Golden Goliath Drilling Discovers Wide Shear Zone Along Pakwash Structure Within Favourable Uchi Belt Host Rocks ON Kwai Property, Red Lake, Ontario
1
TSX.V:GNG
www.goldengoliath.com
GOLDEN GOLIATH DRILLING DISCOVERS WIDE SHEAR
ZONE ALONG PAKWASH STRUCTURE WITHIN
FAVOURABLE UCHI BELT HOST ROCKS ON KWAI
PROPERTY, RED LAKE, ONTARIO
Vancouver, October 15, 2020, Golden Goliath Resources Ltd. (TSX.V GNG ) (US:
GGTH-F) (Frankfurt: GGZ)
Golden Goliath Resources is pleased to report on the progress being made
on the Kwai gold project south of Red Lake Ontario and the continuing drill
program to test numerous IP (Induced Polarization) anomalies associated
with the Pakwash Fault structure and associated, pa rallel, splay faults and
shears. The Kwai property covers a 10 km section of the Pakwash Fault
which partly defines the boundary between the Engli sh River Sub Province
to the south and the Uchi Province (and greenstone belt) to the north. This
structure has never been drilled or mapped in detai l on the Kwai property,
however, it was outlined by a deep seismic survey b y the federal
government and found to be linked to other regional deep seated faults that
are associated with the main gold mines in Red Lake and the LP fault 15km
to the north of the Kwai property on the Dixie Lake property being explored
by Great Bear Resources (GBR).
2
Figure 1: Red Lake District Properties including the Kwai and SLF properties of Golden Goliath
Drilling of hole K20-06, referred to in the most re cent News Release (Sept.
30, 2020) has been successfully completed to a dept h of 399m and has
intersected the IP anomaly target hidden beneath co nductive overburden
(clays and silts). This 50 meter wide intersection of disseminated sulphides
was hosted in both sericite schists and tuffaceous felsic volcanics
(sericitized) with cherty and siliceous zones. Simi lar cherty siliceous units
were seen in hole K20-03 on line 600W, a distance o f 800m away, and in
hole K20-05, 200m east of hole 06.
These siliceous units are interpreted to be a favou rable host for gold
mineralization. Hole 06 was the deepest hole to dat e was drilled south
3
beneath a possible thrust fault plane that brought the English River rocks
over top of the south edge of the Uchi rocks which is the main host for gold
mineralization in the region. The conclusion is th at there is likely a wider
zone of favourable Uchi rocks on the Kwai property than previously thought
hidden below the thin sheet of English River rocks (Figure 2). The other
shears parallel to, but south of the main Pakwash F ault in these Uchi rocks
may be very important additional targets for gold.
Figure 2: Proposed North-South Vertical Cross Section on West Grid on line 200E, Hole K20-06
4
The occurrence of wide zones of disseminated pyrite mineralization
associated with the IP anomalies suggests the setting is favourable for gold
and the numerous anomalies require an extensive dri ll program which is
fully financed by Golden Goliath. The pristine gold grain count associated
with the IP anomalies on both the west and east gri d which are now proven
to be disseminated pyrite zones is further evidence in the case for gold
mineralization associated with the Pakwash Fault.
Following the completion of drill hole K20-06, the drill company had to take
a two week break, due to a prior commitment on an a djacent property. This
hiatus was welcomed by the Company as it has allowe d more time for
analyses to be completed and evaluated. Although th e Company has not
yet received any core analyses as of this date, thi s pause was welcome for
planning the next holes.
Prior to the start of the drill program, three till samples were recovered from
an area south and southeast of Beauregard Lake on t he southern part of
the property which were down ice from two IP anomal y trends. Although
the gold grain counts are less than previous sample s and the number of
pristine gold grains are less (13 total grains in t he rusty till sample), this
sampling indicates a possible bedrock source to the north on the Kwai
property. This information also indicates that the gold grain count on the
property is not homogenous and future sampling could indicate well defined
trains of gold grains in till that could lead us to a potential source of gold in
bedrock, associated with the Pakwash Fault Complex. This has been very
helpful for planning future drill holes east of Beauregard Lake.
5
Figure 3: Location Map showing property grids and latest till sample locations
Split cores from all 6 drill holes have been delive red to the lab for
preparation and analysis and numerous holes have be en planned and drill
pads have been prepared in advance. Drilling will r esume on October 18.
Analyses will be released in meaningful batches as received from the lab.
CEO Paul Sorbara comments: “Having found so many ba sal till gold grains
along the trend of the Pakwash Fault, along with so many good IP
anomalies that are coincident with the fault or sub parallel shears combined
with favourable geology, alteration and sulphide mi neralization is a perfect
6
combination for finding significant gold mineralization. We have only drilled
about 1 km of the 10 km break and only from the north side. The south side
of the west grid will be drilled shortly and we wil l get analyses from the first
six holes also. We have only just begun and I am h ighly encouraged. GBR
has drilled hundreds of holes, Hemlo (Corona) took 76 drill holes to find
mineralization and Eskay Creek took 103 drill holes . We have just six
holes completed so far.”
This news release has been reviewed by Robert S. Mi ddleton P.Eng who
is acting as QP for this phase of the exploration u nder the NI43-101
requirements.
On behalf of the Board of Directors
Paul Sorbara, MSc, PGeo
CEO, Golden Goliath Resources Ltd.
Cautionary Statements Regarding Forward Looking Information
Certain statements included herein may constitute “ forward-looking statements”. All statements
included in this press release that address future events, conditions or results, including in
connection with exploration activity, future acquis itions and any financing, are forward-looking
statements. These forward-looking statements can be identified by the use of words such as
“may”, “must”, “plan”, “believe”, “expect”, “estima te”, “think”, “continue”, “should”, “will”, “could” ,
“intend”, “anticipate” or “future” or the negative forms thereof or similar variations. These
forward-looking statements are based on certain ass umptions and analyses made by
management in light of their experiences and their perception of historical trends, current
7
conditions and expected future developments, as wel l as other factors they believe are
appropriate in the circumstances. These statements are subject to risks, uncertainties and
assumptions, including those mentioned in the Compa ny’s continuous disclosure documents,
which can be found under its profile on SEDAR ( www.sedar.com ). Many of such risks and
uncertainties are outside the control of the Compan y and could cause actual results to differ
materially from those expressed or implied by such forward-looking statements. In making such
forward-looking statements, management has relied u pon a number of material factors and
assumptions, on the basis of currently available information, for which there is no insurance that
such information will prove accurate. All forward-l ooking statements are expressly qualified in
their entirety by the cautionary statements set forth above. The Company is under no obligation,
and expressly disclaims any intention or obligation , to update or revise any forward-looking
statements, whether as a result of new information, future events or otherwise, except as
expressly required by applicable law.
FOR MORE INFORMATION CONTACT:
Golden Goliath Resources Ltd.
J. Paul Sorbara, M.Sc., P.Geo
President & CEO
Phone: +1(604) 682-2950 Email: jps@goldengoliath. com
Neither TSX Venture Exchange nor its Regulation Ser vices Provider (as that term is defined in the poli cies of the
TSX Venture Exchange) accepts responsibility for the adequacy.
About Golden Goliath
Golden Goliath Resources Ltd. is a junior explorati on company listed on the TSX Venture
Exchange (symbol GNG). The Company is focused on ex ploring and developing the gold and
silver potential of properties in the Red Lake Dist rict of Ontario. The Company also holds a
100% interest in the San Timoteo property, located in the Sierra Madre Occidental Mountains of
northwestern Mexico, as well as NSR royalties on several other nearby properties.
To find out more about Golden Goliath visit our website at www.goldengoliath.com .