Saturday, September 26, 2026
MiningNewsTerminal
Saturday, September 26, 2026 Admin

ILC.V ·

International Lithium: PEA for the Raleigh Lake Lithium Project Outlines Highly Favourable After-Tax NPV (Discounted at 8%) of CAD$342.9 million and After-Tax IRR of 44.3% P.A.

Economic Studies

International Lithium: PEA for the Raleigh

Lake Lithium Project Outlines Highly

Favourable After-Tax NPV (Discounted at 8%)

of CAD$342.9 million and After-Tax IRR of

44.3% P.A.

Vancouver, British Columbia--(Newsfile Corp. - December 4, 2023) - International Lithium Corp. (TSXV:

ILC) (OTCQB: ILHMF) (FSE: IAH) (the "

Company

" or "

ILC

") is pleased to announce a positive

Preliminary Economic Assessment ("PEA") for a proposed lithium mining operation to produce

spodumene concentrate at Raleigh Lake, 25 kilometres west of Ignace, Ontario. The PEA relies on

recent metallurgical test work (Phase 1) which indicates that a spodumene concentrate containing 6%

Li

2

O ("SC6") can be produced using a simple crushing circuit and heavy liquid separation techniques. In

the Phase 1 tests lithium recoveries were above 81% while iron oxide content remained within

acceptable limits. As originally foreshadowed, the very near proximity of Raleigh Lake to existing service

infrastructure along the Trans-Canada Highway corridor affords significant logistical and economic

advantages to the project.

This PEA only considers spodumene concentrate, i.e. lithium, as a revenue source. The Company

continues to investigate the potential value associated with the extraction of rubidium from the microcline

zone within the spodumene deposit.

PEA Highlights

Economics (discounted at 8% p.a., CAD$)

Pre-tax Cashflow = CAD$709.4 million, NPV = CAD$385.1 million, IRR = 46.5% p.a.

After-tax Cashflow = CAD$634.0 million, NPV = CAD$342.9 million, IRR = 44.3% p.a.

Price assumptions: CAD$3,139/tonne for 6% Li

2

O concentrate (USD$2,325/tonne)

CAPEX/OPEX

Total pre-production capital costs: CAD$111.9 million

Total sustaining capital: CAD$17.5 million

Total life of mine ("LoM") operating costs: CAD$381 million (including concentrate transport)

Average operating costs: CAD$94.38/tonne milled, CAD$993/tonne SC6

Mining Method

Traditional open pit drilling and blasting followed by load and haul

The plant feed production rate is proposed to be 540,000 tonnes per year ("tpy")

This LoM mine plan is proposed to mine 57 million tonnes ("Mt") of material over the mine life,

which will be comprised of 4Mt of mill feed and 53Mt of waste with an average strip ratio of 13.2:1

Life of mine is forecast at nine years; project duration is 11 years

Process Plant

The base case process plant is designed to crush 1,500 tonnes per day ("tpd") and process 1,500

tpd in a dense media separation ("DMS") plant to produce a nominal 56,000 tpy of 6% Li

2

O at

81% recovery

Process engineering and design were developed to a scoping level based on the results of the

SGS laboratory testing. The SGS lab tests obtained 22.9 weight percentages of 6% Lithium

Concentrate and estimated 81% lithium recovery

A design factor of 10% is applied on nominal requirements to ensure that the process equipment

has enough capacity to take care of the expected feed variation

Total production for LoM is 414,904 tonnes of 6% Li

2

O spodumene concentrate ("SC6")

Raleigh Lake is 100% owned by ILC and there are no overriding royalties. The Company's vision for

Raleigh Lake is a low-risk, low-impact, small-scale mining operation that can begin to provide critical

minerals necessary to fulfil Canada's Critical Mineral Strategy in a shorter time frame than would be

required for a much larger scale, longer duration and more remotely located project. Revenues from the

mine production would continue to feed back into exploration work to expand ILC's drive to become a

significant Critical Minerals supplier in North America.

Executive Comment

John Wisbey, Chairman and CEO of ILC

commented:

"It is very pleasing for ILC to have delivered its first PEA at Raleigh Lake, Ontario with highly respectable

numbers of CAD$385.1 million pre-tax NPV and 46.5% IRR (post-tax CAD$342.9 million and 44.3%

IRR) despite the significant fall in the lithium price this year. This reflects, to a considerable extent, our

good access to infrastructure at Raleigh Lake, which has a very beneficial effect on our projected costs.

It should be noted that this PEA only relates to the 600 hectare Zone 1 out of our 48,500 hectares of

claims at Raleigh Lake. It is also important to note that at this stage these numbers only relate to the

lithium at Raleigh Lake and not to the separately declared rubidium resource. Given the high market

price of rubidium, this leaves appreciable upside.

This year's fall in the lithium price has of course depressed these numbers versus what they would have

been only a few months ago. For example, a major Canadian lithium company produced a feasibility

report in August 2023, using a price assumption of USD$ 4,699 (CAD$6,109) per tonne for 6%

spodumene concentrate. Had we applied this same number to the spreadsheet that ERM have used for

ILC's PEA, our own NPV would have been CAD$1,137 million pre-tax and CAD$906 million post-tax.

These numbers are more than 2.6 times the NPV numbers that we are now reporting. Of course, what

this means is that, as for every mining company, there is a high level of operational gearing in our

business. It is also very important that, when comparing different companies in the sector, investors and

analysts compare like price assumptions with like.

The omission of rubidium from this initial PEA reflects the fact that we and our consultants need to do

more work on the real size of the rubidium market. Our measured and indicated contained tonnes of

rubidium at Raleigh Lake are 822 tonnes and the inferred 521 tonnes. The market price for >99%

rubidium carbonate as at end November 2023 was USD$ 1,159.38 per kg, meaning USD$ 1.16 million

per tonne. However, if world annual demand for rubidium is and remains much smaller than our resource

there, our ability in future to sell at the rate we can produce would be affected, as could the market price."

PEA Summary

Environmental Resource Management ("ERM") was retained by International Lithium Corp. ("ILC" or the

"Company") to prepare a Preliminary Economic Assessment ("PEA") in accordance with National

Instrument 43-101 (NI 43-101) for the Raleigh Lake Project (the "Project") located near Ignace, Ontario,

Canada.

The Raleigh Lake Project is roughly 25 kilometres west of Ignace and 235 kilometres west of Thunder

Bay in the northwestern part of Ontario within the Kenora Mining District. It is adjacent to the Trans-

Canada Highway (Hwy 17) with CN Rail, TC Energy natural gas pipeline and Hydro One 235kV power

lines transcending the Property. It is owned 100% by International Lithium Canada Ltd., a 100% owned

subsidiary of ILC. There are no royalties or other encumbrances on the Property.

ILC identified the opportunity at Raleigh Lake in 2016 but did not begin actively pursuing work on the

project until 2021 when an initial test drilling campaign was conducted along with regional

lithogeochemical sampling. In 2022 the Company completed sufficient drilling to define a maiden

Mineral Resource Estimate ("MRE") with resources reported in the measured, indicated, and inferred

categories (see below and Company press releases dated March 1 and April 13, 2023). Upon analyzing

the MRE the Company embarked upon some initial metallurgical and economic studies that culminated

in the results presented here. It is the Company's opinion that the results to date provide a good basis to

pursue a mining operation at Raleigh Lake and such an operation can be considered low impact due to

the existence of well-developed and utilized infrastructure and the path to environmental permitting and

eventual production would be shorter than if the project were to be more remotely located. The entire

operation could be significantly more sustainable than remote operations and have direct economic

benefits for the nearby and surrounding communities.

The proposed open pit mining operation would extract 57Mt of material over the mine life, which will be

comprised of 4Mt of mill feed and 53Mt of waste with an average strip ratio of 13.2:1. The proposed

PEA level mine plan is based around work at a proposed plant feed production rate of 540,000 tpy

producing a total of 414,904 tonnes of SC6 concentrate over the mine life. The average mill feed grade

is 0.70% Li

2

O (Table 1).

Table 1: Summary of Base Case Cash Flow Modelling and Project Financial Analysis.

Parameter

Value

Unit

Project Schedule

Overall project life

11

years

Mine life

9

years

Mining, Processing and Economic Parameters

Total mill feed

4.4

Mt

Average mill feed grade

0.70

% Li

2

O

Open pit mining rate

1,500

tpd

Process recovery

81.0

%

Total concentrate produced - 6% TG Li

2

O

414,904

T

Commodity price - 6% TG Li

2

O

$2,325

USD/t

Exchange Rate

1.35

CAD/USD

A summary of the base case capital and operating costs calculated and used in the economic analysis

exercise is shown in Table 2 below. Total costs are based on unit cost rates per tonne mill feed

multiplied by the total tonnes of mill feed (4.37Mt).

Table 2: Summary of Base Case Capital and Operating Costs.

Parameter

Value

Unit

Unit Operating Costs -Production Phase

Mining

CAD$3.55

/t mined

Mining

CAD$40.98

/t mill feed

Milling

CAD$28.53

/t mill feed

G & A

CAD$17.74

/t mill feed

Concentrate transportation

CAD$7.13

/t mill feed

Total

CAD$94.38

/t mill feed

Project Operating and Sustaining Capital Costs

Total operating costs

CAD$381.0 million

Total sustaining capital costs

CAD$17.5 million

All operating and capital costs

CAD$398.6 million

A summary of the base case revenues used in the economic analysis exercise is shown in Table 3 and a

summary of the pre- and post-tax economic analysis results is shown in Table 4.

Table 3: Summary of Base Case Revenues.

Parameter

Value

Project Revenue, Profit and Pre/Post Tax Cash Flows

Concentrate sales revenue

CAD$1,302.3 million

Concentrate transportation costs

CAD$31.1 million

Net operating revenue

CAD$1,271.2 million

Operating and sustaining capital costs

CAD$398.6 million

EBITDA

CAD$872.6 million

Payable taxes

CAD$75.5 million

Net profit after taxes (NPAT)

CAD$797.1 million

Total pre-production capital costs

CAD$163.1 million

Table 4: Summary of Pre- and Post-tax Economic Analysis Results.

Parameter

Value

Unit

Economic Analysis Results

Discount Rate

8.0

% p.a.

Pre-Tax Cashflow

$709.5

CAD$ million

Pre-Tax NPV

$385.1

CAD$ million

Pre-Tax IRR

46.5

% p.a.

Post-Tax Cashflow

$634.0

CAD$ million

Post-Tax NPV

$342.9

CAD$ million

Post-Tax IRR

44.3

% p.a

Resource Estimate

The MRE for the Raleigh Lake project that the current PEA study was based on was produced by

Nordmin Engineering Ltd. ("Nordmin"), based in Thunder Bay, Ontario, who prepared an independent

lithium (spodumene-hosted) and rubidium (microcline-hosted) MRE for the Project and Technical Report,

"NI 43-101 TECHNICAL REPORT AND MINERAL RESOURCE ESTIMATE FOR THE RALEIGH LAKE

LITHIUM PROJECT, IGNACE, ONTARIO" (the " MRE Report") consistent with the standards and

guidelines set out by the Canadian Institute of Mining, Metallurgy and Petroleum ("CIM") and in

accordance with National Instrument 43-101 -

Standards of Disclosure for Mineral Projects

.

In preparation of the MRE and MRE Report, Nordmin applied processes that were appropriate for

lithium pegmatite-style deposits. The Report is available on SEDAR. The effective date for the Report

was April 13, 2023.

Detailed summaries of the MRE Report can be found in Company news releases dated March 1 and

April 13, 2023. A tabulated listing of the MRE for both lithium in spodumene and rubidium in microcline is

given in Table 5 and Table 6 respectively.

Table 5: Lithium Open Pit and Underground MRE.

Area

Resource Category

Mass (kt)

Grade

Contained

Li (t)

Li (ppm)

Li

2

O (%)

Li (t)

Open Pit

650ppm

Li Cut-off

Measured

80

3,887

0.84%

313

Indicated

2,021

2,919

0.63%

5,897

Measured + Indicated

2,101

2,956

0.64%

6,210

Inferred

3,247

2,595

0.56%

8,427

Underground

2,000ppm

Li Cut-off

Measured

3

2,560

0.55%

8

Indicated

189

3,203

0.69%

606

Measured + Indicated

192

3,192

0.69%

614

Inferred

655

3,162

0.68%

2,073

Total

Measured + Indicated

2,293

2,976

0.64%

6,824

Inferred

3,902

2,691

0.58%

10,499

Refer to notes on Mineral Resources below.

Table 6: Rubidium Open Pit and Underground MRE.

Area

Resource Category

Mass (kt)

Grade

Contained

Rb (t)

Rb (ppm)

Rb

2

O (%)

Open Pit

4,000ppm

Rb Cut-off

Measured

5

5,412

0.59%

29

Indicated

90

6,073

0.66%

547

Measured + Indicated

95

6,036

0.66%

576

Inferred

18

3,005

0.33%

53

Underground

4,000ppm

Rb Cut-off

Measured

5

6,547

0.72%

35

Indicated

33

6,474

0.71%

211

Measured + Indicated

38

6,484

0.71%

246

Inferred

106

4,427

0.48%

468

Total

Measured + Indicated

133

6,163

0.67%

822

Inferred

123

4,224

0.46%

521

Refer to notes on Mineral Resources below.

Notes on Mineral Resources

1

.

The MRE was prepared by Christian Ballard, P.Geo., of Nordmin, who is the Qualified Person

("QP") as defined by NI 43-101 and is independent of ILC.

2

.

Mineral Resources, which are not Mineral Reserves, do not have demonstrated economic viability.

The above Inferred Mineral Resources are subject to potential upgrade to Indicated and Measured

Mineral Resources with continued drilling. There is no guarantee that any part of the Mineral

Resources discussed herein will be converted to another category or to a Mineral Reserve in the

future. The estimate of Mineral Resources may be materially affected by environmental, permitting,

legal, marketing, or other relevant issues.

3

.

The Mineral Resources in this report were estimated using the Canadian Institute of Mining,

Metallurgy and Petroleum standards on Mineral Resources and reserves, definitions, and

guidelines prepared by the CIM standing committee on reserve definitions and adopted by the CIM

council (CIM 2014 and 2019).

4

.

The MRE is developed with data from diamond drill holes totaling 13,821 m.

5

.

The pit constrained mineral resources were defined using a parented block model, within an

optimized pit shell with average pit slope angles of 45° in rock and 30° in overburden, a 9.8 strip

ratio (waste material: mineralized material) and a revenue factor of 1.0. The pit optimization shells

were created using Deswik.AdvOPM software.

6

.

The lithium resource pit optimization parameters include: 5.5% Li

2

O spodumene concentrate;

US$1,800 Li

2

O spodumene concentrate price; exchange rate of CAD$1.30/USD$1; concentrate

transportation and offsite charges of CAD$175/t, mining cost of CAD$6/t, processing plus general

and administration cost of CAD$41/t; and a process recovery of 75%. Only lithium value was used

to generate the resource optimized pit shell.

7

.

Underground constrained mineral resources were defined within 5 x 5 x 5 m minable shape

optimization wireframes. The mineable shape optimization constraining wireframes were created

using Deswik.SO software.

8

.

The lithium resource underground minable shape optimization parameters include: 5.5% Li

2

O

spodumene concentrate; US$1,800 Li

2

O spodumene concentrate price; exchange rate of CAD

1.30/USD 1; concentrate transportation and offsite charges of CAD$175/t, mining cost of

CAD$80/t, processing plus general and administration cost of CAD$50/t; and a process recovery

of 75%.

9

.

The rubidium resource was constrained above market value due to the current limited world

market. A 4,000 ppm rubidium cut-off grade was selected. The rubidium resource was excluded

from (i.e. neither taken into account nor used as a credit for) the underground and open pit lithium

resource.

10

.

A default density of 2.668 g/cm3 was used for the mineralized zones.

11

.

All figures are rounded to reflect the relative accuracy of the estimates; totals may not add

correctly.

12

.

The effective date of the MRE was February 16, 2023. The effective date for the MRE Report was

April 13, 2023, and is available on SEDAR.

Preliminary Economic Assessment

The Project:

Is 100% owned by ILC and is not subject to any off-take agreements, partnerships, or royalties.

Consists of 48,500 hectares (485 square kilometres) of adjoining mineral claims.

Is located approximately 25 kilometres west of the Township of Ignace, Ontario.

Distinguishes itself from other lithium projects in Canada by being very well situated near to major

public infrastructure, including:

The Trans-Canada Highway, with direct access to Thunder Bay on Lake Superior, is less

than six kilometers north of the Project;

The Canadian Pacific Railway, natural gas pipelines, and Hydro One power transmission

lines (115 and 230 kV) are just a few kilometres from the Project.

Figure 1: Major public infrastructure relative to the Raleigh Lake project.

To view an enhanced version of this graphic, please visit:

https://images.newsfilecorp.com/files/3232/189765_6cc313dab4895b6e_003full.jpg

Mining Methods

The mining method selected for this project will use traditional open pit drilling and blasting followed by

load and haul. The primary mining production will be executed using hydraulic excavators, front shovels,

and/or wheel loaders as appropriate to the terrain and depending on the major production equipment

available for the project. The material will be hauled from the bench to the crusher, ROM stockpiles or

waste dump depending on the material type. Furthermore, ancillary equipment, such as bulldozers,

graders, and a range of vehicles, is employed to perform functions related to maintenance, support,

services, and utilities.

The proposed PEA level mine plan is based around work at a proposed plant feed production rate of

540,000 tpy.

This LoM mine plan is proposed to mine 57Mt of material over the mine life, which will be comprised of

4Mt of mill feed and 53Mt of waste with an average strip ratio of 13.2:1 (Table 7).

The open pit created for the Raleigh Lake deposit covers about 800 metres in length and 450 metres in

width at the surface (Figure 2). The pit's lowest point extends to a depth of 330 metres above sea level,

while the entrance to the pit is positioned at 475 metres above sea level. The pit incorporates two

entrance ramps, with the first granting access to the southern section of the pit and the second facilitating

entry to the northern part.

The approach selected for the storage of tailings generated at the concentrator and the waste rock from

the mine will be co-disposal. This co-disposal method involves containing filtered tailings within

designated waste rock cells. This approach offers the benefit of enhancing overall stockpile stability and

the efficiency of water drainage. The primary goal is to guarantee long-term physical and geochemical

stability.

Figure 2: General arrangement of the mine site layout for Raleigh Lake showing the final open pit (right)

and co-disposal facility (left).

To view an enhanced version of this graphic, please visit:

https://images.newsfilecorp.com/files/3232/189765_6cc313dab4895b6e_004full.jpg

Table 7: Proposed mine production schedule for Raleigh Lake.

Project Year

-1

1

2

3

4

5

6

7

8

9

Total

Mill Feed (tonnes)

54,037

324,183

539,881

540,107

539,899

539,895

540,305

539,713

540,312

208,721

4,367,053

Measured (tonnes)

0

0

5,566

0

6,338

27,854

0

8,927

23,584

2,725

74,994

Indicated (tonnes)

20,659

112,928

365,731

298,367

265,030

250,939

41,048

152,832

278,257

115,990

1,901,781

Inferred (tonnes)

33,378

211,254

168,584

241,741

268,531

261,103

499,257

377,954

238,471

90,005

2,390,278

Grade Li

2

O (%)

0.67

0.67

0.71

0.94

0.83

0.79

0.49

0.54

0.68

0.65

0.70

Measured (Li

2

O%)

0.00

0.00

0.30

0.00

0.63

1.19

0.00

1.13

0.78

0.66

0.92

Indicated (Li

2

O%)

0.47

0.51

0.70

0.93

0.67

0.75

0.47

0.63

0.67

0.58

0.70

Inferred (Li

2

O%)

0.79

0.75

0.75

0.94

0.99

0.79

0.49

0.48

0.68

0.75

0.70

Waste (tonnes)

7,572,425

8,641,731

8,930,422

9,147,177

8,855,024

4,651,476

2,979,449

1,530,607

864,285

509,626

53,682,222

Concentrate

(tonnes)

0

34,194

51,828

68,321

60,532

57,726

35,668

38,988

49,323

18,324

414,904

Mineral Processing

The Raleigh Lake Orebody contains two metallurgical domains, the lithium spodumene domain and the

rubidium microcline domain. These two separate domains represent zones in the Raleigh Lake orebody

that require customized process flowsheets to be developed for each zone. For the lithium domain, the

objective is the recovery of spodumene to 6% Li

2

O concentrate grade, while the rubidium bearing

microcline domain objective is to develop a flowsheet for extraction of the rubidium from the microcline.

The current focus was to perform mineralogy and mineral processing testing to develop the flowsheet for

the lithium zone (Li-Head) and do a literature review to begin to investigate the flowsheet development of

the rubidium zone (Rb Head). Samples of the lithium and rubidium domains were sent to SGS Canada

in August of 2023, to perform phase one mineralogy tests with follow-up mineral processing testing and