Graphite One's Graphite Creek Project Approved for FAST-41 Federal Permitting Dashboard Graphite One becomes the first Alaskan Critical Mineral mining project on the FAST-41 Dashboard FAST-41 status follows completion of Graphite One Feasibility Study funded by a

Economic Studies Permits & Approvals

Graphite One's Graphite Creek Project Approved for FAST-41 Federal

Permitting Dashboard

Graphite One becomes the first Alaskan Critical Mineral mining project on the FAST-41 Dashboard

FAST-41 status follows completion of Graphite One Feasibility Study funded by a

$37.3M

award under the Defense Production Act

G1 enters Permitting Phase as Presidential Critical Mineral Executive Order calls for "Immediate Measures to Increase American Mineral

Production" and "Unleashing Alaska's Extraordinary Resource Potential"

VANCOUVER, BC

,

June 3, 2025

/CNW/ - Graphite One Inc. (TSXV: GPH) (OTCQX: GPHOF) ("

Graphite One

", the "

Company

", or

"G1"

), is

pleased to announce that the Company's Graphite Creek project – the upstream anchor for G1's complete U.S.-based advanced graphite supply

chain ("

Graphite Creek

")– has been accepted as a "covered project" onto the FAST-41 Permitting Dashboard. Graphite One's project is the first

Alaskan mining project to be listed on the FAST-41 Dashboard.

"The approval of Graphite Creek as FAST-41's first Alaskan mining project is a major step for G1 and our complete U.S.-based supply chain

strategy," said

Anthony Huston

, CEO of Graphite One. "With President Trump's Critical Mineral and Alaska Executive Orders, Graphite One is

positioned at the leading edge of a domestic Critical Mineral renaissance that will power transformational applications from energy and transportation

to AI infrastructure and national defense."

Graphite One's domestic supply chain is planned to produce graphite concentrate from the Graphite Creek deposit North of

Nome, Alaska

and Anode

Active Material at a facility to be constructed in

Warren, Ohio

, subject to financing (the "

Project

").

FAST-41 status follows publication of Graphite One's Feasibility Study ("

FS

") on

April 23, 2025

, which, with the support of the Department of

Defense Production Act (DPA) award, was completed 15 months ahead of schedule. The annual graphite concentrate capacity of the Graphite

Creek Mine in the FS was increased from that in the 2022 Pre-Feasibility Study ("

PFS

") – from 53,000 tpy to 175,000 tpy while maintaining a 20-year

mine life. Measured plus Indicated Resources increased to 322% of the PFS resource. The FS projects a post-tax internal rate of return of 27%,

using an 8% discount rate, with a net present value of

$5.03 billion

and a payback period of 7.5 years.

FAST-41 streamlines the permitting process by providing improved timeliness and predictability by establishing publicly posted timelines and

procedures for federal agencies, reducing unpredictability in the permitting process. FAST-41 also provides issue resolution mechanisms, while the

federal permitting dashboard allows all project stakeholders and the general public to track a project's progress, including periods for public

comment.

The action drew strong support from

Alaska's

leading public officials:

"America's dependency on foreign minerals and metals is a drag on our economy and a danger to our national security," said

Alaska

Governor

Mike Dunleavy. "As the largest natural graphite deposit in the nation, adding Graphite Creek to the FAST-41 Permitting Dashboard sends a strong

signal that

Alaska

is key to U.S. Critical Mineral development."

"Graphite One's addition to the FAST-41 permitting dashboard is yet another indication that this project is a national priority of strategic importance,"

said Senator Lisa Murkowski. "There is no question that developing the largest natural graphite deposit in all of

North America

is far better for our

economy, security, and competitiveness than importing the entirety of our supply from unstable nations like

Mozambique

. I thank the Trump

administration for adding Graphite One to the dashboard and look forward to the day this project comes online."

"I want to congratulate Graphite One, which has achieved this milestone thanks to funding from the Defense Production Act, something I have been

working on relentlessly in the Senate since the project's inception," said Senator

Dan Sullivan

. "This project has the potential to open up our state's

abundant reserves of critical minerals and metals, which would also be very significant for our country's national security. We must end America's

dependence on

China

for critical minerals, like graphite, resources that are necessary for alternative energy and sources and critical defense

technologies. Thankfully, President Trump understands our state's great potential, and is determined to help unleash our vast resources and create

good paying jobs to Alaskans. Graphite One's FAST-41 status is great news for our state and our country."

"Securing our supply chains for critical minerals is a core priority and requires a whole of government approach." said

Alaska

Congressman

Nick

Begich

. "Our national security, sovereignty, and continued self-determination require that we take action, and Graphite One is leading the way."

Graphite One's Complete U.S.-Based Supply Chain Strategy

The Project is planned as an integrated business operation to produce lithium-ion battery anode materials and other graphite products for the U.S

domestic market on a commercial scale using primarily natural graphite from

Alaska

. The Project combines the operation of an advanced graphite

manufacturing facility to be located in

Warren Ohio

with the supply of natural flake graphite from the Company's proposed Graphite Creek Mine in

Alaska

. The resources associated with the Company's Alaska State mining claims were cited by the U.S. Geological Survey in

January 2022

as

America's largest natural graphite deposit

1

, and in 2023, "as among the largest in the world." This precedes the FS-verified deposit amount increase.

The

Ohio

manufacturing facility received a

$325M

Letter of Interest from the EXIM Bank in September 2024.

____________________________

1

https://www.usgs.gov/data/graphite-deposits-united-states

About the Permitting Council and FAST-41

Established in 2015 by Title 41 of the Fixing America's Surface Transportation Act (FAST-41), the Permitting Council is a federal agency charged with

improving the transparency and predictability of the federal environmental review and authorization process for certain critical infrastructure projects.

The Permitting Council is comprised of the Permitting Council Executive Director, who serves as the Council Chair; 13 federal agency Council

members (including deputy secretary-level designees of the Secretaries of Agriculture, Army, Commerce, Interior, Energy, Transportation, Defense,

Homeland Security, and Housing and Urban Development, the Administrator of the Environmental Protection Agency, and the Chairs of the Federal

Energy Regulatory Commission, Nuclear Regulatory Commission, and the Advisory Council on Historic Preservation); and the Chair of the White

House Council on Environmental Quality and the Director of the Office of Management and Budget.

The Permitting Council coordinates federal environmental reviews and authorizations for projects that seek and qualify for FAST-41 coverage. FAST-

41 covered projects are entitled to comprehensive permitting timetables and transparent, collaborative management of those timetables on the

Federal Permitting Dashboard. FAST-41 covered projects may be in the energy production, electricity transmission, energy storage, surface

transportation, aviation, ports and waterways, water resource, broadband, pipelines, manufacturing, mining, carbon capture, semiconductors,

artificial intelligence and machine learning, high-performance computing and advanced computer hardware and software, quantum information science

and technology, data storage and data management, and cybersecurity sectors.

The Permitting Council also serves as a federal center for permitting excellence, supporting federal efforts to improve infrastructure permitting

including and beyond FAST-41 covered projects to the extent authorized by law, including activities that promote or provide for the efficient, timely,

and predictable completion of environmental reviews and authorizations for federally-authorized infrastructure projects.

Qualified Person

Jason Todd

, with Barr Engineering Co. is the primary qualified person for the Feasibility Study incorporated in the NI 43-101 technical report that is

available under the Company's SEDAR+ profile at

www.sedarplus.ca

and the Company's website. Mr. Todd is a Qualified Person as defined under

43-101 and has reviewed and approved the technical content of this release.

About Graphite One Inc.

GRAPHITE ONE INC. (TSX

V: GPH; OTCQX: GPHOF) continues to develop its Graphite One Project (the "

Project

"), with the goal of becoming an

American producer of high grade anode materials that is integrated with a domestic graphite resource. The Project is proposed as a vertically

integrated enterprise to mine, process and manufacture high grade anode materials primarily for the lithium

ion electric vehicle battery market.

On Behalf of the Board of Directors

"Anthony Huston" (signed)

For more information on Graphite One Inc., please visit the Company's website,

www.GraphiteOneInc.com

On X @GraphiteOne

Neither the TSX Venture Exchange nor its Regulation Services Provider (as that term is defined in the policies of the TSX Venture Exchange) accepts

responsibility for the adequacy or accuracy of this release.

Cautionary Note Regarding Forward-Looking Statements

All statements in this release, other than statements of historical facts, including those related to the Fast 41 listing and the anticipated impact of

the FAST-41 status, any statements related to the planned production of any mineral reserves and resources, the construction of the

Warren, Ohio

facility, and events or developments that the Company intends, expects, plans, or proposes are forward-looking statements. Generally,

forward

looking information can be identified by the use of forward

looking terminology such as "proposes", "expects", "is expected", "scheduled",

"estimates", "projects", "plans", "is planning", "intends", "assumes", "believes", "indicates", "to be" or variations of such words and phrases that

state that certain actions, events or results "may", "could", "would", "might" or "will be taken", "occur" or "be achieved". The Company cautions that

there is no certainty that the Fast 41 listing will impact the Company as set forth in this press release, that the Graphite Creek Project produces the

minerals set out in the FS or that the facility will be built in

Warren, Ohio

. Although the Company believes the expectations expressed in such

forward-looking statements are based on reasonable assumptions, such statements are not guarantees of future performance and actual results or

developments may differ materially from those in the forward-looking statements. Factors that could cause actual results to differ materially from

those in forward-looking statements include market prices, exploitation and exploration successes, continuity of mineralization, uncertainties

related to the ability to obtain necessary permits, licenses and title and delays due to third party opposition, changes in government policies

regarding mining and natural resource exploration and exploitation, and continued availability of capital and financing, and general economic,

market or business conditions. Readers are cautioned not to place undue reliance on this forward-looking information, which is given as of the date

it is expressed in this press release, and the Company undertakes no obligation to update publicly or revise any forward-looking information,

except as required by applicable securities laws. For more information on the Company, investors should review the Company's continuous

disclosure filings that are available at

www.sedarplus.ca

.

View original content to download multimedia:

https://www.prnewswire.com/news-releases/graphite-ones-graphite-creek-project-approved-for-fast-41-federal-permitting-dashboard-302471530.html

SOURCE

Graphite One Inc.

View original content to download multimedia:

http://www.newswire.ca/en/releases/archive/June2025/03/c4613.html

%SEDAR: 00025247E

For further information:

Anthony Huston, CEO, President & Director, Tel: (604) 889-4251, Email: [email protected]; Investor

Relations Contact, Tel: (604) 684-6730, [email protected]

CO: Graphite One Inc.

CNW 07:00e 03-JUN-25