Saturday, September 26, 2026
MiningNewsTerminal
Saturday, September 26, 2026 Admin

HI.V ·

Highland Copper Identifies Key Optimization Opportunities Through Detailed Engineering at the Copperwood Project

Corporate Updates

June 3, 2026

TSX.V : HI | OTCQB : HDRSF Page 1 of 5

HIGHLAND COPPER IDENTIFIES KEY OPTIMIZATION OPPORTUNITIES THROUGH DETAILED

ENGINEERING AT THE COPPERWOOD PROJECT

VANCOUVER, BRITISH COLUMBIA – June 3, 2026 – Highland Copper Company Inc. (TSXV: HI; OTCQB:

HDRSF) ("Highland Copper" or “Highland” or the "Company") is pleased to provide an update on ongoing

engineering and project optimization efforts at its Copperwood project (“Copperwood” or the “ Project”)

located in Michigan, U.S.A . The results of the optimization work , including the previously announced

process plant redesign, are expected to be incorporated into an updated feasibility study (the “ Updated

FS”). This Updated FS will support project development planning and project financing initiatives.

Highlights:

• Evaluating Lower Cut-off Grades to Expand Mineable Resources: Ongoing studies are assessing

lower cut-off grades based on a long -term copper price of approximately US$4.80 per pound, with

the potential to convert additional Measured and Indicated Mineral Resources into mineable

reserves.

• Ore Sorting Technology to Unlock Additional Resource Potential : Bulk ore sorting technologies

are being evaluated to potentially incorporate the Upper Copper Bearing Sequence (" UCBS")

resource, which hosts 10.2 million tonnes in the Measured and Indicated category grading 1.1%

copper into future mine plans, increasing operational flexibility and expanding the project's

economic resource base.

• Geotechnical Studies Support Potential Mine Design Enhancements : Updated geotechnical

interpretations, combined with conventional room -and-pillar mining methods, may enable

optimization of mining heights and pillar dimensions while allowing dilution to be sourced from the

mineralized hanging wall rather than the floor.

• Simplified Process Plant Design Expected to Enhance Project Economics: Building on previously

announced metallurgical optimization work, the Updated FS is expected to incorporate a simplified

process flowsheet designed to reduce secondary milling requirements, lower energy and reagent

costs, decrease plant footprint, and most importantly, increase copper recoveries to 87.6%, relative

to 86.0% in the 2023 Feasibility Study.

• Updated FS Targeted for Q1 2027 : Given the improvement in long -term consensus copper prices

since the 2023 Feasibility Study, the Updated FS is expected to incorporate revised Mineral

Resources and Reserves, mine and process optimization initiatives, and updated capital and

operating costs, reflecting the significant advancement of the Copperwood Project.

• Advancing Towards Project Financing : Front-End Engineering and Design (“FEED”) advancing

toward 40% completion in 2026, positioning Copperwood for project financing and technical due

diligence activities.

Barry O’Shea, CEO of Highland Copper, stated, “As we continue our integrated mine plan review against a

backdrop of significantly improved long -term consensus copper prices, we are encouraged by the

TSX.V : HI | OTCQB : HDRSF Page 2 of 5

opportunities to further optimize Copperwood through mine design, processing, and engineering

enhancements. These initiatives have the potential to strengthen project economics and will be

incorporated into the updated feasibility study. With Copperwood advancing toward a construction

decision, the Project is entering an increasingly important stage of development at a time when few new

copper projects are positioned to come online in the United States in the near term. As demand for

domestically sourced critical minerals continues to grow, we believe Copperwood is strategically positioned

to play an important role in the future U.S. copper supply chain.”

Integrated Mine Plan Review

Following the successful redesign of the process plant flow sheet, the current focus on engineering is an

integrated mine plan review to evaluate potential optimizations to the mine plan, including revisions to cut-

off grade assumptions and geotechnical parameters. The integrated mine plan review will also conclude on

final design criteria and assumptions.

Evaluation of Reduced Cut-off Grade: At a long-term consensus copper price of approximately $4.80 per

pound, Highland is evaluating Copperwood Mineral Resources and Reserves at reduced cut -off grades

compared to cut-off grades applied in the Company’s 2023 Feasibility Study1. Early indications include the

potential addition of Measured and Indicated Resource s into the mine plan, although t he impact of this

change on Mineral Reserves has not yet been determined. The potential impact on Mineral Resources is

consistent with the sensitivity analyses presented in the 2023 Feasibility Study.

Evaluation of the Upper Copper Bearing Sequence (UCBS): The Company is also evaluating the potential

application of bulk ore sorting technologies to selectively reject lower-grade or barren material between the

Lower Copper Bearing Sequence (“ LCBS”) and Upper Copper Bearing Sequence (“ UCBS”). The current

Mineral Resource Estimate includes 54.2 million tonnes in the Measured and Indicated category at a 1.51%

copper grade. Of this, the UCBS represents 10.2 million tonnes in the Measured and Indicated category at a

1.1% copper grade, none of which is included in the reserve mine plan. At a reduced cut -off, and with the

benefit of bulk ore sorting, the UCBS may come into consideration from a mine plan perspective. This work

remains preliminary in nature, and there is no certainty that such technologies will be implemented or that

the UCBS may come into the mine plan.

Evaluation of Geotechnical Assumptions: As part of the integrated mine plan review, Highland is also

reconsidering Copperwood’s geotechnical assumptions. Geotechnical investigations completed to date,

including laboratory and field test work, which indicate that the previously assumed requirement to maintain

a 30 cm beam of GLAM material may not be necessary. This interpretation, combined with the adoption of

conventional room -and-pillar mining methods, may enable optimization of mining heights and pillar

dimensions. It may also allow dilution from the mineralized hanging wall, rather than the floor. These design

changes remain subject to ongoing engineering validation.

1 See “Feasibility Study Update Copperwood Project Michigan, USA” with an Effective Date of March 6, 2023, prepared

for the Company by G Mining Services Inc. available under the Company’s profile at www.sedarplus.com

TSX.V : HI | OTCQB : HDRSF Page 3 of 5

At the same time, Highland is reassessing productivity , ground support, and labor assumptions . The

consolidated set of updated assumptions and final design criteria will be incorporated in the Updated FS.

Mineral Processing and Metallurgical Test Work

A metallurgical test work program completed in September 2025 evaluated alternative processing

configurations and reagent schemes. Key highlights included:

• Evaluation of a mill-float-mill-float (“MF2”) flowsheet incorporating a de-sliming stage;

• Reduction of mass reporting to secondary milling through rejection of up to approximately 25% of

primary rougher tailings;

• Estimated comminution energy reductions of approximately 10% to 13.7%;

• Development of an optimized reagent scheme with the potential to reduce operating costs by up to

$1.00 per tonne milled; and

• Projected average life-of-mine metallurgical performance, incorporating ultrafine flotation and the

optimized flowsheet, is estimated at approximately 87.6% copper recovery (relative to 86.0% copper

recovery in the 2023 FS) at a 25% concentrate grade.

The simplified plant is anticipated to decrease overall footprint, reducing structural, civil, platework, piping

and installation capital. A reduced footprint also naturally reduce s environmental impact. The revised

process flowsheet will be incorporated into the Update FS.

These projections are based on test work and engineering assumptions and have not yet been demonstrated

under operating conditions. The Company notes that metallurgical recoveries are subject to variability and

may differ from test work results.

Tailings Management

Following the metallurgical program, a tailings dewatering test work campaign was conducted at

Responsible Mining Solutions Corp. (RMS) in Sudbury, Ontario. The results indicate that thickened tailings

with a target density of approximately 55% solids by mass can be produced under test conditions.

The use of thickened tailings is being evaluated as part of the design of the Tailings Deposition Facility

(“TDF”) and may reduce the overall TDF footprint, potentially reducing related earthwork cost during initial

construction. Tailings thickeners also allow for increased process recovery water, reducing pumping costs

from reclaim water pumps and water recirculation between the process plant and TDF. Overall, this

potential change can reduce environmental impact and certain operational risks.

Updated Feasibility Study and Project Development

Given the scope of potential design changes and updated economic assumptions, the Company intends to

prepare Updated FS results in Q1 2027. Through the remainder of 2026, Highland will conclude on remaining

design criteria, and advance FEED to 40% for key work packages. The Updated FS is expected to include:

TSX.V : HI | OTCQB : HDRSF Page 4 of 5

• Updated Mineral Resources and Reserves estimates;

• Revised mine design and production schedule;

• Optimized process flow sheet incorporating Jameson cells;

• Potential reduction of TDF;

• Updated capital and operating cost estimates; and

• Results of ongoing engineering optimization work.

An updated FS reflective of long -term consensus copper price, with FEED complete and design

optimizations incorporated, will position Highland for the technical due diligence related to project

financing.

Qualified Person

The scientific and technical information contained in this news release has been reviewed and approved by

Trace Arlaud , a “Qualified Person” as defined under NI 43 -101. Ms. Arlaud is a consultant to Highland

Copper and serves as the Company's Project Director.

Approval of the process and tailings statement is based on previously QP Press Release by Dr. Wynand van

Dyk dated September 4th, 2025.

About Highland Copper Company

Highland Copper Company Inc. is focused on developing the Copperwood Project in the Upper Peninsula of

Michigan, U.S.A. The Company also owns surface rights securing access to the Copperwood deposit and

providing space for infrastructure at Copperwood as required. The Company has 738,188,122 common

shares issued and outstanding. Its common shares are listed on the TSX Venture Exchange under the symbol

"HI" and trade on the OTCQB Venture Market under symbol "HDRSF".

More information about the Company is available on the Company's website at www.highlandcopper.com

and on SEDAR+ at www.sedarplus.com.

Cautionary Note Regarding Forward-Looking Information

This news release contains “forward -looking statements” and “forward -looking information” (collectively “forward -

looking statements”) within the meaning of applicable Canadian securities legislation. Forward -looking statements in

this news release include, but are not limited to, statements regarding: Integrated Mine Plan Review , including the

information regarding the evaluation of reduced cutoff grade, evaluation of the UCBS and evaluation of geotechnical

assumptions, the potential implications of recently completed mineral processing and metallurgical test work,

potential for thickening tail ings and the potential implications of thickened tailings including reduced TDF footprint

and reduced environmental impact; the timeline for, and potential results of, an Updated FS; the anticipated

completion of FEED engineering and advancement to appro ximately 40% engineering; the results of the integrated

mine plan review, including updates to cut-off grade, mining method, equipment strategy, and ground support design;

and the assessment and potential implementation of drift and fill mining method and potential increased mine

recoveries.

TSX.V : HI | OTCQB : HDRSF Page 5 of 5

These forward-looking statements are based on certain key assumptions, that FEED engineering can be completed as

planned and within budget; that the results of the integrated mine plan review, metallurgical and mining test work and

tailings management improvements will result in improvements to the project economics ; a positive Updated FS will

be sufficient to advance the Project to support due diligence for Project Finance; that copper prices will remain at levels

that support project economics; that cost inflation will not materially exceed current estimates; and that there will be

no material adverse changes in metal markets, regulatory requirements, or general economic conditions.

Forward-looking statements involve known and unknown risks, uncertainties and other factors which may cause the

actual results, performance or achievements of the Company to be materially different from any future results,

performance or achievements expre ssed or implied by the forward -looking statements. Such risks and uncertainties

include, the Company may be unable to obtain project financing on acceptable terms or at all, which would prevent

the Company from proceeding to construction; the FEED enginee ring may reveal technical challenges, cost overruns,

or design issues that delay the project or increase capital requirements; the integrated mine plan review may not result

in improvements to project economics and may reveal the need for more conservative mining parameters; any

technical optimizations may require permit amendments, which are subject to regulatory approval and may be

delayed, denied, or granted with unfavorable conditions; permit amendment processes may take longer than

anticipated, delayin g the construction decision or construction start; environmental mitigation projects may not

perform as designed, requiring additional remediation work and expense; the availability of skilled labor and adequate

housing may be insufficient to support const ruction and operations, particularly in the Upper Peninsula of Michigan;

the Company may be unable to retain qualified technical advisors, offtake advisors, or debt finance advisors on

acceptable terms; the debt financing process may not result in financing on acceptable terms or at all; offtake partners

may not be available or may only be available on unfavorable commercial terms; Trace Arlaud may become unavailable

as a consultant or may be unable to complete the integrated mine plan review, and the Company may be unable to

recruit a qualified replacement Project Director in a timely manner, either of which could impact the Company’s

operating plans; capital costs and operating costs may increase materially due to inflation, supply chain disruptions,

labor shortages, or other factors; copper prices may decline, adversely affecting project economics and the ability to

obtain financing; metal markets may experience volatility or prolonged downturns; regulatory requirements may

change or become more stringent, requiring additional permitting, studies, or capital expenditures; general economic

conditions may deteriorate, affecting the availability of financing and the cost of capital; geotechnical conditions may

prove more challenging than anticipated, requiring changes to mining method, ground support, or pillar design; the

Company may encounter unforeseen technical, environmental, or social challenges in advancing the project; and the

other risks and uncertainties set out in the Company’s public disclosure docu ments, including its Annual Information

Form, filed on SEDAR+. Although the Company believes that the assumptions and factors used in preparing the

forward-looking statements in this news release are reasonable, undue reliance should not be placed on such

statements. All forward -looking statements in this press release are based on information available to the Company

as of the date hereof, and the Company undertakes no obligation to update forward -looking statements except as

required by law.

Neither the TSX Venture Exchange nor its Regulation Services Provider (as that term is defined in the policies

of the TSX Venture Exchange) accepts responsibility for the adequacy or accuracy of this release.

For further information or media requests, please contact:

Barry O'Shea, CEO

Email: [email protected]

Website: www.highlandcopper.com