i-80 Gold Announces Positive Preliminary Economic Assessment on the Granite Creek Open Pit Project, Nevada; After-Tax NPV(5%) of $421 Million with an After-Tax IRR of 30% at US$2,175/oz Au
i-80 Gold Announces Positive Preliminary Economic Assessment on the
Granite Creek Open Pit Project, Nevada; After-Tax NPV(5%) of $421 Million
with an After-Tax IRR of 30% at US$2,175/oz Au
This news release constitutes a "designated news release" for the purposes of the Company's prospectus supplement dated
August 12, 2024
, to its short form
base shelf prospectus dated
June 21, 2024
.
RENO, Nevada
,
March 6, 2025
/CNW/ -
i-80 GOLD CORP.
(TSX:IAU) (NYSE:IAUX)
("i-80 Gold", or the "Company")
is pleased to announce the results of the
preliminary economic assessment (the "PEA") for the Granite Creek Open Pit Project ("Granite Creek Open Pit" or the "Project"). Granite Creek Open Pit is
located within the Getchell Trend in northern Nevada,
United States
, immediately south of the Turquoise Ridge Complex of
Nevada Gold Mines
.
"This Granite Creek Open Pit has all the markings of a top tier project; it is an open pit oxide project in
Nevada
with very good grades and recoveries leading to
robust economics. This project on its own could be a company maker and it's only one of five projects within the i-80 Gold portfolio. It's a key component to
growing our production profile towards mid-tier status, and our team is working vigorously to permit and move this project forward," stated
Richard Young
, Chief
Executive Officer.
Granite Creek Open Pit PEA Highlights
Mineral Estimates, Production and
Mine Life
Large open pit carbon-in-leach ("CIL") gold mine with a life of mine ("LOM") of approximately 10 years.
Annual gold production of approximately 130,000 ounces following ramp up.
Estimated LOM cash costs
(1)
of
$1,185
per ounce and all-in-sustaining costs
(1)
of
$1,225
per ounce.
Updated mineral resource estimate resulting in an indicated gold mineral resource of 1.44 million ounces at 1.18 grams per tonne ("g/t").
Updated mineral resource estimate resulting in an inferred gold mineral resource 0.08 million ounces at 1.09 g/t.
Project Economics
Based on a
$2,175
/oz gold price, the Project's undiscounted after-tax cash flows
(2)
total
$661 million
with an after-tax net present value
(2)
("NPV") of
$421
million
, assuming a 5% discount rate, generating an 30% internal rate of return ("IRR").
Based on spot gold of
$2,900
/oz, the Project's undiscounted after-tax cash flows total
$1,267 million
with an after-tax NPV
(2)
of
$866 million
, assuming a 5%
discount rate, generating an IRR of 50%.
Mine construction capital, including all pre-production facilities and infrastructure is estimated at approximately
$200 million
. No capital is included in mine
construction capital for mobile equipment as the plan incorporates contract mining. Unit mining costs have been increased accordingly.
Additionally, 12.9 million tonnes of stripping is required pre-production and 4.7 million tonnes in the first production year, costing
$33.9 million
.
LOM sustaining capital is estimated at
$30.3 million
, primarily for tailings dam expansion and general sustaining costs.
Total capital includes a contingency of 25%, or
$49.1 million
.
Mining and Processing
The primary mining method will be a conventional open pit truck (10 to 12 trucks) and loader (4 loaders) operation, moving approximately 40 million tonnes
per year during a steady state of production.
The LOM strip ratio is 8.2:1, excluding capitalized pre-stripping.
Material mined will be treated in a CIL process plant on site at a rate of approximately 3.5 million tonnes per year during steady state.
Overall average gold grade processed of 1.25 g/t with an expected average gold recovery of 86.6%.
All amounts are in
United States
dollars, unless otherwise stated.
A summary of key valuation, cost, and operating metrics is presented in Table 1 below. For more detailed metrics presented on an annual basis, see Granite
Creek Open Pit Detailed Cash Flow Model in Appendix.
Table 1: Summary of PEA Key Operating and Financial Metrics
Project
Economics
Unit
Gold Price
$/oz
$2,175
Pre-Tax NPV
(5%)
(2)
$M
$581.3
After-Tax NPV
(5%)
(2)
$M
$421.2
After-Tax IRR
%
30 %
After-Tax Cash Flow
$M
$660.9
Production Profile
Mine Life
years
~10
Mineralized Material Mined
000s
tonnes
34,854.5
Gold Grade of Mineralized Material Mined
g/t Au
1.25
Waste Tonnes Mined (excluding Capitalized Stripping)
000s
tonnes
287,352.9
Capitalized Stripping Tonnes Mined
000s
tonnes
21,969.9
Total Tonnes Moved (Incl. Capitalized Stripping)
000s
tonnes
339,845.0
Total Mineralized Material Processed
000s
tonnes
34,854.5
Gold Grade Processed
g/t Au
1.25
Strip Ratio (excluding capitalized stripping)
(waste:mineralized
material)
8.2:1
Average Gold Recovery
%
86.6 %
Total Gold Recovered
000s oz
1,120
Average Annual Gold Equivalent
Production
(1)
(LOM)
000s oz
110.0
Average Annual Gold Production
(following production ramp up)
000s oz
128.6
Unit Operating Costs
Mineralized Material Mined
$/t mined
$2.37
Processed (CIL)
$/t processed
$11.83
G&A
$/t processed
$1.83
LOM Total Cash Costs
(1)
(net of by-product credit)
$/oz
$1,185
LOM All-in Sustaining Costs
(1)
(net of by-product credit)
$/oz
$1,225
Total Capital Costs
Permitting
$M
$10.0
Construction Capital
$M
$200.2
Capitalized Stripping
$M
$33.9
Sustaining Capital
$M
$30.3
Reclamation & Surety
$M
$18.0
Total Capital & Closure Costs
$M
$292.4
"The steady increase in the gold price has provided the opportunity to reassess the optimal processing stream for the Granite Creek Open Pit Project. The PEA
confirms that anchoring entirely on a CIL processing facility adds significant value, primarily through higher gold recoveries, compared to conventional heap leach
processing and reduces recovery risk. Additionally, the Project benefits from existing underground infrastructure, such as the dewatering systems, which improve
efficiency and reduce capital requirements. Further, with this being a restart of a previously mined open pit, we anticipate an efficient permitting process," added
Matthew Gili
, President and Chief Operating Officer.
Mineral Resource Update
The Project's open pit mineral resource was estimated in four main zones from west to east: B, A, CX, and Mag pits. In each zone, the geology was modeled
using structural domains and grade indicator shells to define the concentrated high-grade and surrounding low-grade zones. The global estimation was then
constrained by an optimized pit shell for resource reporting. Whittle shell optimization model has been utilized to create resource pit shells in Table 2.
Table 2
:
Granite Creek Open Pit Mineral Resource Estimate Statement as of
May 4, 2021
Measured and Indicated Mineral Resources
Class
Deposit
Tonnes
Au
Au
(Mt)
(g/t)
(Moz )
Measured
Pit B
2.91
1.32
0.123
Pit A
0.56
1.07
0.019
CX
10.89
1.30
0.455
Mag
12.00
1.21
0.468
Total Measured
26.36
1.26
1.066
Indicated
Pit B
0.36
1.10
0.013
Pit A
0.69
0.80
0.018
CX
2.97
1.25
0.120
Mag
7.32
0.93
0.219
Total Indicated
11.34
1.01
0.369
Measured
and
Indicated
Pit B
3.27
1.29
0.136
Pit A
1.25
0.92
0.037
CX
13.86
1.29
0.575
Mag
19.32
1.11
0.687
Total Measured & Indicated
37.70
1.18
1.435
Inferred Mineral Resources
Class
Deposit
Tonnes
Au
Au
(000s)
(g/t)
(000s oz)
Inferred
Pit B
0.03
0.64
0.001
Pit A
0.21
0.59
0.004
CX
1.35
1.16
0.050
Mag
0.56
1.11
0.020
Total Inferred
2.15
1.09
0.075
Notes to table above:
I. The effective date of the mineral resources estimate is May 4, 2021.
II. The qualified persons for the estimate are Terre Lane QP-MMSA and Hamid Samari QP-MMSA of GRE, Inc.
III. Mineral resources, which are not mineral reserves, do not have demonstrated economic viability. The estimate of mineral resources may be materially affected by environmental, permitting, legal, title, socio-political, marketing, or other relevant factors. Mineral resources are not ore
reserves and are not demonstrably economically recoverable.
IV. Mineral resources are reported at a 0.30 g/t cutoff, an assumed gold price of 2,040 $/tr. oz, using variable recovery, a slope angle of 41 degrees, 6% royalty, heap leach processing cost $9.04 per tonne (includes admin costs), CIL processing cost of $17.22 per tonne (includes admin
costs).
V. An inferred mineral resource is that part of a mineral resource for which quantity and grade or quality are estimated on the basis of limited geological evidence and sampling. Geological evidence is sufficient to imply but not verify geological and grade or quality continuity. An inferred
mineral resource has a lower level of confidence than that applying to an indicated mineral resource and must not be converted to a mineral reserve. It is reasonably expected that the majority of inferred mineral resources could be upgraded to indicated mineral resources with continued
exploration.
VI. The reference point for mineral resources is in situ.
Figure 1: Granite Creek Conceptual Open Pit Oblique View Layout (CNW Group/i-80 Gold Corp)
Figure 2: Granite Creek Open Pit Longitudinal Section (CNW Group/i-80 Gold Corp)
Economic Analysis
The project economics shown in the PEA are favorable, providing positive NPV values at varying gold prices, capital costs, and operating costs. The Project's
NPV and IRR in relation to fluctuations in the gold price are outlined in Table 3.
Table 3: Granite Creek Open Pit Gold Price Sensitivity After-tax Analysis
Gold Price ($/oz)
$1,850
$2,000
$2,175
$2,500
$2,750
$2,900
$3,000
NPV
5%
($M)
(2)
$260
$361
$421
$624
$776
$866
$926
IRR (%)
21 %
26 %
30 %
39 %
46 %
50 %
52 %
Project Overview
Granite Creek Open Pit is a large open pit CIL gold development project. The Granite Creek property (the "Property") also includes the Granite Creek
Underground Project, a fully permitted, constructed and operating mine currently in the production ramp up phase. The Property is located at the intersection of
the highly prolific
Battle Mountain
-
Eureka
and Getchell gold trends, near Nevada Gold Mines' Turquoise Ridge Complex (see Figure 2). Situated in the
Potosi
mining district, the Project lies approximately 27 miles northeast of
Winnemucca
, within
Humboldt County, Nevada
.
Access to the Property is provided by a combination of paved interstate and state highways and well-maintained, unpaved private roads. The towns of
Winnemucca
and
Battle Mountain
are located 35 miles by road to the southwest and 60 miles to the southeast of the Property, respectively.
Between 1980 and 1999, approximately 987,000 ounces of gold was produced from various open pit mining operations on the site. The Granite Creek Open Pit is
an expansion of the previously mined areas.
Figure 3: i-80 Gold Regional Map (CNW Group/i-80 Gold Corp)
Geology and Mineralization
Mineralization at Granite Creek is
Carlin
-type, with gold hosted in fine-grained arsenian pyrite similar to nearby deposits at Nevada Gold Mines' Turquoise Ridge
Complex which hosts approximately 20 million measured and indicated ounces of gold
(3)
. The primary host rocks at Granite Creek are interbedded shale,
siltstone, and limestone of the Ordovician Comus Formation. Open-pit mineralization at Granite Creek is hosted in Upper Comus siltstone and shale in the Mag pit.
Conversely, mineralization is hosted in the Lower Comus marble, limestone, and siltstone in the CX and B pits. In the CX and B pits, mineralization is strongly
structurally controlled, typically by inverted thrust faults and normal faults trending north to northeast. In the Mag pit, mineralization has a stronger stratigraphic
control with mineralization along bedding in the footwall of the northwest trending Mag fault.
Mining and Processing
Figure 4: LOM Processing Schedule (CNW Group/i-80 Gold Corp)
The PEA demonstrates an initial mine life of approximately 10 years with an annual gold production of approximately 130,000 ounces following production ramp
up. The PEA represents a preliminary point-in-time estimate of the mine plan. The previous preliminary economic assessment released on Granite Creek in 2021,
envisioned a predominately heap leach operation with a small-scale CIL plant for Granite Creek open pit. Further work and higher gold prices have demonstrated
better economics by migrating to a full CIL scenario.
The Project's above ground mine plan will be accomplished using conventional open pit mining techniques with 10 to 12 haul trucks (133 tonne) and four loaders
(nine cubic yard bucket). Mineralized material will be mined at a rate of 10,000 tonnes per day, assuming 350 days of mining a year, for a total of 3.5 million
tonnes annually.
Waste rock would be placed in waste rock storage facilities and as pit backfill as the mining sequence allows. Pits were designed with overall 41-degree side
wall slopes and 90-foot haul roads with a maximum of 10% grade.
The study envisions the construction of 10,000 tonne per day CIL plant on-site. The process plant for Granite Creek was selected based on the material
characteristics, in particular the presence of organic carbon ("TOC") and the associated cyanide leach performance. The variable organic carbon concentrations in
the material make the use of conventional cyanide heap leaching less robust and require more strict ore control measures to divert high TOC materials to an
alternative leach process. Given this, a CIL process was selected, CIL also showed a significant gold recovery advantage over heap leaching.
The Project's process design includes primary crushing via a large jaw crusher with an intermediate stockpile. The crushed material is fed to a sag and ball mill
circuit consisting of a semi-autogenous ("SAG") mill in closed circuit with a ball mill. Pebble crushing has not been included at this stage. The target throughput is
10,000 tonnes per day at a 90% availability. The ground material is directed to a thickener and the thickener underflow to the CIL tanks.
The CIL circuit employs simultaneous cyanide gold leaching and activated carbon gold adsorption with the carbon advancing countercurrent to the leach slurry.
The presence of active carbon during the leaching mitigates the impact of gold adsorption by the organic carbon present in the material.
The loaded carbon is stripped of the gold in a modified Zadra elution circuit. Hot cyanide and sodium hydroxide solutions remove the gold from the carbon into a
concentrated stream that reports to an electrowinning circuit. The electrowon gold is further thermally refined into doré bars prior to shipment.
A conventional tailings storage facility would be constructed near the CIL plant.
Capital Cost Summary
Mine construction capital and sustaining capital over LOM is estimated to total approximately
$292.4 million
. This includes
$33
.9 million in capitalized stripping
cost,
$200.2 million
in construction capital,
$30.3 million
in sustaining capital,
$18 million
in reclamation costs, and
$10 million
for permitting. There is a 25% or
$49.1 million
contingency included in the capital figures. Approximately 12.9 million tonnes of stripping is required in the year prior to production and 4.7 million
tonnes in the first year of production to gain access to the body or mineralized material costing
$37.7 million
. The Project is a former producing mine with a large
portion of the necessary infrastructure in place.
Granite Creek Open Pit is expected to generate an estimated
$660.9 million
in after-tax cash flow over the current mine life (see Figure 5).
Table 4: Granite Creek Open Pit Capital Cost Estimates (excludes permitting and reclamation costs)
Mine Construction
Sustaining
($M)
($M)
Capitalized Waste
$30.1
Construction Capital
$160.8
Sustaining Capital
$24.2
Contingency
(25% on capital and 20% on capitalized waste)
$43.1
$6.1
Total Capital Cost
$234.0
$30.3
Figure 5: Granite Creek Open Pit LOM Annual Cash Flow (at $2,175/oz gold) (CNW Group/i-80 Gold Corp)
Operating Cost Summary
The PEA estimates cash costs
(1)
of
$1,185
per ounce of gold and all-in sustaining costs
(1)
of
$1,225
per ounce of gold for the LOM (see Table 5). Figure 6
illustrates these operating costs over the Project's estimated production profile.
Table 5: Granite Creek Open Pit Total and Unit Operating Costs
Total Costs
Unit Cost
Cost per Ounce
($M)
($/t )
($/oz Au)
Mining
$764.4
$21.93
$632
Processing
$412.3
$11.83
$341
G&A
$63.9
$1.83
$53
Refining, Royalties & Net Proceeds Tax
$193.3
$5.55
$160
Total Operating Cost/Cash Costs
(1)
$2,511.0
$40.8
$1,185
Closure & Reclamation
$18.00
$0.5
$15
Sustaining Capital
$30.3
$0.9
$25
All-in Sustaining Costs
(1)
$1,482.3
$42.5
$1,225
Figure 6: Granite Creek Open Pit LOM Gold Production Profile vs Cost per Ounce (CNW Group/i-80 Gold Corp)
Permitting
The Project has the necessary permits for the ongoing small-scale underground mining operation.
In order to execute the project plan, additional state and federal permits are required. The Project will extend to non-patented mining claims and will require a
permit under the National Environmental Policy Act ("NEPA") which is the regulation that requires an Environmental Impact Statement ("EIS"). The EIS requires
significant effort to acquire; however, i-80 Gold currently expects to successfully permit the Project in a reasonable time frame of three years.
State permits are required for air quality protection, groundwater protection, surface water protection, and water rights. The current PEA includes a timeline for
acquiring these permits, and the costs associated with the permitting effort.
Water Management
The underground mine will abstract up to 3,000 gpm of dewatering water coming from the underground mine sumps and the dewatering wells required to dewater
the mine. The MAG pit is currently flooded and must be dewatered. Many of the types of dewatering water contain elevated arsenic concentrations above Nevada
Reference Values, as does much of Nevada's natural groundwater. As a result, the site has a plan for the management and treatment of any Mine Influenced
Water ("MIW") that does not meet discharge standards. This plan includes preferentially consuming MIW for operations, treating water in a metal-precipitator
treatment plant, and the entrainment of MIW in the tailings pond, followed by forced evaporation over the tailings pond. The majority of pumped groundwater will
be reinfiltrated in several already-permitted Rapid Infiltration Basins ("RIBs") which return the water to the
Humboldt
basin aquifers.
Closure
The site closure costs are estimated at
$18.0 million
. The closure plan involves covering the tailings facility and mine waste with industry-standard engineered
covers which will prevent groundwater and surface water quality impacts. Upon closure, no long-term liabilities are currently predicted to exist which may
complicate bond release and a walk-away post-closure condition.
Next Steps to Feasibility Study
A feasibility study in accordance with National Instrument 43-101 -
Standards of Disclosure for Mineral Projects
("NI 43-101") and Subpart 1300 of Regulation S-
K ("S-K 1300") with an updated mineral resource estimate is expected to be completed in Q4 2025. Below is a summary of additional work to be conducted.
Metallurgical
Improved geo-metallurgical analysis by increasing the range of materials tested to include grade (gold, silver, carbon and sulfur), spatial (elevation and
strike), and geologic domains.
Additional CIL testing to improve the gold extraction relationships.
Comminution testing examining the SAG and ball mill work index.
Infill the drill hole database with TOC and sulfur assays.
Conduct arsenic and mercury assays on all samples employed for metallurgical testing.
Technical Disclosure and Qualified Persons
The PEA was prepared in accordance with NI 43-101. The PEA will be filed within 45 days of the date of this press release under the Company's issuer profile on
SEDAR+ at
www.sedarplus.ca
. An Initial Assessment for the Granite Creek Open Pit Project ("S-K 1300 Report") was also prepared in accordance with S-K
1300 and Item 601 of the Regulation S-K and the S-K 1300 Report will be filed on EDGAR at
www.sec.gov
. Both reports will be available on the Company's
website at
www.i80gold.com
. The mineral estimates and project economics are the same under the PEA and the S-K 1300 Report.
The technical information contained in this press release has been prepared under the supervision of, and has been reviewed and approved by
Terre Lane
(SME
No. 4053005 / MMSA No. 01407QP) of Global Resource Engineering ("GRE"), and Tyler Hill CPG., Vice President Geology for the Company, who are all
qualified persons within the meaning of NI 43-101 and S-K 1300.
For a description of the data verification, assay procedures and the quality assurance program and quality control measures applied by the Company, please see
the Company's Annual Information Form dated
March 12, 2024
filed under the Company's profile on SEDAR+ at
www.sedarplus.ca
and filed with the Company's
Form 40-F under the Company's profile on EDGAR at
www.sec.gov
. Further information about the PEA referenced in this news release, including information in
respect of data verification, key assumptions, parameters, risks and other factors, will be contained in the PEA.
The PEA is preliminary in nature and includes an economic analysis that is based, in part, on inferred mineral resources. Inferred mineral resources that are
considered too speculative geologically to have for the application of economic considerations applied to them that would enable them to be categorized as
mineral reserves, and there is no certainty that the results of the PEA will be realized. Mineral resources do not have demonstrated economic viability and are not
mineral reserves.
Endnotes
1
.
This is a non-IFRS/non-GAAP measure. Please see the section titled "Non-IFRS Performance Measures/Non-GAAP Financial Performance Measures"
below.
2
.
Cash flow and NPV are calculated as of the start of construction, which is anticipated to commence in early 2028, subject to obtaining the necessary permits
by
December 31, 2027
, as anticipated.
3
.
Turquoise Ridge Complex gold mineral resource estimate of approximately 20 million ounces (110 Mt at 5.42 g/t Au) as at
December 31, 2023
based on
publicly filed technical reports of Barrick Gold Corporation available on SEDAR+ at
www.sedarplus.ca
and
www.barrick.com
. No qualified person of the
Company has independently verified any mineral resource information in respect of the Turquoise Ridge Complex contained in this news release and such
information is not necessarily indicative of the mineralization on the property subject to such technical reports.
About i-80 Gold Corp.
i-80 Gold Corp. is a Nevada-focused mining company committed to building a mid-tier gold producer through a new development plan to advance its high-quality
asset portfolio. The Company is the fourth largest gold mineral resource holder in the state with a pipeline of high-grade development and production-stage
projects strategically located in Nevada's most prolific gold-producing trends. Leveraging its fully permitted central processing facility, i-80 Gold is executing a hub-
and-spoke regional mining and processing strategy to maximize efficiency and growth. i-80 Gold's shares are listed on the Toronto Stock Exchange (TSX: IAU)
and the NYSE American (NYSE: IAUX). For more information, visit
www.i80gold.com
.
Forward-Looking Information
Certain statements in this release constitute "forward-looking statements" or "forward-looking information" within the meaning of applicable securities laws,
including but not limited to, statements regarding the updated results of the PEA on the Project, such as future estimates of internal rates of return, net present
value, future production, estimates of cash cost, proposed mining plans and methods, mine life estimates, cash flow forecasts, metal recoveries, estimates of
capital and operating costs, timing for permitting and environmental assessments, timing, completion and results of feasibility studies, and the size and timing of
phased development of the Project. Furthermore, forward-looking statements are necessarily based upon a number of estimates and assumptions that, while
considered reasonable by the Company as of the date of such statements, are inherently subject to significant business, economic and competitive uncertainties
and contingencies. With respect to this specific forward-looking information concerning the development of the Project, the Company has based its assumptions
and analysis on certain factors that are inherently uncertain. Uncertainties include: (i) the adequacy of infrastructure; (ii) geological characteristics; (iii) metallurgical
characteristics of the mineralization; (iv) the ability to develop adequate processing capacity; (v) the price of gold, silver and other commodities; (vi) the availability
of equipment and facilities necessary to complete development; (vii) the cost of consumables and mining and processing equipment; (viii) unforeseen technological
and engineering problems; (ix) natural disasters and/or accidents; * currency fluctuations; (xi) changes in regulations; (xii) the compliance by and/or key suppliers
with terms of agreements; (xiii) the availability and productivity of skilled labour; (xiv) the regulation of the mining industry by various governmental agencies,
including permitting and environmental assessments; (xv) the ability to raise sufficient capital to develop such projects; (xiv) changes in project scope or design;
and (xv) political factors.
Such statements can be identified by the use of words such as "may", "would", "could", "will", "intend", "expect", "believe", "plan", "anticipate", "estimate",
"scheduled", "forecast", "predict" and other similar terminology, or state that certain actions, events or results "may", "could", "would", "might" or "will" be taken,
occur or be achieved. These statements reflect the Company's current expectations regarding future events, performance and results and speak only as of the
date of this release and are expressly qualified in their entirety by this cautionary statement. Subject to applicable securities laws, the Company does not assume
any obligation to update or revise the forward-looking statements contained herein to reflect events or circumstances occurring after the date of this release.
This release also contains references to estimates of mineral resources. The estimation of mineral resources is inherently uncertain and involves subjective
judgments about many relevant factors. Mineral resources that are not mineral reserves do not have demonstrated economic viability. The accuracy of any such
estimates is a function of the quantity and quality of available data, and of the assumptions made and judgments used in engineering and geological interpretation
(including estimated future production from the Project, the anticipated tonnages and grades that will be mined and the estimated level of recovery that will be
realized), which may prove to be unreliable and depend, to a certain extent, upon the analysis of drilling results and statistical inferences that may ultimately prove
to be inaccurate. Mineral resource estimates may have to be re-estimated based on: (i) fluctuations in commodities prices; (ii) results of drilling, (iii) metallurgical
testing and other studies; (iv) proposed mining operations, including dilution; (v) the evaluation of mine plans subsequent to the date of any estimates; and (vi) the
possible failure to receive required permits, approvals and licenses or changes to existing mining licenses.
Forward-looking statements and information involve significant known and unknown risks and uncertainties, should not be read as guarantees of future
performance or results and will not necessarily be accurate indicators of whether or not such results will be achieved. A number of factors could cause actual
results to differ materially from the results expressed or implied by such forward-looking statements or information, including, but not limited to: the Company's
ability to finance the development of its mineral properties; assumptions and discount rates being appropriately applied to the PEA and S-K 1300 Report,
uncertainty as to whether there will ever be production at the Company's mineral exploration and development properties; risks related to the Company's ability to
commence production at the Project and generate material revenues or obtain adequate financing for its planned exploration and development activities;
uncertainties relating to the assumptions underlying resource and reserve estimates; mining and development risks, including risks related to infrastructure,
accidents, equipment breakdowns, labour disputes, bad weather, non-compliance with environmental and permit requirements or other unanticipated difficulties
with or interruptions in development, construction or production; the geology, grade and continuity of the Company's mineral deposits; the uncertainties involving
success of exploration, development and mining activities; permitting timelines; government regulation of mining operations; environmental risks; unanticipated
reclamation expenses; prices for energy inputs, labour, materials, supplies and services; uncertainties involved in the interpretation of drilling results and geological
tests and the estimation of reserves and resources; unexpected cost increases in estimated capital and operating costs; the need to obtain permits and
government approvals; material adverse changes, unexpected changes in laws, rules or regulations, or their enforcement by applicable authorities; the failure of
parties to contracts with the company to perform as agreed; social or labour unrest; changes in commodity prices; and the failure of exploration programs or
studies to deliver anticipated results or results that would justify and support continued exploration, studies, development or operations. For a more detailed
discussion of such risks and other factors that could cause actual results to differ materially from those expressed or implied by such forward-looking statements,
refer to i-80 Gold's filings with Canadian securities regulators, including the most recent Annual Information Form, available on SEDAR+ at
www.sedarplus.ca
.
Non-IFRS/Non-GAAP Financial Performance Measures
The Company has included certain terms or performance measures in this news release that commonly used in the gold mining industry that are not defined under
International Financial Reporting Standards ("IFRS") or United States Generally Accepted Accounting Principles ("US GAAP"). This includes: all-in sustaining costs
per ounce and cash cost per ounce. Non-IFRS/Non-GAAP financial performance measures do not have any standardized meaning prescribed under IFRS or US
GAAP, and therefore, they may not be comparable to similar measures employed by other companies. The data presented is intended to provide additional
information and should not be considered in isolation or as a substitute for measures prepared in accordance with IFRS US GAAP and should be read in
conjunction with the Company's financial statements. Because the Company has provided these measures on a forward-looking basis, it is unable to present a
quantitative reconciliation to the most directly comparable financial measure calculated and presented in accordance with IFRS or US GAAP without unreasonable
efforts. This is due to the inherent difficulty of forecasting the timing or amount of various reconciling items that would impact the most directly comparable
forward-looking IFRS or US GAAP measure that have not yet occurred, are outside of the Company's control and/or cannot be reasonably predicted.
Definitions
"All-in sustaining costs" is a non-IFRS or US GAAP financial measure calculated based on guidance published by the World Gold Council ("WGC"). The WGC is a
market development organization for the gold industry and is an association whose membership comprises leading gold mining companies. Although the WGC is
not a mining industry regulatory organization, it worked closely with its member companies to develop these metrics. Adoption of the all-in sustaining cost metric is
voluntary and not necessarily standard, and therefore, this measure presented by the Company may not be comparable to similar measures presented by other
issuers. The Company believes that the all-in sustaining cost measure complements existing measures and ratios reported by the Company. All-in sustaining cost
includes both operating and capital costs required to sustain gold production on an ongoing basis. Sustaining operating costs represent expenditures expected to
be incurred at the Project that are considered necessary to maintain production. Sustaining capital represents expected capital expenditures comprising mine
development costs, including capitalized waste, and ongoing replacement of mine equipment and other capital facilities, and does not include expected capital
expenditures for major growth projects or enhancement capital for significant infrastructure improvements.
"Cash cost per gold ounce" is a common financial performance measure in the gold mining industry but has no standard meaning under IFRS or US GAAP. The
Company believes that, in addition to conventional measures prepared in accordance with IFRS or US GAAP, certain investors use this information to evaluate the
Company's performance and ability to generate cash flow. Cash cost figures are calculated in accordance with a standard developed by The Gold Institute. The
Gold Institute ceased operations in 2002, but the standard is considered the accepted standard of reporting cash cost of production in North America. Adoption of
the standard is voluntary, and the cost measures presented may not be comparable to other similarly titled measures of other companies.
For a more detailed breakdown on how these measures were calculated, please see the table below:
Total Costs
Unit Cost
Cost per Ounce
($M)
($/t )
($/oz Au)
Mining
$764.4
$21.93
$632
Processing
$412.3
$11.83
$341
G&A
$63.9
$1.83
$53
Refining, Royalties & Net Proceeds Tax
$193.3
$5.55
$160
Total Operating Cost/Cash Costs
(1)
$2,511.0
$40.8
$1,185
Closure & Reclamation
$18.00
$0.5
$15
Sustaining Capital
$30.3
$0.9
$25
All-in Sustaining Costs
(1)
$1,482.3
$42.5
$1,225
APPENDIX
Granite Creek Open Pit Project Detailed Cash Flow Model
Granite Creek Open Pit
UNITS
TOTAL / LOM
2028E
2029E
2030E
2031E
2032E
2033E
2034E
2035E
2036E
2037E
2038E
2039E
2040E
2041E
MINING
Mine Life
Years
~10
Mineralized Material Mined
k tonnes
34,854.5
291
4,511
4,110
4,091
3,739
1,531
4,954
4,333
5,483
1,812
-
-
Expensed Waste Moved
k tonnes
287,352.9
-
25,936
47,957
36,314
35,287
31,497
50,415
33,147
24,739
2,061
-
-
k tonnes
Total Moved
k tonnes
322,207
-
291
30,447
52,066
40,405
39,026
33,028
55,369
37,480
30,222
3,873
-
-
Strip Ratio
(Excluding Capitalized Strip.)
(waste:mineralized material)
8.2:1
0
5.7:1
11.7:1
8.9:1
9.4:1
20.6:1
10.2:1
7.6:1
4.5:1
1.1:1
Strip Ratio
(Including Capitalized Strip.)
(waste:mineralized material)
8.9:1
44.4:1
7.8:1
11.7:1
8.9:1
9.4:1
20.6:1
10.2:1
7.6:1
4.5:1
1.1:1
Daily Mining Rate
(Mineralized Material)
tpd
10,291.7
-
798
12,360
11,259
11,207
10,244
4,195
13,572
11,871
15,022
4,963
-
-
Capitalized Mining
k tonnes
17,637.7
12,937
4,701
-
-
-
-
-
-
-
-
-
-
PROCESSING
Total Material for Processing
k tonnes
34,854
-
-
2,188
3,500
3,500
3,500
3,500
3,500
3,500
3,500
3,500
3,500
1,167
Au Average Grade
g/t Au
1.25
-
-
1.87
1.28
1.27
1.03
0.88
1.48
1.75
1.64
1.21
0.53
0.53
Contained Gold
'000 oz Au
1,397
-
-
131.7
144.5
142.8
115.6
99.0
166.6
196.9
184.3
136.2
59.8
19.9
CIL Processing
Total Tonnes Processed
k tonnes
34,854
2,188
3,500
3,500
3,500
3,500
3,500
3,500
3,500
3,500
3,500
1,167
Gold Grade
g/t Au
1.25
-
-
1.87
1.28
1.27
1.03
0.88
1.48
1.75
1.64
1.21
0.53
0.53
Silver Grade
g/t Au
0.00
-
-
-
-
-
-
-
-
-
-
-
-
-
Contained Gold
'000 oz Au
1,397
131.7
144.5
142.8
115.6
99.0
166.6
196.9
184.3
136.2
59.8
19.9
Recovered Gold
'000 oz Au
1,210
113.8
125.8
123.8
100.2
85.6
145.4
170.7
159.5
117.6
51.0
17.0
Recovered Silver
'000 oz Ag
-
Total Tonnes Processed
k tonnes
34,854
-
-
2,187.5
3,500.0
3,500.0
3,500.0
3,500.0
3,500.0
3,500.0
3,500.0
3,500.0
3,500.0
1,167.0
Total Gold Production
'000 oz Au
1,210
-
-
113.8
125.8
123.8
100.2
85.6
145.4
170.7
159.5
117.6
51.0
17.0
REVENUE
Gold Price
US$/oz Au
$2,175
$2,175
$2,175
$2,175
$2,175
$2,175
$2,175
$2,175
$2,175
$2,175
$2,175
$2,175
$2,175
Silver Price
US$/oz Ag
$27.25
$27.25
$27.25
$27.25
$27.25
$27.25
$27.25
$27.25
$27.25
$27.25
$27.25
$27.25
$27.25
Gold Revenues
US$M
$2,632.7
-
-
$248
$274
$269
$218
$186
$316
$371
$347
$256
$111
$37
Silver Revenue
$0.0
-
-
-
-
-
-
-
-
-
-
-
-
-
Total Revenue
$2,632.7
-
-
$248
$274
$269
$218
$186
$316
$371
$347
$256
$111
$37
OPERATING COSTS
Mining Costs (all)
US$M
$764.4
$69.0
$103.9
$94.2
$91.3
$95.1
$117.5
$90.0
$85.0
$18.5
-
-
CIL Processing
US$M
$412.3
-
$25.0
$41.5
$41.2
$42.0
$42.4
$41.3
$39.9
$39.8
$41.5
$43.2
$14.4
G&A
US$M
$63.9
$7.1
$7.1
$7.1
$7.1
$6.9
$7.1
$7.1
$7.1
$4.6
$1.6
$1.1
Total Operating Cost
US$M
$1,240.7
-
-
$101.2
$152.5
$142.5
$140.4
$144.4
$165.9
$137.0
$131.9
$64.6
$44.8
$15.5
Refining & Sales
US$M
$6.1
-
$0.6
$0.6
$0.6
$0.5
$0.4
$0.7
$0.9
$0.8
$0.6
$0.3
$0.1
Royalties & State Taxes
US$M
$187.3
$20.8
$21.9
$20.0
$15.1
$12.2
$21.7
$24.9
$22.3
$18.3
$7.5
$2.4
Mining costs
(Mineralized Material)
US$/t mined
$21.93
-
-
$15.30
$25.28
$23.02
$24.41
$62.11
$23.72
$20.76
$15.51
$10.21
-
-
Mining Costs
(Mineralized Mat'l & Waste)
US$/t mined
$2.37
-
-
$2.27
$2.00
$2.33
$2.34
$2.88
$2.12
$2.40
$2.81
$4.78
-
-
Mining costs
(ore & waste )
US$/t mined
$2.37
-
-
$2.27
$2.00
$2.33
$2.34
$2.88
$2.12
$2.40
$2.81
$4.78
-
-
Processing
US$/t process.
$11.83
-
-
$11.45
$11.85
$11.78
$12.01
$12.11
$11.81
$11.40
$11.37
$11.86
$12.36
$12.36
G&A
US$/t process.
$1.83
-
-
$3.25
$2.03
$2.03
$2.03
$1.97
$2.03
$2.03
$2.03
$1.31
$0.45
$0.97
Total
US$/t process.
$35.6
-
-
$46.25
$43.56
$40.72
$40.11
$41.25
$47.41
$39.13
$37.69
$18.45
$12.80
$13.32
CAPITAL EXPENDITURES
Contingent. Payments
US$M
$0
Permitting
US$M
$10.0
$5.0
$5.0
Capitalized Stripping
US$M
$33.9
-
$25.4
$8.5
-
-
-
-
-
-
-
-
-
-
Initial & Construction Capital
US$M
$200.2
$97.5
$102.7
-
-
-
-
-
-
-
-
-
-
-
-
Sustaining Capital
US$M
$30.3
-
$0.1
$0.0
$0.0
$1.2
$5.8
$5.8
$5.8
$5.8
$5.8
$0.1
$0.0
$0.0
-
Total Capital
US$M
$274.4
$102.5
$133.1
$8.5
$0.0
$1.2
$5.8
$5.8
$5.8
$5.8
$5.8
$0.1
$0.0
$0.0
-
Reclamation & Surety
US$M
$18.0
-
-
-
-
-
-
-
-
-
-
-
-
$9.0
$9.0
CASH COSTS & AISC
Total Cash Costs (Inc. Royalty)
US$/oz
$1,185
-
-
$1,077
$1,392
$1,317
$1,557
$1,834
$1,296
$953
$972
$710
$1,031
$1,059
-
All-in Sustaining Costs
(1)
US$/oz
$1,225
-
-
$1,077
$1,392
$1,327
$1,614
$1,901
$1,336
$987
$1,008
$710
$1,031
$1,590
-
CASH FLOW ANALYSIS
Revenue
US$M
$2,632.7
-
-
$248
$274
$269
$218
$186
$316
$371
$347
$256
$111
$37
-
Operating Costs Gold & Royalties
US$M
($1,434.0)
-
-
($123)
($175)
($163)
($156)
($157)
($188)
($163)
($155)
($83)
($53)
($18)
-
Depreciation
US$M
($255.8)
-
-
($20.4)
($23.5)
($23.2)
($18.9)
($16.8)
($29.8)
($36.9)
($37.1)
($31.0)
($13.5)
($4.5)
-
Net Operating Income (Pre-Tax)
US$M
$943.0
-
-
$105
$75
$83
$43
$12
$98
$172
$155
$141
$45
$14
-
Income Taxes & 10% NPI
(2)
US$M
($245.5)
-
-
($16)
($12)
($23)
($12)
($6)
($28)
($49)
($43)
($41)
($12)
($3)
-
Net Income
US$M
$697.5
-
-
$89
$63
$60
$31
$7
$70
$122
$111
$101
$33
$11
-
Depreciation & Depletion
US$M
$255.8
$20.4
$23.5
$23.2
$18.9
$16.8
$29.8
$36.9
$37.1
$31.0
$13.5
$4.5
-
Reclamation
US$M
($18.0)
-
-
-
-
-
-
-
-
-
-
-
($9.0)
($9.0)
Operating Cash Flow
US$M
$1,035.3
-
-
$109
$87
$95
$57
$27
$113
$180
$167
$149
$53
$8
($9)
Capital Expenditures
US$M
($274.4)
($103)
($133)
($9)
($0)
($1)
($6)
($6)
($6)
($6)
($6)
($0)
($0)
($0)
-
NET CASH FLOW
US$M
$660.9
($102.5)
($133.1)
$100.6
$86.1
$82.2
$44.2
$17.7
$93.8
$153.4
$142.7
$131.5
$46.7
$6.5
($9.0)
PROJECT ECONOMICS (as of Jan. 1 2028)
After-tax NPV 5%
discounting
US$M
$421.2
30 %
Notes to table above:
(1) AISC annual calculations are on a cash basis rather than on an accrual basis. As such, the weighted average of the annual AISC amounts will not agree to the life of mine AISC.
(2) Includes a 10% net profits interest to Gold Royalty Corp.
View original content to download multimedia:
https://www.prnewswire.com/news-releases/i-80-gold-announces-positive-preliminary-economic-assessment-on-the-granite-creek-open-pit-project-nevada-after-tax-npv5-of-421-million-with-an-after-tax-irr-of-30-at-us2-175oz-au-302394446.html
SOURCE
i-80 Gold Corp
View original content to download multimedia:
http://www.newswire.ca/en/releases/archive/March2025/06/c5415.html
%SEDAR: 00052022E
For further information:
For further information, please contact: Leily Omoumi, VP Corporate Development & Strategy, 1.866.525.6450, [email protected],
www.i80gold.com
CO: i-80 Gold Corp
CNW 06:00e 06-MAR-25