Saturday, September 26, 2026
MiningNewsTerminal
Saturday, September 26, 2026 Admin

HI.V ·

Highland Copper Completes Environmental Mitigation Program Demonstrating Benefit of Concurrent Reclamation at Copperwood Project

Corporate Updates

September 10, 2025

TSX.V : HI | OTCQB : HDRSF Page 1 of 5

HIGHLAND COPPER COMPLETES ENVIRONMENTAL MITIGATION PROGRAM DEMONSTRATING

BENEFIT OF CONCURRENT RECLAMATION AT COPPERWOOD PROJECT

Vancouver, British Columbia – September 10, 2025 – Highland Copper Company Inc. (TSXV: HI; OTCQB:

HDRSF) (“Highland” or the “Company”) is pleased to announce the successful completion of its early site

work and related environmental mitigation program at its 100%-owned, fully permitted Copperwood Project

in Michigan, USA.

The program was completed safely, within budget, and in full compliance with the Michigan Wetlands and

Streams Permit. The early site works program focused on preparing the site for future construction while

proactively implementing environmental safeguards and controls. The work has been subject to ongoing

inspection from the Michigan Department of Environment, Great Lakes , and Energy (“EGLE”) and has met

all key regulatory obligations . Importantly, the environmental mitigation program has demonstrated the

positive impact of concurrent reclamation. Completion of this initiative not only ensures that permits remain

in good standing but also demonstrates Highland’s ongoing commitment to responsible development.

A central component of the program was a significant investment in environmental stewardship to minimize

and mitigate the project's impact. Key activities included:

• Wetland Creation: The construction of approximately 18 acres of compensating wetlands to offset

impacted areas.

• Revegetation: The successful planting of nearly 20,000 native trees, wildflowers, sedges, and

rushes in the newly created habitats throughout the stream diversion and wetlands.

• Long-Term Preservation: Commitment to establish a 717-acre wetland preservation area, with a

conservation easement and long -term management plan being finalized to ensure permanent

protection beyond the life of mining operations.

Barry O’Shea, CEO of Highland Copper, commented: “ Michigan has stringent regulation to ensure mining

projects minimize and mitigate their impact. Highland takes this commitment seriously and has

demonstrated this with its environmental mitigation work at this early stage of its development. We are also

showing that re clamation does not need to start at closure. It can be done concurrent with development.

We are particularly pleased that the stream and wetland projects are maturing well into high -quality

habitats.”

The following photos show how the wetland creation and revegetation efforts are quickly maturing. A variety

of seeded and planted species are taking hold, along with abundant wildlife . These mitigation projects are

continuing to develop into a self-sustaining systems, rich in biodiversity.

TSX.V : HI | OTCQB : HDRSF Page 2 of 5

Figure 1 – A section of the East Stream diversion channel, comparing April (left) and August (right) 2025. Vigorous

vegetation growth across the reconstructed stream areas has stabilized the new channels against erosion while

creating high-quality wildlife habitat.

Figure 2 – Plant growth in the Gipsy wetland mitigation area has been impressive. The images above show

vegetation development in wetland cell ‘C1’ from May (left) to August (right) 2025.

TSX.V : HI | OTCQB : HDRSF Page 3 of 5

Figure 3 – The Choate Road crossing over Bluff Creek was improved to replace a set of culverts with a

clear-span bridge. Shown above are the culverts (before) and the new bridge (after). This stream mitigation

project was designed to improve fish passage and stream habitat quality. Additional restoration of in-

stream features, both up and down-stream from the bridge, will be completed in September 2025.

Figure 4 – Stream restoration in several sections of Bluff Creek is designed to improve stream flow

properties and habitat quality. Shown above is a location where the eroded outside bank (left - April 2025)

is in the process of being reconstructed (right - August 2025).

TSX.V : HI | OTCQB : HDRSF Page 4 of 5

About Highland Copper Company

Highland Copper Company Inc. is a Canadian company focused on exploring and developing copper

projects in the Upper Peninsula of Michigan, U.S.A. The Company owns the Copperwood deposit through

long-term mineral leases and 34% of the White Pine North proje ct through a joint venture with Kinterra

Copper USA LLC. The Company also owns surface rights securing access to the Copperwood deposit and

providing space for infrastructure at Copperwood as required. The Company has 736,363,619 common

shares issued and outstanding. Its common shares are listed on the TSX Venture Exchange under the symbol

"HI" and trade on the OTCQB Venture Market under symbol "HDRSF".

More information about the Company is available on the Company’s website at www.highlandcopper.com

and on SEDAR+ at www.sedarplus.com.

Cautionary Note Regarding Forward-Looking Information

This news release contains “forward -looking statements” and “forward -looking information” (collectively

“forward-looking statements”) within the meaning of applicable Canadian securities legislation. These

statements include, without limitation, statements with respect to: the anticipated benefits of early site work

program at Copperwood. The forward-looking statements are subject to a number of assumptions, including

those set out in the technical reports entitled “Feasibility Study Update Copperwood Project Michigan, USA”

and the Company’s annual information form for the year ended June 30, 2024 (the “AIF”). These underlying

assumptions may prove to be incorrect. Important factors that could materially impact the Company's

expectations include: changes in project parameters as plans continue to be refined; availability of services,

materials and skilled lab our to complete work programs, testing and drilling; effects of regulation by

governmental agencies; the fact that permit extensions, renewals and amendments are subject to regulatory

approvals, which may be conditioned, delayed or denied; advancement to a construction decision at

Copperwood is subject to additional studies, for which the Company will req uire additional funds, which

may not be available on a timely basis and accordingly could delay a construction decision; unexpected cost

increases, which could include significant increases in estimated capital and operating costs and the effects

of inflation; fluctuations in metal prices and currency exchange rates; general market and industry

conditions, the results of baseline studies and test work may result in unforeseen issues which could delay

or hamper advancement of the projects, and the other risks set out in the Company’s public disclosure

documents, including the AIF, filed on SEDARPlus. Although the Company believes that the assumptions

and factors used in preparing the forward -looking statements in this news release are reasonable, undue

reliance should not be placed on forward looking statements. All forward -looking statements in this press

release are based on information available to the Company as of the date hereof, and the C ompany

undertakes no obligation to update forward-looking statements except as required by law.

Neither the TSX Venture Exchange nor its Regulation Services Provider (as that term is defined in the

policies of the TSX Venture Exchange) accepts responsibility for the adequacy or accuracy of this

release.

TSX.V : HI | OTCQB : HDRSF Page 5 of 5

For further information or media requests, please contact:

Barry O’Shea, CEO

Email: [email protected]

Website: www.highlandcopper.com