Heliostar Provides Progress Update on Ana Paula Feasibility Study

Corporate Updates

TSX.V: HSTR

OTCQX: HSTXF

Heliostar Provides Progress Update on Ana Paula

Feasibility Study

Highlights:

• Feasibility Study remains on track for completion in Q2 2027

• Targeting a mid-2027 construction decision, with first gold planned before the end of 2028

• Updated Mineral Resource estimate in final stages of completion

• Process flowsheet finalized with metallurgical test work substantially completed

• Permitting timelines progressing with no material delays

• Overall feasibility study is 34% complete with early work s evaluation, construction planning and

debt financing arrangement all underway

• Trade-off studies have focused on opportunities to improve project economics and extend mine life

Vancouver, Canada – September 21, 2026 – Heliostar Metals Ltd. (TSX.V: HSTR, OTCQX: HSTXF, FRA:

RGG1) (“Heliostar” or the “Company”) is pleased to provide details on the progress of key activities and

milestones for the planned development of the Ana Paula project.

Heliostar CEO, Charles Funk, commented, “ The Ana Paula Feasibility Study is the most significant new

value creation activity within Heliostar today. The study sets the design, operating plan, and cost of a

potential mine build that is planned to start in mid-2027. Earlier this year , we reorganized our executive

structure to prioritize development of Ana Paula, we remain on track to meet our Q2, 2027 Feasibility

Study timeline and are targeting a H2, 2028 first production goal. Delivering these milestones takes

Heliostar through the backend, production-growth portion of the Lassonde curve , a position which

historically has proven to be one of the most valuable share price drivers within the mining industry.”

“We have made significant progress on the study this year. We have completed drilling to support the

evaluation of the upper portion of the Ana Paula deposit and are nearing completion of the updated

mineral resource model and the metallurgical program. The mine, mill, and tailings facility workstreams

are each approximately 1/3 complete and progressing well, with the key permit submission due in the

coming weeks. We intend to provide milestone updates each quarter as we progress to wards our target

of building a highly profitable, ten -year mine averaging 100,000 produced gold ounces per year at Ana

Paula.”

Drill Program

The objectives of the drill program through the first half of 2026 at Ana Paula have been to support an

updated mineral resource estimate, provide material for additional metallurgical test work and for a

geotechnical site investigation.

Since the Preliminary Economic Assessment (“NI 43 -101 Technical Report Preliminary Economic

Assessment of the Ana Paula Project, Guerrero, Mexico” with effective date of November 6, 2025) 74

holes totalling 25,07 2 metres have been incorporated into the mineral resource estimate. This drilling

largely focused on the High Grade Panel, with additional drilling also directed to the Expansion Zone target

and other exploration targets north of the High Grade Panel. Total drilling completed to date is presented

2

595 Burrard Street, Suite 1723, Vancouver BC, V7X 1J1, Canada -- Tel +1 844 753 0045

TSX.V: HSTR, OTCQX: HSTXF, FRA: RGG1

in Table 1 below, which includes holes completed for resource definition, metallurgy, geotechnical

evaluation, and condemnation purposes.

Table 1 - Summary of Ana Paula Drilling

Phase # of Holes Hole

Size

Total

Metres

2025/2026 74 PQ, HQ 25,072

2026 - post resource cutoff 35 PQ, HQ 8,384

Condemnation 13 HQ 1,665

Total: 122 35,121

The High Grade Panel has been traced over a horizontal strike length of 300 metres , down-plunge over

330 metres and averages 50-60 metres thick in its core. The Expansion Zone currently extends up to 200

metres down-plunge of the High Grade Panel and remains open in multiple directions.

Parameters used in the mineral resource estimation remain similar to those used in the previous

Preliminary Economic Assessment (“PEA”). Final resource estimation domains are constrained by geologic

domains using an ordinary kriging algorithm. Search ellipses are oriented in the direction of the variogram

for each domain. Samples are composited two metres downhole by domain , and gold and silver grades

were capped after compositing by domain. A total of 11,843 density determinations were included in the

mineral resource estimate , and densities were estimated by domain using an inverse distance squared

algorithm.

Metallurgical Testing

Additional samples for metallurgical testing were collected from across the deposit during the Feasibility

Study drilling program. These samples were subject to metallurgical variability testing to refine recovery

and operating cost estimates and establish final BIOX design parameters. Early results confirm consistency

of the style of mineralization within the Ana Paula deposit.

All metallurgical work for the flotation circuit has been finalized. A bulk composite of flotation concentrate

is undergoing pilot plant-scale testing of the proposed bio-oxidation (“BiOX”) circuit and will be complete

in the coming weeks . Further variability testing of sub-batches of flotation concentrate is being

undertaken to define operating parameter ranges for the processing circuit . C ircuit optimizations are

planned to be completed in October 2026.

Initial results have been in line with earlier testing that supported the PEA, showing that the mineral ized

material is amenable to recovery using conventional grinding and flotation followed by bio-oxidation and

carbon-in-leach (“ CIL”) recovery from the flotation concentrate. Results remain in line with those

generated in the amenability testing completed during the PEA metallurgical program.

The Company intends to move from a fixed gold grade cut -off used in the PEA to a net smelter return

(“NSR”) model in the Feasibility Study. A variable gold grade cut-off model has been developed considering

the gold-to-sulfur ratio and additional factors including mineralization hardness and carbonate content.

The results of this work appear to support evaluation of a higher mill throughput than contemplated in

3

595 Burrard Street, Suite 1723, Vancouver BC, V7X 1J1, Canada -- Tel +1 844 753 0045

TSX.V: HSTR, OTCQX: HSTXF, FRA: RGG1

the PEA and a potential mid-life mill expansion that could increase production rates if supported by the

updated mineral resource estimate and Feasibility Study . Design work is underway to incorporate the

necessary flexibility in the plant layout to facilitate a future expansion should the updated resource

support that decision.

Engineering

Engineering activities continue to advance across multiple fronts to support the Feasibility Study. Overall

feasibility engineering progress is 34% complete and on track to deliver the Feasibility Study in Q2 2027.

The engineering work completed to date has supported the advancement of the project design, the

environmental permit submission, geotechnical design of the dry -stack tailing s storage facility and

supporting infrastructure design . Trade-off studies have been completed to support mine design

modifications that are being evaluated to potentially eliminate underground truck haulage, lower

development and mining costs, and reduce surface impacts of the project.

A number of optimization opportunities have been identified and are expected to be reflected in the

permit submission as part of the Company’s proposed plan for Ana Paula:

• Throughput Optimization – The process plant and associated infrastructure is now planned to run

at 2,000 tonnes per day (“tpd”) compared to the 1,800 tpd outlined in the PEA

• Expansion Opportunity – The comminution circuit will be sized to accommodate up to 2,500 tpd,

allowing for a potential staged expansion part way through the mine life

• Underground Access – An internal trade-off study indicates that placing the crusher underground

and conveying mineralized material to the plant through a second decline could have a notably

positive impact on project economics through operating cost savings. Capital increases from this

modification are anticipated to be minimal due to the offsetting reduction of removing the raise

bore and associated ventilation infrastructure considered in the PEA

• Mine Plan – Lower unit operating costs from trade-off optimizations and variable gold:sulfur ratio

analysis indicate potential for lower average cutoff grades in the Feasibility Study. The Company

is reviewing opportunities to modify the mine plan to evaluate potential improvements to Ana

Paula’s economics while seeking to maintain lowest quartile per -ounce costs. An internal mine

plan is expected to be completed in Q4 2026

Procurement activities for key long-lead items, including the primary and secondary crushers, the ball mill,

and the electrical transformer, are advancing through the vendor quotation process. This work is intended

to provide firm pricing and confirmed delivery schedules to support future procurement decisions and

project execution planning.

Heliostar plans to take advantage of its strong balance sheet and positive operating cash flow to place

firm orders for these items in Q4 2026. This is expected to support the target timeline for first gold before

the end of 2028, subject to completion of the Feasibility Study, financing and permitting.

4

595 Burrard Street, Suite 1723, Vancouver BC, V7X 1J1, Canada -- Tel +1 844 753 0045

TSX.V: HSTR, OTCQX: HSTXF, FRA: RGG1

Permitting

Ana Paula was previously permitted for an open pit mine plan (“2017 MIA”) that covers significant

infrastructure currently in place at the project. Heliostar is modifying the mine plan to an underground-

only mining operation. To support this approach, the submission of another environmental permit (“MIA-

R”) to the Secretariat of Environment and Natural Resources ( “SEMARNAT”, the permitting agency

responsible for the environmental permitting of mines in Mexico) will be undertaken by September or

October 2026, covering the proposed consolidated underground mining operation. The new underground

MIA-R reduces the amount of proposed surface disturbance by approximately 65% compared to the

previous open pit mining plan.

Key changes compared to the previous open pit permit include 1) reducing the size of the processing plant

and adjusting its location closer to the underground access portal, 2) adopting dry stack tailings to reduce

environmental risks and conform to industry -leading practices , and 3) proposing the use of tailings as

paste backfill for the underground, further reducing the surface footprint.

Supporting Permits Received – In the quarter, the Company received permissions for surface disturbance

to complete the ongoing condemnation drilling program for the proposed plant and tailings facility areas.

Water Supply – Heliostar has submitted a water concession application to CONAGUA to support the

project’s anticipated water requirements. The application includes seven potential locations for water

supply exploration as the Company continues to advance its water supply strategy for Ana Paula.

Power Supply – Heliostar has submitted a request to the Centro Nacional de Control de Energía

(“CENACE”), the decentralized public body responsible for operating Mexico’s national electric system and

wholesale electricity market) for the System Impact Study associated with the project’s anticipated power

requirements, advancing the assessment of the electrical infrastructure required to support the potential

future development of Ana Paula.

Local Engagement

In preparation for the next stages of development, Heliostar continues to build its long-term community

and environmental engagement in the area around the Ana Paula project. These programs are focused

on health, education, infrastructure, local economic development, and cultural engagement. These

initiatives are complemented by local supplier dev elopment, partnerships with government and

educational institutions, reforestation programs, and the establishment of a community brigade for

forest-fire prevention and control.

The Company is also building its Community Engagement and Development Management System. This

system includes establishing a comprehensive stakeholder map, performing social baseline studies, as

well as materiality and risk assessments. The aim of this system is to support s takeholder engagement

and support activities for economic development of communities surrounding the project.

Financing

Heliostar is planning to fund the Ana Paula construction and commissioning with a combination of

internally generated cash and new project debt . The Company is working with Hannam & Partners as

advisor to arrange the debt component of the financing plan and will be pursuing various non -dilutive

financing options during Q4 2026. The Company continues to forecast generating approximately $150

million of after-tax cash from its current operations through the next two years to support funding Ana

Paula. As of June 30, 2026, Heliostar had $43.0 million in cash and no debt.

5

595 Burrard Street, Suite 1723, Vancouver BC, V7X 1J1, Canada -- Tel +1 844 753 0045

TSX.V: HSTR, OTCQX: HSTXF, FRA: RGG1

Feasibility Study Next Steps

• Site Investigation – Continued condemnation and geotechnical drilling

• Permitting – Finalize and submit MIA-R permit application

• Metallurgy - Refine and optimize the process design parameters for the BIOX flow sheet and

design criteria

• Mine Design – Optimized stope designs and schedule based on updated cutoff grade criteria

• Water – Water test wells will be drilled following CONAGUA approval of the water concession

• Early Works - Evaluate opportunities to advance selected early works and construction-readiness

activities such as pre-development activities and site preparation

• Financing – Select a short list of preferred lenders to advance to detailed due diligence

• Community Engagement – Implementation of training programs supporting the development of

local vendors

Ana Paula Preliminary Economic Assessment Note

Heliostar announced the results of a Preliminary Economic Assessment on November 6, 2025. References

to the results in this release are provided in greater detail here. The PEA is preliminary in nature, includes

inferred mineral resources that are considered too speculative geologically to have economic

considerations applied to them that would enable them to be categorized as mineral reserves, and there

is no certainty that the PEA will be realized. Mineral resources are not mineral reserves and do not have

demonstrated economic viability.

Statement of Qualified Person

Gregg Bush, P.Eng., and Stewart Harris, P.Geo., Qualified Person s, as such term is defined by National

Instrument 43 -101 – Standards of Disclosure for Mineral Projects, ha ve reviewed the scientific and

technical information contained in this news release and have approved the disclosure herein. Mr. Bush

is employed as the COO, and Mr. Harris is employed as Exploration Manager of the Company.

About Heliostar Metals Ltd.

Heliostar is a growing gold producer with a goal to produce 500,000 ounces per year by the end of the

decade. The cash flow from the Company’s La Colorada Mine in Sonora and the San Agustin Mine in

Durango supports the development of its 100% owned pipeline of growth projects in Mexico and the USA.

These include the flagship Ana Paula development project in Guerrero, the Cerro del Gallo project in

Guanajuato, the San Antonio project in Baja Sur , the Goldstrike project in Utah and the Unga project in

Alaska.

FOR ADDITIONAL INFORMATION, PLEASE CONTACT:

Charles Funk

President and Chief Executive Officer

Heliostar Metals Limited

Email: [email protected]

Phone: +1 844-753-0045

Rob Grey

Investor Relations Manager

Heliostar Metals Limited

Email: [email protected]

Phone: +1 844-753-0045

6

595 Burrard Street, Suite 1723, Vancouver BC, V7X 1J1, Canada -- Tel +1 844 753 0045

TSX.V: HSTR, OTCQX: HSTXF, FRA: RGG1

Neither TSX Venture Exchange nor its Regulation Services Provider (as that term is defined in the policies

of the TSX Venture Exchange) accepts responsibility for the adequacy or accuracy of this release.

Cautionary Statement Regarding Forward-Looking Information

This news release includes certain "Forward–Looking Statements" within the meaning of the United States

Private Securities Litigation Reform Act of 1995 and "forward –looking information" under applicable

Canadian securities laws. When used in this news release, the words "anticipate", "believe", "estimate",

"expect", "target", "plan", "forecast", "may", "would", "could", "schedule" and similar words or

expressions, identify forward– looking statements or information. These forward– looking statements or

information relate to, among other things : the completion and results of the Ana Paula Feasibility Study;

the timing, scope and results of mineral resource estimation, metallurgical testing, engineering,

permitting, procurement, early works and financing activities; potential construction timing and first gold

production; potential mine life, production rates, throughput, operating costs, capital costs and project

economics; the Company’s forecast cash flows from operations; and the Company’s plans for quarterly

milestone updates.

Forward-looking statements and forward-looking information relating to the completion and results of the

Ana Paula Feasibility Study, potential development and construction of Ana Paula, timing of any first gold

production, project financing and debt arrangements, forecast cash flows from operations, liquidity, future

exploration and technical programs, and the timing and outcome of permitting processes are based on

management’s reasonable assumptions, estimates, expectations, analyses and opinions, which are based

on management’s experience and perception of trends, current conditions and expected developments,

and other factors that management believes are relevant and reasonable in the circumstances, but which

may prove to be incorrect. Assumptions have b een made regarding, among other things, the receipt of

necessary permits, approvals and financing;, price of metals; no escalation in the severity of public health

crises or ongoing military conflicts; costs of exploration and development; the estimated co sts of

development of exploration projects; and the Company’s ability to operate in a safe and effective manner

and its ability to obtain financing on reasonable terms.

These statements reflect the Company’s respective current views with respect to future events and are

necessarily based upon a number of other assumptions and estimates that, while considered reasonable

by management, are inherently subject to significant business, economic, competitive, political, and social

uncertainties and contingencies. Many factors, both known and unknown, could cause actual results,

performance, or achievements to be materially different from the results, performance or achievements

that are or may be expressed or implied by such forward– looking statements or forward-looking

information and the Company has made assumptions and estimates based on or related to many of these

factors. Such factors include, without limitation: precious me tals price volatility; risks associated with the

conduct of the Company’s mining activities in foreign jurisdictions; regulatory, consent or permitting

delays; risks relating to reliance on the Company’s management team and outside contractors; risks

regarding exploration and mining activities; the Company’s inability to obtain insurance to cover all risks,

on a commercially reasonable basis or at all; currency fluctuations; risks regarding the failure to generate

sufficient cash flow from operations; risks relating to project financing and equity issuances; risks and

unknowns inherent in all mining projects, including the inaccuracy of reserves and resources, metallurgical

recoveries and capital and operating costs of such projects; contests over title to properties, particularly

title to undeveloped properties; laws and regulations governing the environment, health and safety; the

ability of the communities in which the Company operates to manage and cope with the implications of

7

595 Burrard Street, Suite 1723, Vancouver BC, V7X 1J1, Canada -- Tel +1 844 753 0045

TSX.V: HSTR, OTCQX: HSTXF, FRA: RGG1

public health crises; the economic and financial implications of public health crises, ongoing military

conflicts and general economic factors to the Company; operating or technical difficulties in connection

with mining or development activities; employee relations, labour unrest or unavailability; the Company’s

interactions with surrounding communities; the Company’s ability to successfully integrate acquired

assets; the speculative nature of exploration and development, including the risks of diminishing quantities

or grades of reserves; stock market volatility; conflicts of interest among certain directors and officers; lack

of liquidity for shareholders of the Company; litigation risk; and the factors identified under the caption

“Risk Factors” in the C ompany’s public disclosure documents. Readers are cautioned against attributing

undue certainty to forward– looking statements or forward -looking information. Although the Company

has attempted to identify important factors that could cause actual results to differ materially, there may

be other factors that cause results not to be anticipated, estimated or intended. The Company does not

intend, and does not assume any obligation, to update these forward– looking statements or forward -

looking information to r eflect changes in assumptions or changes in circumstances or any other events

affecting such statements or information, other than as required by applicable law.