G MINING VENTURES ANNOUNCES 10,000 METER EXPLORATION AND DRILLING PROGRAM AND PROVIDES OVERVIEW OF TOCANTINZINHO DEPOSIT o Inaugural 10,000 meter drilling program to commence shortly o Limited drilling to date, with only 82,805 meters (296 drill holes) from 2004-2015

Exploration Programs

Page | 1

November 8, 2021 TSXV:GMIN

G MINING VENTURES ANNOUNCES

10,000 METER EXPLORATION AND DRILLING PROGRAM AND

PROVIDES OVERVIEW OF TOCANTINZINHO DEPOSIT

o Inaugural 10,000 meter drilling program to commence shortly

o Limited drilling to date, with only 82,805 meters (296 drill holes) from 2004-2015

o Focus on optimizing mine plan, de-risking initial years of production, and exploration at depth

o 1 diamond rig and 1 RC rig to be mobilized on site by mid-November

o GMIN also provides geological overview of deposit and historical drilling campaigns to date

G Mining Ventures Corp. (“ GMIN” or the “Corporation”) is pleased to announce an exploration and drilling

program (the “ Program”) at its recently acquired Tocantinzinho Gold project located in Para State, Brazil

(“Tocantinzinho” or the “Project”). The Program will total 10,000 meters and be focused on (i) de-risking the

pre-production period and (ii) testing for extensions to the known mineralization below t he pit in the

directions that remain open . Additionally, GMIN is pleased to provide a geological overview of the

Tocantinzinho deposit and of the historical drilling campaigns completed from 2004 through 2015.

Louis-Pierre Gignac, President & CEO of GMIN, commented: “Tocantinzinho is a homogenous orebody with

excellent grade continuity, and we are excited to launch our inaugural drilling program. With an existing gold

reserve of 1.8 million ounces , o nly 82,805 meters in 296 drill holes were completed inside the broader

tenement, in various phases between 2004 and 2015. The primary objective of the Program is to optimize

mine planning and de -risk mine performance during the initial years of production . With the deposit open

at depth and down p lunge, t he Program will also include exploration diamond drilling focused on

mineralization below the pit. The Program is to commence this month and continue into 2022.”

Pre-Production Drilling Campaign

7,000 meters of diamond and reverse circulation drilling will be targeting mineralization planned to be mined

during the early years of production. This campaign is intended to significantly de-risk mine performance,

particularly in the initial years of production. The objectives are to:

• Mitigate ore dilution by providing better definition of ore and waste boundaries;

• Optimize mine scheduling in the first 2 years of operation by populating areas with a low er drilling

density near surface (see Figure 1);

• Increase confidence in the quantity of ore mined and milled during ramp -up from a project financing

perspective; and

• Expand and validate the artisanal tailings by i mproving the sampling coverage in the area above the

pit and near the future infrastructure footprint.

Page | 2

Exploration Drilling Campaign

3,000 meters of diamond drilling will be targeting mineralization at depth down plunge to the northeast and

southeast of the currently known mineralization . The campaign is intended to test for extensions to the

known mineralization below the pit in the directions that remain open. The deposit is weakly tested at depths

beyond 350 meters, as focus by prior operator shifted to permitting after the mineral resource exceeded

2.0 million gold ounces . The deepest drill hole reaches 490 meters from surface, which is only 150 meters

below the current pit design (see Figure 2).

GMIN will follow up on drill holes from previous campaigns that rem ain open, such as TOC 09-121,

TOC 09-139 and TOC 09-152 (see Figure 2), which show higher -grade mineralization at the northwestern

and southeastern ends of the pit. This first phase of exploration drilling is aiming at better understanding the

attitude and spatial continuity of the high -grade interval in TOC 09-139, and potentially demonstrating

continuity of gold grades with TOC 09 -152. Partially tested mineralized intervals at the southeastern

extremity of the pit also provide good exploration opportuniti es and will be tested in the current program

(see Figure 2).

Details of the significant intervals at the base of the pit are presented below.

DDH Hole ID From

(meters)

To

(meters)

Interval

(meters)

Estimated

True Width

(meters)

Gold Grade

(g/t Au)

TOC 09-121 256.7 310.0 53.3 32.0 1.83

Including 257.6 278.7 21.2 12.7 2.78

TOC 09-139 324.6 383.1 58.5 26.3 2.50

Including 339.7 356.4 16.8 7.6 4.78

TOC 09-152 394.4 433.9 39.5 31.6 1.26

Including 413.0 421.0 8.0 6.4 2.65

DDH Hole ID Easting

(meters)

Northing

(meters)

Elevation

(meters)

Azimuth

(degrees)

Dip

(degrees)

Length

(meters)

TOC 09-121 578,537 9,330,529 142 220 (79) 454.2

TOC 09-139 578,317 9,330,814 144 220 (70) 472.4

TOC 09-152 578,143 9,330,497 148 40 (60) 487.7

Note: All holes are DDH. Coordinates are in SAD69/UTM Zone 21S.

Page | 3

Overview and Background of Tocantinzinho Gold Deposit

Mineralization and Deposit Type

Tocantinzinho is a granite -hosted gold deposit, with several features typical of intrusion -related gold

systems, such as gold-bearing magmatic-hydrothermal textures and specific alteration assemblages such as

phyllic alteration. Its genesis is a source of debate as it also shares some features of Porphyry -style gold

deposits. Mineralization is mainly hosted in sub -parallel or anastomosing sheeted veins and veinlets

(chlorite-quartz-pyrite) in multiple directions.

The deposit is located within an intrusive suite, bounded and controlled by a major regional northwestern -

trending structure. In the center of the deposit lies an andesitic body, mostly barren, and often marks a

contact with mineralization . The Fort Knox g old mine, located in Alaska, USA, and currently operated by

Kinross Gold Corporation is an example of a deposit classified as an intrusion-related gold deposit and shares

some similarities with Tocantinzinho, such as gold-bearing sheeted veins, granite-hosted, Au>Ag and timing

of mineralization within the intrusion.

The deposit is sub -vertical, southeast trending with excellent grade continuity and consistency (see

Figure 3). Its continuity has been demonstrated by diamond drilling over approximately 900 meters in strike-

length, with widths up to 140 -200 meters and vertical extents up to 360 meters. While the lateral extents

have been tested by diamond drilling (see Figure 2), the main exploration upside is at depth where

mineralization remains open (current target of exploration drilling).

Historical Exploration and Drilling (2004-2015)

The exploration work completed to date includes geological mapping, channel and chip sampling, soil and

stream sediment geochemical surveys, a detailed topography survey, auger drilling, geophysical

investigations, limited reverse circulation drilling, and core drilling. Diamond drill holes are the principal

source of geological and grade data for Tocantinzinho deposit. However, the deposit does not have a high

level of historical drilling, with only 82,805 meters in 296 drill holes completed inside the broader tenement

between 2004 and 2015. The mineral resource estimate is directly supported by only 45,039 meters drilled

(55% of total) between 2004 and 2010. A summary of the historical drilling can be found below.

Drilling Objective Time

Period

Meters

Drilled

Drill

Holes

Resource Drilling and Resource Conversion 2004-2010 45,039 155

Exploration Drilling (tenement-wide) 2004-2015 34,492 159

Metallurgical Test work Drilling 2009 1,490 6

Geotechnical Drilling 2010 1,784 6

Total 2004-2015 82,805 296

Page | 4

Mineral Resource and Reserve Estimate(1)

The current mineral resources estimate was generated on September 30, 2018 and is reported at a 0.30 g/t

Au cutoff grade. The estimate is supported by 3D geological and mineralization models , and the block size

used is 10 m east x 10 m north x 10 m high. Modelling consisted of grade interpolation by ordinary kriging

(OK) inside the mineralized shell.

Mineral Resource Category Tonnage

(000 t Ore)

Grade

(g/t Au)

Contained

(000 oz Au)

Measured 17,530 1.51 851

Indicated 31,202 1.26 1,264

Measured and Indicated 48,732 1.35 2,115

Inferred 2,395 0.90 69

The current mineral reserve estimate was generated on March 31, 2019 using a $1,200 per ounce gold price,

and is reported at a 0.365 g/t Au cutoff grade. GMIN is in the process of updating the current 2019 feasibility

study (Q1-22) and plans to optimize the mineral reserves and mine plan using a $1,400 per ounce gold price

that is more in line with the current market.

Mineral Reserve Category Tonnage

(000 t Ore)

Grade

(g/t Au)

Contained

(000 oz Au)

Proven 17,007 1.52 834

Probable 21,898 1.35 949

Proven and Probable 38,905 1.42 1,783

Tapajos Gold Province

Tocantinzinho is located in the large Tapaj ós Gold Province and is the largest known gold deposit in the

region. This region was the site of a major gold rush by artisanal miners from the late 1970s until the late

1990s which, according to the Brazilian Department of Mineral Production, had a total historical production

of between 20 and 30 million ounces of gold mainly from alluvial and saprolite sources.

The region is underexplored and hosts many gold deposits, such as Cuiù Cuiù ( Cabral Gold Inc.), Palito and

São Chico (Serabi Gold plc), and São Jorge (GoldMining Inc.). Deposit types vary from orogenic, disseminated

intrusion-related, porphyry -style and epithermal gold, as well as and po tentially porphyry Cu -Mo

mineralization. Deposit models evolve, leading towards the Tapajós Province being host of a major intrusive

system potentially generating various mineralization styles. Drill core observations and grade distributions

of the Tocantinzinho deposit also suggest a minor, late orogenic overprinting.

The association of gold with intrusions and higher -grade veining (orogenic gold) are at the heart of the

exploration model for future property-wide exploration drilling at Tocantinzinho. The numerous showings

and exploration upside in the property could potentially extend the current mine life with shallow, satellite

pits.

Page | 5

Timetable and Next Steps

Over the next 12 months, GMIN will be focused on the following activities:

• Completion of Program (Q4-2021 through Q1-2022);

• Completion of project optimization studies and detailed engineering (Q4-21 through Q4-22);

• Completion of an updated 43-101 feasibility study (Q1-22);

• Commencement of onsite early works activities to support infrastructure and allow for rapid start of

construction activities (Q2-22 through Q3-22);

• Finalization of a comprehensive project finance facility to fund construction (H1-22); and

• Positive construction decision (H2-22).

Sampling and QAQC Disclosure

From May 2009 to December 2011, the sample preparation procedure at ALS involved weighing and drying

the sample before being crushed to 70% passing 2 millimeters. The sample was then riffle split to 1-kilogram

and pulverised to 85% passing 75 μm (200-mesh screen). The chemical analysis was performed at ALS Lima,

Peru, using 30 g sample for fire assay analysis (ALS Code Au-AA23). Select samples were also assayed for a

suite of trace elements using aqua -regia digestion and inductively coupled plasma -emission spectroscopy

(ICP-ES, ALS code ME-ICP41). A gravimetric finish was performed on fire assays returning more than 10 g/t

gold. Samples with visible gold were submitted to a metallic screen analysis under ALS protocols (ALS Code:

SCR21).

From July 2011 to January 2015 assays were performed at ACME Analytical Laboratory in Santiago, Chile.

Sample preparation was completed at ACME Analytical Laboratory in Itaituba, Brazil, where they were

crushed, split and pulverized until passing a 200 microns mesh. Gold was analyzed by fire assay with an

atomic absorption finish (ACME Code G6/FA430). Samples were also assayed for a suite of trace elements

using an aqua regia digestion and ICP-ES (ACME Code: D01/AQ300).

The QAQC program implemented by the previous operator involved the regular insertion of blanks, certified

standards and field duplicates. Blanks were used at the rate of one blank at each 40 samples, and a standard

was inserted every 10 samples . Field duplicates (one quarter of a core) were inserted at each 15th sample

or less. Coarse duplicates were submitted to the laboratory after return of the rejects of quartering. Results

from QAQC are monitored regularly.

Qualified Person

The technical information presented in this press release has been approved by Christian Beaulieu, P.Geo

(OGQ 1072), Senior Geologist of G Mining Services Inc. Christian is a member of the l’Ordre des géologues

du Québec, and a “qualified person” as defined by National Instrument 43-101 – Standards of Disclosure for

Mineral Projects (“NI 43-101”). Christian has visited Tocantinzinho and h as verified the exploration results

reported in this press release.

Page | 1

About G Mining Ventures Corp.

G Mining Ventures Corp. (TSXV:GMIN) is a mineral exploration company engaged in the acquisition,

exploration and development of precious metal projects. Its flagship asset, the permitted Tocantinzinho

Project, is located in Para State, Brazil. Tocantinzinho is an open -pit gold deposit contai ning 1.8 million

ounces of reserves at 1.4 g/t. The deposit is open at depth, and the underexplored 688km 2 land package

presents additional exploration potential.

Additional Information

For further information on GMIN, please visit the website at www.gminingventures.com or contact:

Dušan Petković

Vice President, Corporate Development & Investor Relations

647.728.4176

[email protected]

(1) Source: Feasibility study technical report entitled “Technical Report Tocantinzinho Project Brazil” effective date of June 21, 2019, filed on SEDAR by Eldorado Gold Corporation

on August 9, 2019.

Page | 2

Neither the TSX Venture Exchange nor its Regulation Services Provider (as that term is defined in the policies of the TSX

Venture Exchange) accepts responsibility for the adequacy or accuracy of this press release.

Cautionary Statement on Forward-Looking Information

All statements, other than statements of historical fact, contained in this press release constitute “forward-looking information” and “forward-

looking statements” within the meaning of certain securities laws and are based on expectations and projections as of the date of this press

release. Forward-looking statements contained in this press release include, without limitation, those related to:

• The Project’s permitting status and mine life;

• The growth potential from expanded mineral resources and exploration upside;

• The filing of an updated 43-101 technical report;

• The eventual positive construction decision for early H2-22;

• The Program’s expected commencement and duration, as well as the total meters to be drilled;

• The Program’s objectives and specific targets, and GMIN’s ability to achieve them;

• The Program improving the sampling coverage in the area above the pit and near the future infrastructure;

• The future property-wide exploration drilling at Tocantinzinho;

• The potential extension of the Project’s mine life, notably with satellite pits; and

• More generally, the above section entitled “Timetable and Next Steps”.

Forward-looking statements are bas ed on expectations, estimates and projections as of the time of this press release. Forward -looking

statements are necessarily based upon a number of estimates and assumptions that, while considered reasonable by the Corporation as of the

time of such stat ements, are inherently subject to significant business, economic and competitive uncertainties and contingencies. These

estimates and assumptions may prove to be incorrect. Such assumptions include, without limitation, the items listed on the above section

entitled “Timetable and Next Steps”.

Many of these uncertainties and contingencies can directly or indirectly affect, and could cause, actual results to differ ma terially from those

expressed or implied in any forward-looking statements. There can be no assurance that (i) the Program will de-risk the Project’s initial years of

production and will help optimizing mine planning, (ii) the known mineralization will be extended below the current pit design, (iii) th e follow-

up work on previous drill holes or on partially tested intervals will prove conclusive, (iv) the Project’s mineral reserves will be optimized, (v) the

“underexplored” 688 km2 land package will yield additional exploration potential, and (vi) the Corporation will bring the Project into commercial

production and will acquire any other significant precious metal asset, as future events could differ materially what is currently anticipated by

the Corporation.

By their very nature, forward -looking statements involve inherent risks and uncertainties, both general and specific, and risks exist that

estimates, fo recasts, projections and other forward -looking statements will not be achieved or that assumptions do not reflect future

experience. Forward-looking statements are provided for the purpose of providing information about management’s expectations and plans

relating to the future. Readers are cautioned not to place undue reliance on these forward-looking statements as several important risk factors

and future events could cause the actual outcomes to differ materially from the beliefs, plans, objectives, expectations, anticipations, estimates,

assumptions and intentions expressed in such forward-looking statements. All the forward-looking statements made in this press release are

qualified by these cautionary statements and those made in the Corporation’s other filings with the securities regulators of Canada including,

but not limited to, the cautionary statements made in the relevant section of the Corporation’s Management Discussion & Analysis. The

Corporation cautions that the foregoing list of factors that may affect future results is not exhaustive, and new, unforeseeable risks may arise

from time to time. The Corporation disclaims any intention or obligation to update or revise any forward-looking statements or to explain any

material difference between subsequent actual events and such forward-looking statements, except to the extent required by applicable law.

Page | 8

Figure 1 – Example of early years ore blocks and locally sparse drilling above a conceptual Phase 1 pit design.