Itafos Announces Notice to Proceed FOR Husky 1/NORTH DRY Ridge; Solidifying the Potential FOR Mineral Resource Life Through 2037(1)
TSX-V: IFOS
News Release
ITAFOS ANNOUNCES NOTICE TO PROCEED FOR HUSKY 1/NORTH DRY RIDGE;
SOLIDIFYING THE POTENTIAL FOR MINERAL RESOURCE LIFE THROUGH 2037(1)
All approvals were received for the Notice to Proceed (“NTP”) for the Husky 1/North Dry Ridge(“H1/NDR”) mine
development project, which marks the final step in a multi-year process working col laboratively with federal, state and
local stakeholders
The NTP approval solidifies the potential for long-lived operat ions, with mineral resource mine life through 2037 and
potential for additional mineral resources thereafter through leases and third-party agreements(1)
Activities commenced on the requisite infrastructure and ci vil works required for the mine development upon receipt of
the NTP
HOUSTON, TX – May 10, 2023, – Further to the April 24th announcement regarding the Record of Decision, Itafos Inc. (TSX-V:
IFOS) (“Itafos” or the “Company”) has received the Notice to Proceed (“NTP”) for the Husky 1 / North Dry Ridge (“H1 / NDR”) mine
development project. Upon receipt of the NT P, the Company has begun capital activit ies associated with the mine development
project. The H1 / NDR project is expected to be internally funded and is comprised primarily of infrastructure and mine related
development, while continuing to utilize the Conda plant for processing and fertilizer production. Mineral resources from H1 / NDR
are expected in 2026,(1) providing an uninterrupted supply as the Rasmussen Valley Mine reaches the end of its useful life.
David Delaney, Chief Executive Officer, commented “The Notice to Proceed is the final approval step to allow us to achieve our
strategic goal of extending Conda’s mine life with H1 / NDR. Itafos, and the Conda community, would like to thank the Bureau of
Land Management, the U.S. Forest Service and all the other regula tory agencies for their diligent and collaborative work on thi s
project. The Itafos team at Conda is quickly mobilizing resources and operations to begin the development of H1/NDR.”
About Itafos
The Company is a phosphate and specialty fertilizer company. The Company’s businesses and projects are as follows:
Conda – a vertically integrated phosphate fertilizer business located in Idaho, US with production capacity as follows:
- approximately 550kt per year of monoammonium phosphate (“MAP”), MAP with micronutrients (“MAP+”),
superphosphoric acid (“SPA”), merchant grade phosphoric acid (“MGA”) and ammonium polyphosphate (“APP”);
and
- approximately 27kt per year of hydrofluorosilicic acid (“HFSA”);
Arraias – a vertically integrated phosphate fertilizer business located in Tocantins, Brazil with production capacity as
follows:
- approximately 500kt per year of single superphosphate (“SSP”) and SSP with micronutrients (“SSP+”); and
- approximately 40kt per year of excess sulfuric acid (220kt per year gross sulfuric acid production capacity);
Farim – a high-grade phosphate mine project located in Farim, Guinea-Bissau;
Santana – a vertically integrated high-grade phosphate mine and fertilizer plant project located in Pará, Brazil; and
Araxá – a vertically integrated rare earth elements and niobium mine and extraction plant project located in Minas
Gerais, Brazil.
The Company’s shares trade on the TSX Venture Exchange (“TSX-V”) under the ticker symbol “IFOS”.
For more information, or to join the Company’s mailing list to receive notification of future news releases, please visit the
Company’s website at www.itafos.com.
Scientific and Technical Information
Note (1) – Timeline for Husky 1 / North Dry Ridge based on management estimates and subject to certain assumptions, including
successful permitting and development activities. The Husky 1 / North Dry Ridge mine life extension is based on a Preliminary
Economic Assessment (“2019 PEA”) included in the Conda Technical Report (as defined below). The 2019 PEA on the H1 and
NDR properties is preliminary in nature and includes inferred miner al resources that are considered too speculative geologically
to have the economic considerations applied to them that would enable them to be categorized as mineral reserves, and there is
no certainty that the 2019 PEA will be realized. Readers are referred to the Conda Technical Report for the applicable qualifications
and assumptions in connection with its 2019 PEA.
The scientific and technical information contained in this news release related to Mineral Resources for Conda has been reviewed
and approved by Jerry DeWolfe, Professional Geologist (P.Geo.) with the Association of Professional Engineers and Geoscientists
of Alberta. Mr. DeWolfe is a full-time employee of WSP Canada Inc. and is independent of t he Company. The scientific and
technical information contained in this news release related to Mineral Reserves for Conda has been reviewed and approved by
Edward Minnes, Professional Engineer (P.E.) licensed by the State of Missouri. Mr. Minnes is a part-time employee of WSP USA
Inc. and is independent of the Company. The Company’s latest technical report in respect of Conda is entitled, “NI 43-101
Technical Report on Itafos Conda and Paris Hills Mineral Projects, Idaho, USA,” with an effective date of July 1, 2019 (the “Conda
Technical Report”) and is available under the Company’s website at www.itafos.com and under the Company’s profile on SEDAR
at www.sedar.com.
Forward-Looking Information
Certain information contained in this news release constitutes forward-looking information, including statements with respect t o
the timing for commencement of operations at H1 / NDR, the expected resource life of H1 / NDR and the sources of funding to be
used for the development of H1 / NDR. All information other than information of historical fact is forward- looking information. The
use of any of the words “intend”, “anticipate”, “plan”, “continue”, “estimate”, “expect”, “may”, “will”, “project”, “should”, “would”,
“believe”, “predict” and “potential” and similar expressions are intended to identify fo rward- looking information. This inform ation
involves known and unknown risks, uncertainties and other factors that may cause actual results or events to differ materially from
those anticipated in such forward-looking information.
The FLI contained in this news release is based on the opinions, assumptions and estimates of management, including those set
out herein, which management believes are reasonable as at the date the statements are made. Those opinions, assumptions
and estimates are inherently subject to a variety of risks and uncertainties and other known and unknown factors that could cause
actual events or results to differ materially from those pr ojected in the FLI. These include the Company’s expectations and
assumptions with respect to the following: commodity prices; oper ating results; safety risks; changes to the Company’s mineral
reserves and resources; risk that timing of expected permitting will not be met; changes to mine development, optimization plans
and completion; foreign operations risks; changes to regulation; environmental risks; the impact of adverse weather and climate
change; general economic changes, including inflation and foreign exchange rates; the actions of the Company’s competitors and
counterparties; financing, liquidity, credit and capital risks; t he loss of key personnel; impairment risks; cybersecurity risk s; risks
relating to transportation and infrastructure; changes to equip ment and suppliers; adverse litigation; changes to permitting an d
licensing; loss of land title and access rights; changes to insu rance and uninsured risks; the potential for malicious acts; ma rket
volatility; changes to technolo gy; changes to tax laws; the risk of operating in foreign jurisdictions; and the risks posed by a
controlling shareholder and other conflicts of interest. Readers are cautioned that t he foregoing list of risks, uncertainties and
assumptions is not exhaustive.
Although the Company has attempted to identify crucial factors that could cause actual actions, events or results to differ materially
from those described in FLI, there may be ot her factors that cause actions, events or results not to be as anticipated, estimat ed
or intended. Additional risks and uncertainties affecting the FLI c ontained in this news release are described in greater detai l in
the Company’s current Annual Information Form and current Management’s Discussion and Analysis available under the
Company’s profile on SEDAR at www.sedar.com and on the Company’s website at www.itafos.com. There can be no assurance
that FLI will prove to be accurate, as actual results and future events could differ materially from those anticipated in such
information. The reader is cautioned not to place undue reliance on FLI. The Company undertakes no obligation to update forward-
looking statements if circumstances or management’s estimates, assumptions or opinions should change, except as required by
applicable securities law. The FLI included in this news release is expressly qualified by this cautionary statement and is made as
of the date of this news release.
NEITHER THE TSX-V NOR ITS REGULATION SERVICES PROVIDER (AS THAT TERM IS DEFINED IN THE POLICIES OF
THE TSX-V) ACCEPTS RESPONSIBILITY FOR THE ADEQUACY OR ACCURACY OF THIS NEWS RELEASE.
For further information, please contact:
Matthew O’Neill
Itafos Investor Relations [email protected] 713-242-8446