Graphite One's Graphite Creek Coordinated Project Plan Posted on the FAST-41 Federal Permitting Dashboard Coordinated Project Plan (CPP) Brings All Participating Federal Agencies and the Company Together to Identify and Publicly Post All Project Reviews, Authorizations and Timelines

Permits & Approvals

Graphite One's Graphite Creek Coordinated

Project Plan Posted on the FAST-41 Federal

Permitting Dashboard

Coordinated Project Plan (CPP) Brings All Participating Federal Agencies and the Company

Together to Identify and Publicly Post All Project Reviews, Authorizations and Timelines

Coordinated Plan Establishes Graphite Creek Permitting Timeline at 13.5 Months

G1's listing on the FAST-41 Dashboard Aligns with the Presidential Critical Mineral Executive

Orders calling for "Immediate Measures to Increase American Mineral Production" and

"Unleashing Alaska's Extraordinary Resource Potential"

VANCOUVER, BC

,

Aug. 5, 2025

/CNW/ - Graphite One Inc. (TSXV: GPH) (OTCQX: GPHOF)

("

Graphite One

", the "

Company

", or

"G1"

), is pleased to announce that the Company's Graphite

Creek project (the "

Project

") – the upstream anchor for G1's complete U.S.-based advanced

graphite supply chain ("

Graphite Creek

")– has completed the FAST-41 60-day Coordinated Project

Plan ("

CPP

") process, with the resulting plan for reviews, authorizations and timeline posted on the

FAST-41 Federal Dashboard, which can be accessed

here

.

Graphite One's project is the first Alaskan mining project to be listed on the FAST-41 Dashboard.

"The ability to coordinate with all participating federal agencies involved in our permitting, develop a

transparent plan for the process and post that plan publicly is a testament to the FAST-41 process

and the predictability and transparency it provides," said

Anthony Huston

, CEO of Graphite One.

"With President Trump's Critical Mineral and Alaska Executive Orders, Graphite One is positioned at

the leading edge of a domestic Critical Mineral renaissance that will power transformational

applications from energy and transportation to AI infrastructure and national defense."

FAST-41 CPP:

Established pursuant to Title 41 of the Fixing America's Surface Transportation Act (FAST-41), the

CPP is a concise plan for coordinating public and agency participation in, and completion of, any

required federal environmental reviews and authorizations for the Project. The CPP is developed by

the lead/facilitating agency, in consultation with each coordinating and participating agency. FAST-41

encourages lead/facilitating agencies to have preliminary engagement with project sponsors when

developing CPPs.

The CPP contains:

A list of, and roles and responsibilities for, all entities with environmental review or authorization

responsibilities for the Project.

A permitting timetable that includes intermediate and final completion dates for action by each

agency on any federal environmental review or authorization required for the Project, and to the

maximum extent practicable, the dates by which State permits, reviews and approvals must be

made.

A discussion of potential avoidance, minimization, and mitigation strategies, if required by

applicable law and known.

Plans and a schedule for public and tribal outreach and coordination, to the extent required by

applicable law.

Graphite One's domestic supply chain is planned to produce graphite concentrate from the Graphite

Creek deposit North of

Nome, Alaska

and Anode Active Material at a facility to be constructed in

Warren, Ohio

, subject to financing.

FAST-41 status follows publication of Graphite One's Feasibility Study ("

FS

") filed on

April 23, 2025

,

which, with the support of the Department of Defense Production Act (DPA) award, was completed

15 months ahead of schedule. The annual graphite concentrate capacity of the Graphite Creek Mine

in the FS was increased from that in the 2022 Pre-Feasibility Study ("

PFS

") – from 53,000 tpy to

175,000 tpy while maintaining a 20-year mine life. Measured plus Indicated Resources increased to

322% of the PFS resource. The FS, effective

March 25, 2025

, projects a post-tax internal rate of

return of 27%, using an 8% discount rate, with a net present value of

$5.03 billion

and a payback

period of 7.5 years.

FAST-41 streamlines the permitting process by providing improved timeliness and predictability by

establishing publicly posted timelines and procedures for federal agencies, reducing unpredictability

in the permitting process. FAST-41 also provides issue resolution mechanisms, while the federal

permitting dashboard allows all project stakeholders and the general public to track a project's

progress, including periods for public comment.

The filing of the FAST-41 CPP received support from the following federal officials:

"As

Alaska's

first Critical Mineral mining project on the FAST-41 Dashboard, Graphite One is blazing

the trail for projects that contribute not only to the American economy but to our national security,"

said

Alaska

Governor

Mike Dunleavy

. "In the 21st Century, the wealth of nations - their ability to

provide opportunities for their people, their ability to remain safe in a dangerous world - depends on

access to the resources that power our technologies. For our nation, the message is clear: There is

no path forward to American Energy Dominance without the minerals, metals and natural gas

resources

Alaska

has in abundance."

"I thank the Permitting Council for recognizing the strategic importance of the Graphite One project

and for moving quickly to add it to the FAST-41 dashboard—the first Alaskan mining project on the

dashboard," said

Alaska

Senator

Lisa Murkowski

. "As China continues to restrict

the United

States'

supply of critical minerals, it is crucial for Graphite One to advance without delay. This is

North America's

largest deposit of natural graphite, foundational to any effort to rebuild our domestic

supply chains, and we now have a concrete timeline of 13.5 months for federal agencies to bring it

through the permitting process."

"FAST-41 is designed to provide speed, transparency, and accountability for all groups involved in

permitting and approving projects like those offered by Graphite One, and it's encouraging to see

G1 complete this process within the allotted 60 day window," said

Nick Begich

, Congressman

for

All Alaska. "Domestic supply chains for critical minerals are cornerstone requirements for domestic

production and national security. G1 is blazing a trail for additional efforts of this kind -

demonstrating how we can work across governmental jurisdictions to unlock the full potential of

Alaska

for the benefit of all Americans."

"Graphite Creek is critical to achieving President Trump's energy dominance agenda and is exactly

the kind of project that can benefit from the transparency and accountability that comes with FAST-

41," said

Emily Domenech

, Executive Director, Federal Permitting Improvement Steering Council

(FPISC). "Our team worked with federal agencies to develop an efficient and responsible permitting

timetable, and we are ready to partner with Graphite One to get this project to construction."

Graphite One's Complete U.S.-Based Supply Chain Strategy

The Project is planned as an integrated business operation to produce lithium-ion battery anode

materials and other graphite products for the U.S domestic market on a commercial scale using

primarily natural graphite from

Alaska

. The Project combines the operation of an advanced graphite

manufacturing facility to be located in

Warren Ohio

, subject to financing, with the supply of natural

flake graphite from the Company's proposed Graphite Creek Mine in

Alaska

. The resources

associated with the Company's Alaska State mining claims were cited by the U.S. Geological Survey

in

January 2022

as America's largest natural graphite deposit

1

, and in 2023, "as among the largest

in the world." This precedes the FS-verified deposit amount increase. The Company entered into a

non-binding letter of interest with the EXIM Bank in

September 2024

for a potential

$325 million

loan

to fund the

Ohio

manufacturing facility.

____________________________

1

https://www.usgs.gov/data/graphite-deposits-united-states

About the Permitting Council and FAST-41

Established in 2015 by Title 41 of FAST-41, the Permitting Council is a federal agency charged with

improving the transparency and predictability of the federal environmental review and authorization

process for certain critical infrastructure projects. The Permitting Council is comprised of the

Permitting Council Executive Director, who serves as the Council Chair; 13 federal agency Council

members (including deputy secretary-level designees of the Secretaries of Agriculture, Army,

Commerce, Interior, Energy, Transportation, Defense, Homeland Security, and Housing and Urban

Development, the Administrator of the Environmental Protection Agency, and the Chairs of the

Federal Energy Regulatory Commission, Nuclear Regulatory Commission, and the Advisory Council

on Historic Preservation); and the Chair of the White House Council on Environmental Quality and the

Director of the Office of Management and Budget.

The Permitting Council coordinates federal environmental reviews and authorizations for projects that

seek and qualify for FAST-41 coverage. FAST-41 covered projects are entitled to comprehensive

permitting timetables and transparent, collaborative management of those timetables on the Federal

Permitting Dashboard. FAST-41 covered projects may be in the energy production, electricity

transmission, energy storage, surface transportation, aviation, ports and waterways, water

resource, broadband, pipelines, manufacturing, mining, carbon capture, semiconductors, artificial

intelligence and machine learning, high-performance computing and advanced computer hardware

and software, quantum information science and technology, data storage and data management,

and cybersecurity sectors.

The Permitting Council also serves as a federal center for permitting excellence, supporting federal

efforts to improve infrastructure permitting including and beyond FAST-41 covered projects to the

extent authorized by law, including activities that promote or provide for the efficient, timely, and

predictable completion of environmental reviews and authorizations for federally-authorized

infrastructure projects.

About Graphite One Inc.

GRAPHITE ONE INC. continues to develop its Graphite One Project (the "

Project

"), with the goal of

becoming an American producer of high grade anode materials that is integrated with a domestic

graphite resource. The Project is proposed as a vertically integrated enterprise to mine and process

natural graphite, and to manufacture artificial and natural graphite anode materials primarily for the

lithium

ion electric vehicle battery and energy storage markets.

On Behalf of the Board of Directors

"Anthony Huston" (signed)

For more information on Graphite One Inc., please visit the Company's website,

www.GraphiteOneInc.com

On X @GraphiteOne

Neither the TSX Venture Exchange nor its Regulation Services Provider (as that term is defined in

the policies of the TSX Venture Exchange) accepts responsibility for the adequacy or accuracy of

this release.

Cautionary Note Regarding Forward-Looking Statements

All statements in this release, other than statements of historical facts, including those related to

the Fast 41 listing and the anticipated impact of the FAST-41 status, any statements related to the

planned production of any mineral reserves and resources, the construction of the

Warren, Ohio

facility, and events or developments that the Company intends, expects, plans, or proposes are

forward-looking statements. Generally, forward

looking information can be identified by the use of

forward

looking terminology such as "proposes", "expects", "is expected", "scheduled", "estimates",

"projects", "plans", "is planning", "intends", "assumes", "believes", "indicates", "to be" or variations

of such words and phrases that state that certain actions, events or results "may", "could", "would",

"might" or "will be taken", "occur" or "be achieved". The Company cautions that there is no

certainty that the Fast 41 listing will impact the Company as set forth in this press release, that the

Graphite Creek Project produces the minerals set out in the FS or that the facility will be built in

Warren, Ohio

. Although the Company believes the expectations expressed in such forward-looking

statements are based on reasonable assumptions, such statements are not guarantees of future

performance and actual results or developments may differ materially from those in the forward-

looking statements. Factors that could cause actual results to differ materially from those in

forward-looking statements include market prices, exploitation and exploration successes,

continuity of mineralization, uncertainties related to the ability to obtain necessary permits, licenses

and title and delays due to third party opposition, changes in government policies regarding mining

and natural resource exploration and exploitation, and continued availability of capital and

financing, and general economic, market or business conditions. Readers are cautioned not to

place undue reliance on this forward-looking information, which is given as of the date it is

expressed in this press release, and the Company undertakes no obligation to update publicly or

revise any forward-looking information, except as required by applicable securities laws. For more

information on the Company, investors should review the Company's continuous disclosure filings

that are available at

www.sedarplus.ca

.

SOURCE

Graphite One Inc.

View original content to download multimedia:

http://www.newswire.ca/en/releases/archive/August2025/05/c3549.html

%SEDAR: 00025247E

For further information:

Anthony Huston, CEO, President & Director, Tel: (604) 889-4251, Email:

[email protected]; Investor Relations Contact: Tel: (604) 684-6730,

[email protected]

CO: Graphite One Inc.

CNW 07:00e 05-AUG-25