Saturday, September 26, 2026
MiningNewsTerminal
Saturday, September 26, 2026 Admin

IAU.TO ·

i-80 Gold Announces Lone Tree Plant Refurbishment Update; Study Highlights Material Increase in Margins and Short Payback Period Refurbishing and commissioning the Lone Tree Plant marks a key milestone in i-80 Gold's phase one growth plan

Mine Development & Operations Metallurgy & Processing

i-80 Gold Announces Lone Tree Plant Refurbishment Update; Study

Highlights Material Increase in Margins and Short Payback Period

Refurbishing and commissioning the Lone Tree Plant marks a key milestone in

i-80 Gold's phase one growth plan

TORONTO

,

Dec. 18, 2025

/CNW/ -

i-80 GOLD CORP.

(TSX: IAU) (NYSE American: IAUX)

("i-80 Gold", or the "Company")

is pleased to announce the results

of an engineering study (the "Study" or the "Engineering Study") for the refurbishment of its Lone Tree Plant ("Lone Tree Plant" or the "Plant") located in

Northern

Nevada, USA

. i-80 Gold is one of two gold companies in

Nevada

with an autoclave processing plant. As part of i-80 Gold's development plan, the Lone Tree Plant

is expected to serve as a central hub for processing refractory material from the Company's three high-grade underground mines: Granite Creek, Archimedes,

and Cove (see Figure 1 in Appendix).

Figure 1: Regional map of Lone Tree Plant and i-80 Gold’s regional projects in Northern Nevada, USA (CNW Group/i-80 Gold Corp)

"The Lone Tree Plant is a cornerstone asset within phase one of i-80 Gold's development plan," stated

Richard Young

, President & Chief Executive

Officer. "Refurbishing the Lone Tree Plant marks a major step forward in our goal of creating a mid-tier gold producer by enabling us to transition from toll-milling

to an owner-operator processing model. This change is expected to significantly increase margins and free cash flow generation. In addition to advancing the

development plan, we are progressing well on our recapitalization plan with ongoing engagement from debt and royalty providers, as well as preliminary interest in

our non-core asset sale. We are encouraged by the overall progress and are on track to complete the recapitalization process before the end of the second

quarter of 2026 or earlier."

The Study was completed by Hatch Ltd. ("Hatch"), an industry leader in autoclave technology design, and builds on a previous internal engineering study

completed by Hatch in 2023. Hatch's responsibilities in this Study included the engineering of the refurbishment design and the capital costs; while i-80 Gold is

responsible for completing the associated mine plan basis, metallurgical test work, recovery analysis, operating cost estimates (based on the Hatch design and

detailed mass balance), and economic analysis.

Highlights

All amounts are expressed in

United States

dollars unless otherwise stated.

Nameplate capacity of 2,268 tonnes per day or 827,806 tonnes per annum, consistent with historic production data, with integrated pressure oxidation

("POX") and carbon-in-leach ("CIL") circuits capable of processing both refractory (sulfide) and non-refractory (oxide) mineralized material.

Scope of work includes the replacement and refurbishment of some existing infrastructure, and the installation of new infrastructure, equipment and

environmental systems, including the refurbishment and upgrade of the existing autoclave to a modern POX circuit.

Capital cost estimate (AACE Class 3) of

$412 million

, inclusive of contingency, owner's costs, and first fills, plus

$18 million

in capital spares for a total of

$430 million

. The estimate is higher than the anticipated amount of approximately

$400 million

, largely due to increased costs associated with inflation and

engineering design details, and additional redundancy by expanding the capacity of the filtered tailings system. This may allow for operational and throughput

flexibility, both of which could ultimately increase throughput by allowing for processing of oxidized material during planned maintenance outages of the

autoclave.

Potential short payback period of 12 to 24 months depending on the grade processed and gold price.

Early works activities have commenced under a limited notice-to-proceed granted by the Board of i-80 Gold. A construction decision is expected once the

recapitalization is complete. Upon the approval of associated permits, construction activities are anticipated to commence in the second half of 2026 with

plant commissioning anticipated at the end of 2027.

Transitioning from a toll-milling to owner-operated processing scenario is expected to reduce current processing costs to approximately one third, resulting in

an estimated margin increase of approximately

$1,000

to

$1,500

per ounce of gold (depending on grade and gold price).

On track for the completion of engineering designs associated with construction and environmental permits in the fourth quarter of 2025 with permitting

applications projected to be submitted in the first quarter of 2026 following the internal review process.

i-80 Gold is one of two gold companies in

Nevada

with an autoclave facility, the other is

Nevada Gold Mines

("NGM"), a joint venture between Barrick Mining

Corporation and Newmont Corporation.

"The engineering study confirms that the Lone Tree Plant refurbishment incorporates standard, technically straightforward upgrades designed to improve

operating efficiency," stated

Paul Chawrun

, Chief Operating Officer. "Importantly, the planned work represents low execution risk as demonstrated by the modest

number of direct construction hours, the minimal requirement for long-lead equipment, and the Plant's location within a mature, best-in-class mining district. With

approximately 30% of detailed engineering now complete, this level of technical definition provides significantly improved accuracy in our capital cost estimate."

Mr. Chawrun added, "In addition to working with Hatch – a globally recognized engineering firm with deep expertise in autoclave design and technology – our

internal technical team brings extensive experience in refractory gold metallurgy, and the construction and operation of POX autoclave facilities, gained through

leadership roles at large-scale Nevada gold operations. The combination of detailed engineering, cost definition, and proven internal and external expertise

positions us to confidently advance the Lone Tree Plant refurbishment toward execution as a key component of i-80 Gold's growth strategy."

A video overview of the Lone Tree refurbishment plan is available by clicking here:

https://vrify.com/decks/20657

Scope of Work

The scope of refurbishment work includes a combination of new and improved design components and the replacement of some existing infrastructure aimed at

modernizing the Plant to improve process efficiency and operating flexibility, and additionally to meet new environmental compliance standards (see Figures 2 and

3 in Appendix).

This includes the demolition of certain equipment, such as legacy CIL tanks, oxygen plant and refinery, and the construction, replacement, and addition of

equipment, such as an upgraded mercury abatement circuit to meet updated environmental regulations (see Figures 4 to 7 in Appendix).

A central component of the Study is upgrading the existing autoclave circuit to convert it to a modern POX circuit within the overall flowsheet design for improved

operating efficiency (see Figure 8 in Appendix). The SAG and ball mills are also planned to feature a new modern control system.

Another key component is the addition of a tailings filtration system. This change resulted in the addition of several circuits, including filtration, water treatment for

water recirculation, a modified cyanide destruction circuit, and POX off-gas water system changes. When compared to conventional tailings storage, a filtered

tailings system is a more environmentally responsible tailings design that allows for increased water recovery, a smaller environmental footprint, and a lower cost

at closure associated with a simpler reclamation design.

A new oxygen plant design has also been incorporated to meet updated processing requirements, while further reducing project risk from previous studies where

refurbishment of the existing oxygen plant was considered. The oxygen plant is expected to be operated by a third-party through an over-the-fence supply

contract.

Overall, the Lone Tree Plant refurbishment is estimated to require approximately 600,000 direct construction hours, with peak workforce of about 400 construction

personnel, which suggests a relatively low overall construction intensity when compared to greenfield mine capital projects.

The project will be overseen by an experienced Nevada-based owners' team to work jointly with the Hatch EPCM team, each with a proven track record in the

construction and commissioning of autoclave processing facilities and will be supported by highly skilled local contractors. The internal team also brings extensive

experience operating and managing autoclave facilities at large-scale gold operations in

Nevada

.

Processing

The Lone Tree autoclave plans to process up to 2,268 tonnes per day with total annual throughput of 827,806 tonnes based on 85% plant availability, consistent

with historic production data.

The feed to the autoclave will consist of refractory material from i-80 Gold's three planned high-grade underground mines: Granite Creek, which is currently in

commissioning, Archimedes, where construction recently commenced, and Cove, which is advancing toward feasibility and permitting (see Figure 10 in Appendix).

The Plant is designed to process refractory material using the integrated POX-CIL processing stream, along with high grade oxide material, in which case the

POX circuit is bypassed, and the material is processed solely in the CIL circuit after grinding (see Figures 8 and 9 in Appendix). This flexibility allows the treatment

of mineralized material to be optimized with the lowest cost and highest recovery rate. Bypassing the POX circuit (autoclave) when processing oxide material has

the potential to increase throughput capacity by between 5% and 10% above the nameplate capacity.

The updated design incorporates an acid-based POX process, whereas previously both acid and alkaline processes were incorporated into the design. The acid-

based POX is expected to improve the overall gold recovery rates compared to the alkaline process, offsetting the increased operating costs associated with the

acid environment.

Capital Cost

Over the past several years, extensive engineering reviews, operating assessments, and trade-off studies have been completed to optimize project capital and

identify opportunities to bring forward Lone Tree's development timeline. The estimate has been developed to an AACE Class 3 level of definition. The estimate is

modestly higher than the anticipated amount of approximately

$400 million

, largely due to increased costs associated with inflation and engineering design details,

and additional redundancy by expanding the capacity of the filtered tailings system. This may allow for operational and throughput flexibility, both of which could

ultimately increase throughput by allowing for processing of oxidized material during planned maintenance outages of the autoclave. See Table 1 below for a

summary of capital cost estimates by activity.

Table 1: Capital Cost Summary

US$ Millions

Direct Costs

POX and POX Utilities

$86

Tailings Filtration

$50

Reagents and Utilities

$39

Neutralization, CIL, Cyanide Destruction

$28

Power and Electrical

$20

Refinery

$16

Grinding Circuit

$14

Subtotal Direct Costs

$253

Indirect Costs

EPCM

$66

Construction Indirects

$17

First Fills/Freight

$8

Subtotal Indirect Costs

$91

Total Direct + Indirect Costs

$343

Contingency (~12%)

(1)

$43

Owner's Cost

$25

Subtotal Cost

(Excluding Capital Spares)

$412

Capital Spares

$18

Total Project Cost

$430

Notes to table above:

Numbers do not sum due to rounding.

(1) Contingency of approximately 12% for total direct and indirect cost.

i-80 Gold continues to advance its recapitalization plan to support the Company's growth strategy. The Company is currently in active discussions with several

parties regarding a potential combination of senior debt, a royalty sale, and non-core asset sale. The Company aims to complete its recapitalization plan by the

end of the second quarter of 2026 or earlier.

Permitting

The Plant is permitted for the existing operational components in use. The approval of new and revised permit applications pertaining to air quality, water pollution,

mercury abatement and reclamation management programs for the new Plant design remain outstanding. The Company is on track to complete the engineering

designs associated with the construction and environmental permits in the fourth quarter of 2025 with permitting applications projected to be submitted in the first

quarter of 2026 following the internal review process. Various construction activities will commence upon the approval of the associated permits and the

completion of required financing.

Timeline and Next Steps

In

August 2025

, the Board of i-80 Gold approved a limited notice to proceed with detailed engineering to allow for the procurement of long-lead equipment and the

commencement of permitting updates. A construction decision is expected once the recapitalization is complete, with demolition activities expected to commence

in the second quarter of 2026, followed by construction activities in the second half of 2026. For a schedule of refurbishment milestones see Figure 11 in the

Appendix.

Based on current forecasts, commissioning of the Lone Tree Plant is expected to begin in the fourth quarter of 2027. Upon the completion of the commissioning

phase, the Plant is anticipated to begin processing refractory material from the Company's Granite Creek and Archimedes underground mines. Prior to the Plant's

commissioning, both underground projects are expected to process refractory material under a third-party autoclave toll-milling agreement.

About the Lone Tree Property

The Lone Tree property is located immediately adjacent to Interstate 80 (I-80). The Lone Tree Plant is a legacy asset with significant existing infrastructure. It

was initially commissioned in 1991 by Santa Fe Pacific Gold, which was acquired by Newmont Corporation in 1997. The Plant's POX circuit started in 1993 and

operated for 14 years until being put on care and maintenance in 2007. It became part of NGM in

July 2019

through the joint venture created between Barrick

Mining and Newmont Corporation. i-80 Gold acquired the Lone Tree property from NGM in

October 2021

. Following the acquisition, the Plant remained on care

and maintenance, while residual leaching of the historic Lone Tree heap leach has continued.

In addition to the processing facilities, the Lone Tree land package includes the Lone Tree open pit, the Buffalo Mountain deposit, and the Brooks open pit mine,

which are also currently on care and maintenance.

The past-producing Lone Tree open pit deposit has defined resources which may be integrated into the Company's future production plans. While not part of the

current development plan, the Lone Tree Open Pit may be re-permitted and supplement the high-grade underground feed in the later years of the underground

mines, subject to permitting, technical studies, and economic evaluation.

Conference Call & Webcast

Management will host a conference call and webcast tomorrow morning to discuss the updates for the Lone Tree refurbishment and the Company's

recapitalization plan, followed by a question-and-answer session. The participation details are as follows:

Date:

December 19, 2025

Time:

9:00 a.m. ET

Webcast:

https://app.webinar.net/xQBabambrnk

The webcast replay will be available for 12 months after the event.

Telephone:

Local or International +1-416-945-7677 North America Toll-free 1-888-699-1199

Replay:

Local or International +1-289-819-1450 North America Toll-free 1-888-660-6345

Replay Code:

84202 #

The telephone replay will be available for 7 days after the event.

Technical Disclosure and Qualified Persons

The Study is a Class 3 engineering study which is a cost analysis and does not constitute a technical report nor a feasibility study each as defined under National

Instrument 43-101 – Standards of Disclosure for Mineral Projects or Subpart 1300 of Regulation S-K.

The technical information contained in this press release has been prepared under the supervision of and has been reviewed and approved by

Paul Chawrun

P.Eng

., Chief Operating Officer, and

Kenji Umeno

, P.Eng., Director of Metallurgy, for the Company, each of whom are qualified persons within the meaning of

National Instrument 43-101 - Standards of Disclosure for Mineral Projects and Subpart 1300 of Regulation S-K.

About i-80 Gold Corp.

i-80 Gold Corp. is a Nevada-focused mining company committed to building a mid-tier gold producer through a new development plan to advance its high-quality

asset portfolio. The Company is the fourth largest gold mineral resource holder in the state with a pipeline of high-grade development and production-stage

projects strategically located in Nevada's most prolific gold-producing trends. Leveraging its central processing facility following an anticipated refurbishment, i-80

Gold is executing a hub-and-spoke regional mining and processing strategy to maximize efficiency and growth. i-80 Gold's shares are listed on the Toronto Stock

Exchange (TSX:IAU) and the NYSE American (NYSE:IAUX). For more information, visit

www.i80gold.com

.

CAUTIONARY STATEMENT ON FORWARD LOOKING INFORMATION

Certain information set forth in this press release, including but not limited to management's assessment of the Company's future plans and operations, the

anticipated timing of permitting the project, a construction decision, construction and commissioning, the anticipated benefits of the refurbished processing plant

including to cash margins and recoveries, the anticipated cost and payback period of the refurbishment plan, the perceived merit of projects or deposits, and the

impact and anticipated timing of the Company's development plan and recapitalization plan, outlook on gold output, the anticipated growth expenditures, the

anticipated timing of permitting, production, project development or technical studies constitutes forward looking statements or forward-looking information within

the meaning of applicable securities laws. All statements other than statements of historical fact are forward-looking statements. Often, but not always, forward-

looking statements can be identified by the use of words such as "plans", "expects", "is expected", "budget", "scheduled", "estimates", "continues", "forecasts",

"projects", "predicts", "intends", "anticipates" or "believes", or variations of, or the negatives of, such words and phrases, or state that certain actions, events or

results "may", "could", "would", "should", "might" or "will" be taken, occur or be achieved. Readers are cautioned that the assumptions used in the preparation of

information, although considered reasonable at the time of preparation, may prove to be inaccurate and, as such, reliance should not be placed on forward-looking

statements. The Company's actual results, performance or achievement could differ materially from those expressed in, or implied by, these forward-looking

statements and, accordingly, no assurance can be given that any of the events anticipated by the forward-looking statements will transpire or occur, or if any of

them do so, what benefits, if any, that the Company will derive therefrom. By their nature, forward looking statements are subject to numerous risks and

uncertainties, some of which are beyond the Company's control, including general economic and industry conditions, volatility of commodity prices, timing of

permitting, title risks and uncertainties, ability to access sufficient capital from internal and external sources such as selling assets, restructuring debt or obtaining

additional equity capital on terms that may be onerous or highly dilutive. The Company's ability to refinance its indebtedness will depend on the capital markets

and its financial condition at such time, currency fluctuations, construction and operational risks, licensing and permit requirements, environmental risks,

competition from other industry participants, the lack of availability of qualified personnel or management, imprecision of mineral resource, or production

estimates.

Please see "Risks Factors" in the Form 10-K for the fiscal year ended

December 31, 2024

for more information regarding risks pertaining to the Company, which

is available on EDGAR at

www.sec.gov/edgar

and SEDAR+ at

www.sedarplus.ca

. Readers are encouraged to carefully review these risk factors as well as the

Company's other filings with the U.S. Securities and Exchange Commission and the Canadian Securities Administrators. All forward-looking statements contained

in this press release speak only as of the date of this press release or as of the dates specified in such statements. The Company disclaims any intention or

obligation to update or revise any forward-looking statements, whether as a result of new information, future events or otherwise except as required by applicable

law.

Additional information relating to i-80 Gold can be found on i-80 Gold's website at

www.i80gold.com

, SEDAR+ at

www.sedarplus.ca

, and on EDGAR at

www.sec.gov/edgar

.

APPENDIX

Figure 1:

Regional map of Lone Tree Plant and i-80 Gold's regional projects in

Northern Nevada, USA

Figure 2:

General overview of the existing Lone Tree Plant

Figure 3:

Scope of work for the Lone Tree Plant refurbishment

Figure 4:

POX autoclave upgrades

Figure 5:

POX mercury abatement system redesign

Figure 6:

CIL tank replacement

Figure 7:

New tailings filtration building

Figure 8:

Lone Tree mineral processing flowsheet

Figure 9:

New Lone Tree Plant layout

Figure 10:

i-80 Gold's three-phase development plan for its Nevada-based asset pipeline

Figure 11:

Schedule of major milestones for the Lone Tree Plant refurbishment

Figure 2: General overview of the existing Lone Tree Plant (CNW Group/i-80 Gold Corp)

Figure 3: Scope of work for the Lone Tree Plant refurbishment (CNW Group/i-80 Gold Corp)

Figure 4: POX autoclave upgrades (CNW Group/i-80 Gold Corp)

Figure 5: POX mercury abatement system redesign (CNW Group/i-80 Gold Corp)

Figure 6: CIL tank replacement (CNW Group/i-80 Gold Corp)

Figure 7: New tailings filtration building (CNW Group/i-80 Gold Corp)

Figure 8: Lone Tree mineral processing flowsheet (CNW Group/i-80 Gold Corp)

Figure 9: New Lone Tree Plant layout (CNW Group/i-80 Gold Corp)

Figure 10: i-80 Gold’s three-phase development plan for its Nevada-based asset pipeline (CNW Group/i-80 Gold Corp)

Figure 11: Schedule of major milestones for the Lone Tree Plant refurbishment (CNW Group/i-80 Gold Corp)

View original content to download multimedia:

https://www.prnewswire.com/news-releases/i-80-gold-announces-lone-tree-plant-refurbishment-update-study-highlights-material-increase-in-margins-and-short-payback-period-302646484.html

SOURCE

i-80 Gold Corp

View original content to download multimedia:

http://www.newswire.ca/en/releases/archive/December2025/18/c0087.html

%SEDAR: 00052022E

For further information:

For further information, please contact: Leily Omoumi, SVP Corporate Development & Strategy; Caterina De Rosa, Director Investor

Relations; 1.866.525.6450, [email protected], www.i80gold.com

CO: i-80 Gold Corp

CNW 19:05e 18-DEC-25