Drill Results

Suite 580 – 625 Howe, Vancouver, British Columbia V6C 2T6

Telephone: 604-687-3959 Facsimile: 604-687-1448 E-Mail: [email protected]

NEWS RELEASE

Independence Gold Intersects 23.00 Metres of 5.85 g/t Gold and 152.70 g/t Silver in the Ted-

Mint Vein System at the 3Ts Project, BC

Vancouver, B.C. (June 20th, 2024 ) – Independence Gold Corp. (TSX.V: IGO) ( OTCQB: IEGCF) (the

“Company” or “Independence”) is pleased to announce the first assay results from the spring drill program

carried out at its 100% owned 3Ts Project. The 3Ts Project is located approximately 185 kilometres (“km”)

southwest of Prince George, British Columbia and is comprised of seventeen mineral claims covering

approximately 8,840 hectares in the Nechako Plateau region of central British Columbia. It is situated 16

km southwest of Artemis Gold Inc.’s Blackwater Project and covers a low-sulphidation epithermal quartz-

carbonate vein district within which more than a dozen individual mineralized veins, ranging from 50

metres (“m”) to more than 1,100 m in strike length, with true widths up to 25m, have been identified.

The spring drill program, consisting of 22 holes and totaling 5,130m, was designed to test several targets

along the Ted-Mint and Tommy Vein Systems, both near surface and at depth below the sill. The program

also tested early-stage exploration target s, including the Johnny and Ian veins, in order to generate

additional drill data for incorporation into the current resource model (see report titled “Technical Report

on the Mineral Resource Estimate Update for the 3Ts Gold Project, Om ineca Mining Division, British

Columbia, Canada” authored by Armitage and Miller, effective August 18th, 2022; please see news release

dated August 18 th, 2022 for further details ). The combined in -pit and underground components of the

Tommy and Ted-Mint vein systems contain a total inferred resource estimate of 4,469,297 tonnes grading

3.64 grams per tonne (“g/t”) gold and 96.26 g/t silver, at a cut-off grade of 0.4 g/t gold equivalent (“AuEq”)

in-pit and 2.0 g/t AuEq underground, containing 522,330 ounces of gold and 13,831,415 ounces of silver,

or 687,156 AuEq ounces.

The Ted-Mint Vein System is situated in the center of the 3Ts Project striking north -south for

approximately one kilometre.

Highlights from the spring drill program at the Ted-Mint vein system include:

• 3TS-24-03: 11.50m grading 9.62 g/t gold and 134.43 g/t silver

• 3TS-24-04: 10.50m grading 2.06 g/t gold and 279.62 g/t silver

• 3TS-24-05: 23.00m grading 5.85 g/t gold and 152.70 g/t silver

• 3TS-24-06: 10.50m grading 4.88 g/t gold and 608.10 g/t silver

• 3TS-24-07: 7.00m grading 12.84 g/t gold and 124.29 g/t silver

Please refer to the website for a map showing the veins and drill hole locations.

Drill Hole Host Rock From

(m)

To

(m)

Drill

Intercept

(m)*

Gold

(g/t)**

Silver

(g/t) Base Metals

Gold

Equivalent

(g/t)***

3TS-24-03 Quartz Veins,

Rhyolite Breccia

321.50 333.00 11.50 9.62 134.43 - 10.96

including 323.50 324.50 1.00 18.08 131.00 - 19.39

Suite 580 – 625 Howe, Vancouver, British Columbia V6C 2T6

Telephone: 604-687-3959 Facsimile: 604-687-1448 E-Mail: [email protected]

Drill Hole Host Rock From

(m)

To

(m)

Drill

Intercept

(m)*

Gold

(g/t)**

Silver

(g/t) Base Metals

Gold

Equivalent

(g/t)***

and including 326.00 327.00 1.00 24.62 275.00 - 27.37

And Rhyolite

Stockwork 342.40 345.00 2.60 0.32 258.10 - 15.23

3TS-24-04 Rhyolite-hosted

Stockwork 52.28 52.77 0.49 1.31 55.10 - 1.86

and

Quartz Veins

67.88 78.50 10.50 2.06 279.62 - 4.86

including 68.00 68.50 0.50 3.54 426.00 - 7.80

and including 70.50 73.00 2.50 3.32 728.80 0.58% Lead,

1.58% Zinc 10.61

and including 75.50 76.50 1.00 1.93 52.00 1.52% Zinc 2.45

3TS-24-05

Quartz Veins

74.36 75.47 1.11 0.95 440.50 0.20% Lead,

0.55% Zinc 5.36

including 74.92 75.47 0.55 1.60 809.00 0.23% Lead,

0.78% Zinc 9.69

and Quartz Veins,

Rhyolite Breccia

266.00 289.00 23.00 5.85 152.70

0.13 % Copper,

0.53% Lead,

0.85% Zinc

7.38

including 267.00 268.00 1.00 62.76 108.00 - 63.84

and including 280.00 282.50 2.50 12.86 427.20 - 17.13

3TS-24-06 Rhyolite-hosted

stockwork 68.00 68.50 1.00 1.10 310.00 0.67% Lead,

1.39% Zinc 4.20

and Rhyolite-hosted

stockwork 72.21 72.62 0.41 2.32 197.56 0.30% Lead,

0.66% Zinc 4.30

and Rhyolite-hosted

stockwork 75.50 76.12 0.62 1.11 217.74 0.20% Lead,

0.78% Zinc 3.29

and Quartz Veins 82.50 93.00 10.50 4.88 608.10 - 10.96

including 82.50 86.50 4.00 10.12 1,246.25 - 22.58

and Quartz Veins 94.50 95.00 0.50 1.18 72.00 - 1.90

3TS-24-07 Quartz Veins 93.00 94.00 1.00 2.20 13.00 - 2.33

and

Quartz Veins

295.50 302.50 7.00 12.84 124.29 0.55% lead,

0.22% Zinc 14.08

including 295.50 297.00 1.50 24.07 194.67 - 26.02

and including 298.00 299.00 1.00 39.85 164.00 - 41.49

*the true widths of the veins are approximately 85% of the reported interval width

**Using a cut-off grade of 0.4 g/t gold as per the resource estimate for “in -pit” grades

*** AuEq assumes Au $2,000 USD/Oz, Ag $20 $USD/Oz and utilizes formula AuEq = (Ag(g/t)*($Ag/$Au))+Au(g/t) and

assumes a metallurgical recovery of 100%. Previous testing has recovered up to 97.9% for gold and 95.5% for silver (see

March 4th, 2021 news release) but as this testing was limited in scope it may not be representative. New metallurgical

studies are planned for summer 2024 to allow more accurate recovery forecasting numbers.

Randy Turner, President & CEO of the Company commented, “We are very pleased with the drill results

to date which indicate the Ted-Mint vein system continues to exhibit wide high-grade intercepts at depth

with some of the highest gold and silver grades ever intercepted on the property. The increase at depth

in base metal values, specifically copper, lead and zinc, along with higher silver grades indicates the 3Ts to

be a classic low sulphidation epithermal deposit. We look forward to receiving the rest of the results and

are actively planning for an extensive summer program at the 3Ts property.”

Summer Exploration Program

A summer exploration program at 3Ts is expected to commence on July 2 nd, 2024, with the primary

Suite 580 – 625 Howe, Vancouver, British Columbia V6C 2T6

Telephone: 604-687-3959 Facsimile: 604-687-1448 E-Mail: [email protected]

objective to define new targets for a fall drill program.

The program will consist of three main goals:

• Extension of the 2019 drone-based magnetic survey to the northern border of the 3Ts project area

and down to the recently staked southern project boundary. This will be supported by ground and

helicopter based mapping and prospecting work to follow up on previously identified isolated gold

and silver anomalies.

• Thorough mapping and sampling over the Ootsa Copper-Silver target area located to the north of

the camp.

• Review of recent drill core with assays to better understand the relationships between precious

metal and base metal veins and their chronology. This will then be applied to historic core to

potentially identify discrete zones of mineralization found outside of the main vein s for further

potential drill targets.

Drill Hole Information from this release

Collar Easting Northing Elevation Azimuth* Dip Total Length

3TS-24-03 364907 5876523 1,155m 90 -70 345m

3TS-24-04 364817 5876582 1,133m 90 -50 108m

3TS-24-05 364817 5876582 1,133m 90 -80 312m

3TS-24-06 364831 5876530 1,146m 90 -45 150m

3TS-24-07 364831 5876530 1,146m 90 -80 326m

* Based on true north. For magnetic declination add 17.5 degrees.

All drill holes completed to date have been sent to SGS lab in Vancouver for sample preparation and analysis.

Robotic sample preparation is used to ensure reproducibility; samples are pulverized to greater than 85%

passing 75 microns. All samples are submitted for four acid digest with an ICP finish. Gold grades are

obtained by fire assay with AAS finish. Samples which return greater than 10 parts per million gold and 100

parts per million silver are resubmitted for fire assay with a gravimetric finish.

NOTES ON MINERAL RESOURCE ASSUMPTIONS MADE IN THIS NEWS RELEASE 1. The classification of the current

Mineral Resource Estimate into Inferred Resource is consistent with current 2014 CIM Definition Standards - For

Mineral Resources and Mineral Reserves.

2. All figures are rounded to reflect the relative accuracy of the estimate and numbers may not add due to rounding.

3. All Resources are presented undiluted and in situ, constrained by continuous 3D wireframe models, and are

considered to have reasonable prospects for eventual economic extraction.

4. Mineral resources which are not mineral reserves do not have demonstrated economic viability. An Inferred Mineral

Resource has a lower level of confidence than that applying to an Indicated Mineral Resource and must not be

converted to a Mineral Reserve . It is reasonably expected that the majority of Inferred Mineral Resources could be

upgraded to Indicated Mineral Resources with continued exploration.

5. It is envisioned that parts of the 3Ts deposit may be mined using open pit mining methods. In -pit mineral resources

are reported at a cut-off grade of 0.4 g/t AuEq within a conceptual pit shell.

6. The results from the pit optimization are used solely for the purpose of testing the “reasonable prospects for

economic extraction” by an open pit and do not represent an attempt to estimate mineral reserves. There are no

mineral reserves on the Propert y. The results are used as a guide to assist in the preparation of a Mineral Resource

statement and to select an appropriate resource reporting cut-off grade.

7. Underground (below -pit) Mineral Resources are estimated from the bottom of the pit and are reported at a base

case cut-off grade of 2.0 g/t AuEq. The underground Mineral Resource grade blocks were quantified above the base

case cut-off grade, below the constraining pit shell and within the constraining mineralized wireframes. At this base

case cut-off grade the deposit shows good deposit continuity with no orphaned blocks.

8. High grade capping was done on 1.0 m composite data.

9. Bulk density values (specific gravity 2.7 grams per cubic centimetre) were determined based on physical test work

from each deposit.

10. “Recoverable AuEq” is based on metal recoveries of 97% for Au and 94% for Ag.

Suite 580 – 625 Howe, Vancouver, British Columbia V6C 2T6

Telephone: 604-687-3959 Facsimile: 604-687-1448 E-Mail: [email protected]

11. The in -pit base case cut -off grade of 0.4 g/t AuEq considers a mining cost of US$2.80/t rock and processing,

treatment and refining, transportation and G&A cost of US$22.00/t mineralized material, and an overall pit slope of

55 degrees. The below -pit base case cut -off grade of 2.0 g/t AuEq considers a mining cost of US$80.00/t rock and

processing treatment and refining, transportation, and G&A cost of US$25.00/t mineralized material.

12. The estimate of Mineral Resources may be materially affected by environmental, permitting, legal, title, taxation,

socio-political, marketing, or other relevant issues

About Independence

Independence Gold Corp. is a well-financed mineral exploration company with holdings ranging from

early-stage grassroots exploration to advanced-stage resource expansion in British Columbia and Yukon.

The Company is positioned to add shareholder value through systematic project advancement, while

management continues to evaluate additional gold and silver projects for possible acquisition. For

additional information, visit the Company's website www.ingold.ca.

Andy Randell, P.Geo., the Company’s Qualified Person as defined by National Instrument 43-101, has

reviewed the technical information in this news release.

ON BEHALF OF THE BOARD OF INDEPENDENCE GOLD CORP.

“Randy Turner”

Randy Turner, President and CEO

Neither the TSX Venture Exchange nor its Regulation Services Provider (as that term is defined in policies of the TSX Venture

Exchange) accepts responsibility for the adequacy or accuracy of this release.

All statements in this press release, other than statements of historical fact, are "forward -looking information" with respect to

Independence within the meaning of applicable securities laws, including statements with respect to the Company’s planned

drilling and exploration activities. The Company provides forward -looking statements for the purpose of conveying information

about current expectations and plans relating to the future and readers are cauti oned that such statements may not be

appropriate for other purposes. By its nature, this information is subject to inherent risks and uncertainties that may be ge neral

or specific and which give rise to the possibility that expectations, forecasts, predictions, projections or conclusions will not prove

to be accurate, that assumptions may not be correct and that objectives, strategic goals and priorities will not be achieved. These

risks and uncertainties include but are not limited to those identified and reported in Independence’s public filings under

Independence Gold Corp.’s SEDAR profile at www.sedar.com. Although Independence has attempted to identify important factors

that could cause actual actions, events or results to differ materially from those described in forward -looking information, there

may be other factors that cause actions, events or results not to be as anticipated, estimated or intended. There can be no

assurance that such information will prove to be accurate as actual results and future events could differ materially from th ose

anticipated in such statements. Independence disclaims any intention or obligation to update or revise any forward -looking

information, whether as a result of new information, future events or otherwise unless required by law.