s 2025
production guidance following record quarterly production at all of its operations , including at Côté
Gold which achieved the top end of its guidance targets.
▪ Côté produced 87,200 attributable ounces (1 24,600 ounces | 100%) in the fourth quarter and
279,900 attributable ounces in 2025 (399,800 ounces | 100%).
▪ Westwood produced 37,900 ounces in the fourth quarter and 113,900 ounces in 2025.
▪ Essakane produced attributable production of 117,300 ounces ( 138,100 ounces | 100%) in the
fourth quarter and 372,100 ounces in 2025 (427,200 ounces | 100%).
• Cash costs1 are expected to be at the top end of the 2025 guidance range of $1,375 and $1,475 per ounce
sold, and AISC1 are expected to approximate the midpoint of the 2025 guidance range of $1,830 and
$1,930 per ounce sold.
• Record revenues expected with preliminary annual gold sales of 817,800 ounces (Côté 70% |
Essakane and Westwood 100%) at an average realized gold price of approximately $ 3,480 per ounce
(including the impact of gold prepayment deliveries in the first half of the year) . Fourth quarter gold sales
were 259,000 ounces at an average realized gold price of approximately $4,190 per ounce.
• IAMGOLD to report year-end financial results on Wednesday, February 18, 2026, after market close.
2026 Outlook
• Attributable gold production of 720,000 to 820,000 ounces , as operations at Côté Gold focus on
sustainable operations at nameplate operating rates ahead of the expansion plans to be announced in the
fourth quarter.
• Cash costs1, excluding royalties, are expected to average $1,100 to $1,250 per ounce sold. With the
current strong gold price environment, royalties account for an average of approximately $ 325 per ounce
sold – based on a gold price assumption for 2026 of $4,000 per ounce. Cash costs1, including royalties,
are expected to average $1,425 to $1,575 per ounce sold.
• Sustaining capital expenditures1 are expected to be approximately $380 million ±5%. Sustaining capital
at Côté Gold, on an attributable basis, is expected to total $160 million ±5%, an increase from the prior year
due to additional non-recurring plant and infrastructure design changes and improvements identified during
the ramp-up to optimize operations and operating costs.
• Expansion capital expenditures1 are expected to total $120 million ±5% in 2026, as the company intends
to accelerate spending to de -risk the contemplated Côté expansion, early works include basic mill
infrastructure and a significant pushback to expand the operating area of the pit.
2 | 8
“I would like to commend our operations teams for an incredible fourth quarter as each of our mines reported record
results, at an opportune time when the gold price is setting new highs and as IAMGOLD accelerates into its position
as a strong mid-tier modern gold producer with significant cashflow generation and organic growth potential,” said
Renaud Adams, President and Chief Executive Officer of IAMGOLD. “Turning the page to 2026, it is going to be a
very exciting year for IAMGOLD as we continue to build on the momentum at Cote, Westwood and Essakane.”
“At Côté, the operations team this year will be focusing on unit cost improvement through stable and efficient mining
and milling practices. It is important for our team to be able to operate Côté within expected specifications before
we expand the operation further. Meanwhile our projects team is pushing full steam ahead on the expansion study
mine plan later this year that will outline : an increase to Côté Gold’s throughput targeting the Côté and Gosselin
zones as a single large pit based on a subset of the 16 million ounces of Measured and Indicated Resources and
four million ounces of Inferred Resources.”
“It is an exciting year as well at our Nelligan Mining Complex in the Chibougamau -Chapais region of Quebec ,
following our acquisitions at the end of last year of Northern Superior and Orbec, which significantly increased our
property package and the potential of the consolidated camp. This year we are substantially increasing our budget
to $25 million for a comprehensive exploration program. We are eager to get our drills to work on this project, which
already is among the largest pre-production stage gold projects in Canada. Further, despite the significant mineral
inventory of over 3.7 million Measured and Indicated ounces and 8 million Inferred ounces, many of the primary
targets have seen minimal drilling over the last few years due to the competition for capital from other projects and
capital constraints in the junior mining market. The exploration program this year will look to expand the mineralized
footprint of both Nelligan and Philibert, while testing Monster Lake at depth, and then conducting regional
exploration on high priority targets to further grow the potential of the project.”
2025 OPERATING REVIEW
Quarter ended Dec 31, 2025
Côté Gold Westwood Essakane
Consolidated
Q4 2025 Q4 2024
Gold produced, attr.1 oz 87,200 37,900 117,300 242,400 176,700
Material mined kt 11,081 279 9,392
Waste mined kt 6,567 - 5,269
Ore mined kt 4,514 279 4,123
Mill feed kt 2,874 299 3,241
Mill feed grade g/t 1.44 4.21 1.50
Gold recovery % 94% 93% 88%
Full year 2025 Côté Gold Westwood Essakane
Consolidated
2025 2024
Gold produced, attr.1 oz 279,900 113,900 372,100 765,900 666,500
2025 Guidance koz 250 – 280 125 – 140 360 – 400 735 – 820
Material mined kt 45,108 1,378 39,648
Waste mined kt 30,468 - 27,738
Ore mined kt 14,640 1,378 11,910
Mill feed kt 10,889 1,154 12,560
Mill feed grade g/t 1.22 3.32 1.18
Gold recovery % 93% 92% 90%
Notes: Figures may not add due to rounding.
1. Attributable ounces for 2025 account for IAMGOLD ownership interests of: Côté Gold – 70%; Essakane – weighted average of 90% share for H1
2025 and 85% for H2 2025; Westwood – 100%
3 | 8
In 2025, IAMGOLD achieved attributable gold production of 765,900 ounces, in line with its guidance range of
735,000 to 820,000 ounces. Annual gold sales of 817,800 ounces (Côté 70% | Essakane and Westwood 100%)
at an average realized gold price of approximately $3,480 per ounce (including the impact of the gold prepay
deliveries completed in the first half of 2025). Fourth quarter gold sales were 259,000 ounces at an average
realized gold price of approximately $4,190 per ounce.
Côté Gold
Annual attributable gold production for Côté Gold was 279,900 ounces (399,800 ounces | 100%) in its first full year
of operations, achieving the top end of the guidance range of 250,000 to 280,000 ounces on an attributable basis
(360,000 to 400,000 ounces | 100%). The mine completed the ramp-up and achieved nameplate plant throughput
of 36,000 tpd over a period of thirty consecutive days ahead of schedule in June.
In the fourth quarter 2025, Côté Gold produced 87,200 attributable ounces (124,600 ounces | 100%), the highest
quarter of production on record. Mining activity in the fourth quarter totaled 11.1 million tonnes, with a record of 4.5
million tonnes of ore mined during the period. The average grade of mined ore was 1.04 g rams per tonne of gold
(“g/t Au”), in line with the mine plan and the highest grade mined to date for the operation. Mill throughput totaled
2.9 million tonnes with record quarterly average head grades of 1.44 g/t Au and recoveries of 94%.
The installation of the additional secondary crusher was completed in November and commissioned in December
with both cone crushers tested and operating in parallel. Operation of the contracted aggregate crusher will be
phased out over the first half of 2026.
Westwood Complex
Annual gold production for Westwood was 113,900 ounces coming in, as noted in the prior quarter, below the
guidance range of 125,000 to 140,000 ounces.
In the fourth quarter, the operation achieved its highest quarter of gold production on record , totaling 37,900
ounces. Underground mining activities averaged 1,139 tpd , translating to 105,000 tonnes in the quarter, a record
volume from underground since the mine restart , with an average underground head grade of 9.87 g/t Au . Mined
grades benefitted from the extraction of higher grade stopes which had been scheduled as part of the 2025 mine
sequence. Mill throughput in the fourth quarter was 299,000 tonnes at a blended average head grade of 4.21 g/t
Au and recoveries of 93%.
Essakane
Annual attributable gold production for Essakane was 372,100 ounces (427,200 ounces | 100%), following a strong
fourth quarter, resulting in the mine achieving production within the attributable guidance range of 360,000 to
400,000 ounces (400,000 to 440,000 ounces | 100%) despite the change in ownership from 90% to 85% that was
effective mid-year.
In the fourth quarter, Essakane achieved record production of 138,100 ounces, or 117,300 ounces on an
attributable basis due to strong head grades. Mining activities totaled 9.4 million tonnes that includes 4.1 million
tonnes of ore mined due to a low strip ratio of 1.3:1 in the quarter. The average grade of mine d ore was 1.44 g/t
Au, which were the highest grades mined in the year as the mine sequences further into Phase 7. Mill throughput
totaled 3.2 million tonnes with strong head grades of 1.50 g/t Au and recoveries of 88%.
Cash Costs1 & AISC1
Cash costs1 are expected to be at the top end of the 2025 guidance range of $1, 375 and $1,475 per ounce sold,
and AISC1 are expected to approximate the mid-point of the 2025 guidance range of $1,830 and $1,930 per ounce
sold. Cost guidance was increased mid-year due to the direct impact of higher gold prices on royalties, as well as
a change in the royalty structure and the impact of a strengthening Euro on costs at Essakane and higher operating
and non-recurring capital costs at Côté during ramp-up to support the long-term availability of the operation.
4 | 8
2026 OPERATING OUTLOOK
IAMGOLD’s operational guidance for 2026 is as follows:
Operating Guidance
Consolidated Côté Gold Westwood Essakane
(attributable to IAMGOLD unless specified)
Gold production – 100% koz 900 – 1,010 390 – 440 110 – 130 400 – 440
Ownership interest % 70% 100% 85%
Gold production – attributable1,2,6 koz 720 – 820 270 – 310 110 – 130 340 – 380
Cash costs (excluding royalties)3 $/oz $1,100 – $1,250 $900 – $1,050 $1,500 – $1,650 $1,150 – $1,300
Royalties per ounce @ $4,000/oz $/oz $325 $300 – $450
Cash costs (including royalties) 3,4 $/oz $1,425 – $1,575 $1,200 – $1,350 $1,500 – $1,650 $1,600 – $1,750
AISC3 $/oz $2,000 – $2,150 $1,775 – $1,925 $1,950 – $2,100 $2,000 – $2,150
Sustaining capital, attr.2,3,4 ±5% $M $380 $160 $55 $165
Expansion capital, attr.2,3 ±5% $M $120 $85 $30 $5
Notes: Figures may not add due to rounding. The 2026 guidance is based on the following full year assumptions: average realized gold price of $4,000
per ounce, USD:CAD exchange rate of 1.35, EUR:USD exchange rate of 1.18 and average Brent oil price of $ 65 per barrel and WTI price of $ 65 per
barrel.
1. Attributable ounces account for IAMGOLD ownership interests: Essakane – 85%; Côté Gold – 70%, Westwood – 100%
2. Amounts shown are attributable to IAMGOLD
3. This is a non-GAAP measure, refer to “Non-GAAP Financial Performance Measures” in the Company’s September 30, 2025, MD&A for further
information. See also the Cautionary Notes to this press release.
4. Assumes a $4,000 per ounce gold price for calculating Royalties based on consensus gold price for 2026
5. Includes $7 million of capitalized exploration and evaluation expenditures also included in the Exploration Outlook guidance table.
6. Mine planning assumes a budgeted gold price of $3,700/oz; while using cut-off grades based on current reserve pricing. Refer to the Mineral
Resource and Reserve estimates in the Company’s disclosures.
Royalty Sensitivities
$ per ounce sold
Gold Price Consolidated Côté Gold Essakane
$3,500 $270 $245 $350
$4,000
(guidance price) $325 $300 $450
$4,500 $390 $340 $540
$5,000 $440 $385 $600
Côté Gold
Côté Gold attributable production in 2026 is expected to be in the range of 270,000 to 300,000 ounces (390,000
to 440,000 ounces | 100%). The focus in 2026 now that the plant is operating at nameplate throughput is on
stabilization and optimization, improving the cost structure and preparing for the contemplated expansion of Côte.
Short to medium term capital investment is planned to improve the operating efficiency and cost structure while
also systematically investing in the expansion to derisk the larger build.
Mining activities in 2026 are planning a total of 52 million tonnes of material mined. This includes a large pushback
to open up the pit to improve mine efficiency and prepare for the contemplated expansion. Mill t hroughput is
expected to average 36,000 tpd over the course of the year after the successful installation of the additional
secondary crusher in the fourth quarter 2025. Plant head grades are expected to average between 1 .00 g/t and
1.10 g/t. Gold production is expected to be higher in the second half of the year based on expected lower grades
5 | 8
in the first half of the year followed by higher grades in the second half – as determined by the scheduled mine
sequence.
Cash costs1, excluding royalties, at Côté Gold are expected to be in the range of $900 to $1,050 per ounce sold,
and including royalties (assuming a $4,000 per ounce gold price) in the range of $1,200 to $1,350 per ounce sold.
AISC1 is expected to be in the range of $1,775 to $1,925 per ounce sold.
Sustaining capital expenditures1 guidance for Côté Gold is approximately $ 160 million ±5% ($230 million | 100%)
that includes $50 million ($70 million | 100%) of non-recurring capital to improve the operating efficiency and the
long-term operating cost structure. Expansion capital1 of $85 million ±5% ($120 million | 100%) and mainly relates
to the planned strategic pit pushback that will provide both operational flexibility in the near term and optionality for
the expansion, as well as moving certain expansion related construction of the plant forward, which includes an
additional Vertimill in early 2027.
Westwood Complex
Westwood production is expected to be in the range of 110,000 to 130,000 ounces in 2026. Underground mining
is planned for between 900 to 1,000 tonnes per day and the Grand Duc open pit life has been extended into 2027
based on the improved economics in the current gold price environment. Mill throughput is expected to average
1.2 million tonnes in 2026 with blended head grades expected to average 3.44 g/t over the course of the year.
Cash costs 1 at Westwood are expected to be in the range of 1,500 to $1,650 per ounce sold and AISC 1 in the
range of $1,950 to $2,100 per ounce sold.
Sustaining capital expenditures1 guidance is $55 million ±5%, primarily consisting of underground development in
support of the mine plan, the continued renewal of the mobile fleet and fixed equipment, and certain asset integrity
projects at the Westwood mill. Expansion capital1 of $30 million is primarily associated with development works to
support the study of options to expand the mine in the eastern parts of Westwood underground that could be
amenable to bulk mining. Additional extensions to the Grand Duc pit will also be investigated this year.
Essakane
Essakane attributable production is expected to be in the range of 340,000 to 380,000 ounces (400,000 to 440,000
ounces | 100%). Mining activities will predominantly target Phase 6 and 7 and the Lao pit that is adjacent to the
Essakane Main Zone, with an estimated target of 42 to 43 million tonnes of material mined at a strip ratio between
2.5 to 3:1. Mill throughput is expected to total near 13 million tonnes with head grades averaging 1.10 g/t Au.
Cash costs1, excluding royalties and gold-price linked costs, are expected to be in the range of $ 1,150 to $1,300
per ounce sold , and including royalties and gold -price linked costs, in the range of $1,600 to $1,750 . AISC1 is
expected to be in the range of $2,000 to $2,150 per ounce sold.
Capital expenditures 1 guidance is approximately $ 165 million ±5%, including approximately $ 90 million of
capitalized waste stripping to progress Phase 6 and into the Lao pit, as well as the ongoing replacement of certain
equipment to improve efficiency and maintenance costs at Essakane , and the annual tailing s dam program. The
capitalized waste stripping is higher than estimated in the December 2023 technical report due to inclusion of the
Lao pit and extension of estimated mine life into 2029.
Exploration
Exploration expenditures for 2026 are expected to be approximately $ 54 million attributable to IAMGOLD, the
majority of which will be expensed. The largest exploration spend will be at the Nelligan Complex of approximately
$24 million including the construction of certain infrastructure to support an expanding program, Côté Gold of
approximately $5 million attributed to IAMGOLD, and Essakane at approximately $6 million.
6 | 8
Exploration Guidance 2026
$ millions Capitalized1 Expensed Total
Exploration projects – greenfield 11 34 45
Exploration projects – brownfield 7 2 9
Total 18 36 54
1. Full year 2026 guidance on capitalized exploration expenditures has also been included in the capital expenditure guidance.
CONFERENCE CALL
IAMGOLD will release its fourth quarter and full year 2025 operating and financial results after market hours on
Tuesday, February 17, 2026. Senior management will host a conference call to discuss the operating performance
and financial results on Wednesday, February 18, 2026, at 8:30 a.m. (Eastern Time).
Listeners may access the conference call via webcast from the events section of the Company’s website at
www.iamgold.com (webcast link below), or through the following options:
Pre-register via: Chorus Call IAMGOLD Q4YE 2025 Conference Call Registration (recommended) –
Upon registering, you will receive a calendar booking by email with dial -in details and unique PIN.
This process will bypass the operator and avoid the queue.
Toll free (North America): 1 (833) 752-3518
International: +1 (647) 846-8209
Webcast: https://event.choruscall.com/mediaframe/webcast.html?webcastid=gVmmp0rw
An online archive of the webcast will be available by accessing the Company’s website at www.iamgold.com. A
telephone replay will be available for one month following the call by dialing toll free 1 (855) 669-9658 within North
America or +1 (412) 317-0088 from international locations and entering the passcode: 9312946.
1 End Notes (excluding tables): This is a non-GAAP financial measure, refer to “Non-GAAP Financial Performance Measures” in the
Company’s September 30, 2025, MD&A for further information. See also the Cautionary Notes to this press release.
About IAMGOLD
IAMGOLD is an intermediate gold producer and developer based in Canada with operating mines in North America
and West Africa, including Côté Gold (Canada), Westwood (Canada) and Essakane (Burkina Faso). The Côté
Gold Mine achieved full nameplate in June 20 25 and has the potential to be among the largest gold mines in
Canada. IAMGOLD operates Côté Gold in partnership with Sumitomo Metal Mining Co. Ltd. In addition, the
Company has an established portfolio of early stage and advanced exploration projects within high potential mining
districts, including the Nelligan Mining Complex located in Quebec, Canada . IAMGOLD employs approximately
3,700 people and is committed to maintaining its culture of accountable mining through high standards of
Environmental, Social and Governance practices. IAMGOLD is listed on the New York Stock Exchange
(NYSE:IAG) and the Toronto Stock Exchange (TSX:IMG).
IAMGOLD Contact Information
Graeme Jennings, Vice President, Investor Relations
Tel: 416 360 4743 | Mobile: 416 388 6883
Toll-free: 1 888 464 9999
7 | 8
CAUTIONARY STATEMENT REGARDING FORWARD-LOOKING INFORMATION
All information included in this news release, including any information as to the Company’s vision, strategy, future financial or operating
performance and other statements that express management’s expectations or estimates of future performance or impac t, including
statements in respect of the prospects and/or development of the Company’s projects, other than statements of historical fact, constitutes
forward-looking information or forward-looking statements within the meaning of applicable securities laws (collectively referred to herein
as “forward-looking statements”) and such forward-looking statements are based on expectations, estimates and projections as of the
date of this news release. Forward -looking statements are generally identifiable by the use of words such as “may”, “will”, “should”,
“would”, “could”, “continue”, “expect”, “budget”, “aim”, “can”, “focus”, “forecast”, “anticipate”, “estimate”, “maintain”, “b elieve”, “intend”,
“plan”, “schedule”, “guidance”, “outlook”, “potential”, “seek”, “t argets”, “cover”, “strategy”, “during”, “ongoing”, “subject to”, “future”,
“objectives”, “opportunities”, “committed”, “prospective”, “likely”, “progress”, “strive”, “sustain”, “effort”, “extend”, “re main”, “pursue”,
“predict”, or “project” or the negative of these words or other variations on these words or comparable terminology. For example, forward-
looking statements in this news release include, without limitation, those under the heading “About IAMGOLD”, and include, but are not
limited to, statements with respect to the delisting of the NSUP Shares, Northern Superior ceasing to be a reporting issuer, the anticipated
benefits from integrating Northern Superior and its assets, and the expansion and extension of the mineralization at Nelligan.
The Company cautions the reader that forward-looking statements are necessarily based upon a number of estimates and assumptions
that, while considered reasonable by management, are inherently subject to significant business, financial, operational and other risks,
uncertainties, contingencies and other factors, including those described below, which could cause actual results, performanc e or
achievements of the Company to be materially different from results, performance or achievements expressed or implie d by such
forward-looking statements and, as such, undue reliance must not be placed on them. Forward -looking statements are also based on
numerous material factors and assumptions, including as described in this news release, including with respect to: th e Company’s
present and future business strategies; operations performance within expected ranges; anticipated future production and cash flows;
local and global economic conditions and the environment in which the Company will operate in the future; the price of precious metals,
other minerals and key commodities; projected mineral grades; international exchanges rates; anticipated capital and operatin g costs;
the availability and timing of required governmental and other approvals for the construction of the Company’s projects.
Risks, uncertainties, contingencies and other factors that could cause actual results, performance or achievements of the Company to
be materially different from results, performance or achievements expressed or implied by such forward -looking statements i nclude,
without limitation: the Company’s business strategies and its ability to execute thereon; the development and execution of implementing
strategies to meet the Company’s sustainability vision and targets; security risks, including civil unrest, war or terrorism and disruptions
to the Company’s supply chain and transit routes as a result of such security risks, particularly in Burkina Faso and the Sah el region
surrounding the Company’s Essakane mine; the availability of labour and qualified contractor s; the availability of key inputs for the
Company’s operations and disruptions in global supply chains; the volatility of the Company’s securities; litigation; contests over title to
properties, particularly title to undeveloped properties; mine closure and rehabilitation risks; the lack of availability of insurance covering
all of the risks associated with a mining company’s operations; unexpected geological conditions; competition and consolidati on in the
mining sector; the profitability of the Company be ing highly dependent on the condition and results of the mining industry as a whole,
and the gold mining industry in particular; changes in the global prices for gold, and commodities used in the operation of the Company’s
business (including, but not limi ted to diesel, fuel oil and electricity); legal, litigation, legislative, political or economic risks and new
developments in the jurisdictions in which the Company carries on business, including the imposition of tariffs by the United States on
Canadian products; changes in taxes, including mining tax regimes; the failure to obtain in a timely manner from authorities key permits,
authorizations or approvals necessary for transactions, exploration, development or operation, operating or technical difficu lties in
connection with mining or development activities, including geotechnical difficulties and major equipment failure; the availability of capital;
the level of liquidity and capital resources; access to capital markets and financing; the Company’s level of indebtedness; the Company’s
ability to satisfy covenants under its credit facilities; changes in interest rates; adverse changes in the Company’s credit rating; the
Company’s choices in capital allocation; effectiveness of the Company’s ongoing cost co ntainment efforts; the Company’s ability to
execute on de-risking activities and measures to improve operations; availability of specific assets to meet contractual obligations; risks
related to third -party contractors, including reduced control over aspec ts of the Company’s operations and/or the failure and/or the
effectiveness of contractors to perform; risks arising from holding derivative instruments; changes in U.S. dollar and other currency
exchange rates or gold lease rates; capital and currency cont rols in foreign jurisdictions; assessment of carrying values for the
Company’s assets, including the ongoing potential for material impairment and/or write-downs of such assets; the speculative nature of
exploration and development, including the risks of diminishing quantities or grades of reserves; the fact that reserves and resources,
expected metallurgical recoveries, capital and operating costs are estimates which may require revision; the presence of unfavourable
content in ore deposits, including clay and coarse gold; inaccuracies in life of mine plans; failure to meet operational targets; equipment
malfunctions; information systems security threats and cybersecurity; laws and regulations governing the protection of the environment
(including greenhouse gas emission reduction and other decarbonization requirements; the uncertainty surrounding the interpretation of
8 | 8
omnibus Bill C -59 and the related amendments to the Competition Act (Canada); employee relations and labour disputes; the
maintenance of tailings storage facilities and the potential for a major spill or failure of the tailings facilities due to uncontrollable events,
lack of reliable infrastructure, including access to roads, bridges, power sources and water supplies; physical and regulatory risks related
to climate change; unpredictable weather patterns and challenging weather conditions at mine sites; di sruptions from weather related
events resulting in limited or no productivity such as forest fires, severe storms, flooding, drought, heavy snowfall, poor air quality, and
extreme heat or cold; attraction and retention of key employees and other qualified personnel; availability and increasing costs
associated with mining inputs and labour, negotiations with respect to new, reasonable collective labour agreements and/or co llective
bargaining agreements may not be agreed to; the ability of contractors to timely complete projects on acceptable terms; the relationship
with the communities surrounding the Company’s operations and projects; indigenous rights or claims; illegal mining; the potential direct
or indirect operational impacts resulting from external fa ctors, including infectious diseases, pandemics, or other public health
emergencies; the completion of the transaction with Mines d’Or Orbec Inc., including the satisfaction of the conditions precedent to the
proposed arrangement, and the inherent risks involved in the exploration, development and mining business generally. Please see the
Company’s Annual Information Form available on SEDAR+ at www.sedarplus.ca or Form 40 -F available on EDGAR at
www.sec.gov/edgar for a comprehensive discussion of the risks faced by the Company and which may cause actual results, performance
or achievements of the Company to be materially different from results, performance or achievements expressed or implied by forward-
looking statements.
Although the Company has attempted to identify important factors that could cause actual results to differ materially from those contained
in forward -looking statements, there may be other factors that cause results not to be as anticipated, estimated or i ntended. The
Company disclaims any intention or obligation to update or revise any forward-looking statements whether as a result of new information,
future events or otherwise except as required by applicable law.