Ivanhoe Electric Provides Update on Activities at its Santa Cruz Copper Project in Arizona 37 Drill Holes Totaling 25,176 Meters of Development Drilling Completed Since Release of the September 2023 Initial Assessment Ongoing Technical Work is Advancing to Support a Preliminary

Exploration Programs

1

January 8, 2024

Ivanhoe Electric Provides Update on Activities at its Santa Cruz

Copper Project in Arizona

37 Drill Holes Totaling 25,176 Meters of Development Drilling

Completed Since Release of the September 2023 Initial Assessment

Ongoing Technical Work is Advancing to Support a Preliminary

Feasibility Study Expected to be Completed by the End of Q2 2025

Recent Infill Drilling Has Delineated a High-Grade Oxide Copper

Domain at Santa Cruz; Drill Hole SCC-125 Intersected 66 Meters at

2.85% Total Copper

14 Drill Holes Totaling 12,510 Meters of Exploration Drilling

Completed in 2023

Recent Assays at Texaco Ridge Confirm Step-out Mineralization;

Drill Hole SCC-122 Intersected 327 Meters Grading 0.81% Total

Copper, Southwest of the Existing Texaco Mineral Resource

Recent Acquisition of Approximately 6,900 Acres of Exploration

Permits Brings the Santa Cruz Project Mineral Rights to Over 18,700

Acres

PHOENIX, ARIZONA – Ivanhoe Electric Inc. (NYSE American: IE; TSX: IE) Executive

Chairman Robert Friedland and President and Chief Executive Officer Taylor Melvin are

pleased to provide an update on ongoing infill and exploration drilling and technical

work at the Santa Cruz Copper Project, located west of Casa Grande, Arizona.

2

Mr. Friedland commented: “Our extensive exploration and development drilling

programs at the Santa Cruz Copper Project have yielded very strong results and

continue to uncover the full potential of the project. By incorporating sustainable

technologies and renewable energy into the upcoming Prefeasibility Study and

leveraging cutting-edge underground material handling methods, we are advancing

studies at Santa Cruz for a modern, high-grade, underground copper mine with very low

projected carbon dioxide-equivalent emissions.”

Mr. Melvin commented: “The fourth quarter of 2023 was an important time for the

advancement of our Santa Cruz Copper Project in Arizona. We significantly increased

our development drilling activity and received substantial assays from recent

exploration drilling. In addition to raising our level of confidence in the Santa Cruz and

East Ridge mineral resource estimates, recent infill drilling identified a large, high-grade

oxide domain in the Santa Cruz deposit. This domain contains higher copper grades

and is located in better quality ground conditions than previously modeled in our 2023

Initial Assessment. Our ongoing development drilling and test work will support the

studies required for our Santa Cruz Prefeasibility Study, which we expect to complete

before the end of Q2 2025. Beyond our development drilling at Santa Cruz and East

Ridge, assays from recent step-out exploration at Texaco Ridge identified wide zones of

primary sulfide mineralization that could provide future growth for our Santa Cruz

Project. The combined success of our recent development and exploration drilling

programs at Santa Cruz provides us with strong momentum as we enter 2024.”

37 development drill holes totaling 25,176 meters have been drilled at the

Santa Cruz and East Ridge Deposits since the release of the September

2023 Initial Assessment

The December 2022 Mineral Resource Estimate that formed the basis for the September

2023 Initial Assessment was modeled from 153,000 meters of drilling in 170 diamond

drill holes. Since the effective date of the 2022 Mineral Resource Estimate, Ivanhoe

Electric has completed an additional 76 drill holes, totaling 55,964 meters, with 25,176

meters drilled since the September 2023 Initial Assessment.

Drilling activity at Santa Cruz ramped up in Q4 2023, with eight rigs drilling nearly

10,000 meters in November alone.

3

Figure 1. 2023 Monthly drilling at the Santa Cruz Project.

* Note December figures include holiday break

4

Figure 2. Map showing drill hole locations at the Santa Cruz Copper Project.

5

Infill and technical drilling confirm the presence of a high-grade oxide and

chalcocite domain

Recent drilling at Santa Cruz has confirmed the presence of high-grade soluble copper

within mineralized oracle granite in an area that was previously classified as an exotic

domain within the 2022 Mineral Resource estimate. We are referring to this domain as

the Verde Domain.

The Verde Domain has higher grades, better rock mass conditions and lower water flow

rates compared to previous modeling. The improved ground characteristics combined

with higher copper grades provide upside potential in terms of possible mining method,

mining rate, and metallurgical recovery compared to what was modeled for this area in

the Initial Assessment. The opportunity to mine the Verde Domain in the relatively early

years is being studied; this has the potential to accelerate capital payback and boost

project economics. The mineralization intersected within the Verde Domain in drill hole

SCC-125 includes:

• 66 meters @ 2.85% total copper from 595 meters, including 56.75 meters @ 3.22%

total copper from 598 meters

• High-grade intersections within SCC-125 include 17.05 meters @ 4.69% total

copper from 602 meters and 11 meters @ 4.87% total copper from 626 meters

6

Figure 3. Shows Verde Domain drilling that has delineated an area of approximately 200

meters by 140 meters in plan view. Assays are pending for several holes in this domain.

7

Photo of core sample from the Verde Domain, drill hole SCC-125 at 630.40 meters

showing granite host rock containing abundant deep green atacamite (a leachable

mineral that is approximately 60% copper by weight).

8

Photo of core boxes from the Verde Domain, drill hole SCC-125 from 625 to 637 meters

showing granite host rock containing abundant deep green atacamite.

Infill drilling designed to support the conversion of indicated resources to

probable reserves

The Initial Assessment is based on 105.2 million tonnes of modeled mill feed from the

current indicated and inferred mineral resource with an average grade 1.58% total

copper. The goal of the current development drilling program is to increase the quality

and confidence of the indicated mineral resource in order to convert a greater portion of

resources to probable mineral reserves as part of the Prefeasibility Study. In 2023, we

completed 76 drill holes in support of this conversion effort.