Global Atomic Provides Update on the Dasa Project U.S. Development Bank Confirms Schedule for Dasa Funding Approval

Corporate Updates

NEWS RELEASE

Global Atomic Provides Update on the Dasa Project

U.S. Development Bank Confirms Schedule for Dasa Funding Approval

Toronto, ON, October 29, 2024: Global Atomic Corporation (“Global Atomic” or the “Company”),

(TSX: GLO, OTCQX: GLATF, FRANKFURT: G12) is pleased to provide an update on its Dasa Project

in the Republic of Niger . Dasa is the highest-grade uranium deposit in Africa surpassed only by

grades found in Canada’s Athabasca Basin and is scheduled to achieve commercial production in

early 2026.

PROJECT FINANCING

As indicated by the U.S. development bank (the “Bank”) with whom the Company is engaged in

project finance discussions and disclosed by the Company on October 3, 2024, the Bank has

provided an updated schedule for the approval of a debt facility to fund the development of Dasa.

In recent positive meetings with the Company, the Bank confirmed its support for Dasa and its

intention to approve a debt facility for US$295 million, which will cover 60% of the planned

project costs. By early Q1 2025, t he Bank intends to conclude its approval process, including

Committee and Board level approvals.

President and CEO of Global Atomic, Stephen G. Roman, stated, “Receiving this update from the

U.S. development bank is good news. Although we continue to assess a number of other financing

options, we believe the development bank offers the best financing solution for the benefit of our

shareholders and our nuclear power utility customers . The approval timelines outlined by the

bank support yellowcake deliveries in 2026 as anticipated in the four off -take agreements we

have in place with American and European nuclear power utilities.”

“To help fund the continuing development of Dasa until the bank funds are available, earlier this

month we raised C$40 million in an oversubscribed public offering. We take this opportunity to

thank our long-time supportive investors as well as many new shareholders for this strong show

of support for Global Atomic and the Dasa Project.”

In addition to the development bank , Global Atomic is in discussions with parties regarding

potential joint venture investment in the Dasa Project and other financing solutions.

The extension of the expiry date of common share purchase warrants issued pursuant to our

March 2023 financing from September 17, 2024, to December 31, 2024, as announced on

September 13, 2024, has been approved by the TSX.

Page 2 of 3

SITE UPDATE – PROESSING PLANT

Earthworks and civil engineering are progressing in preparation for the installation of plant

equipment, components of which are now arriving at site.

SITE UPDATE – MINING

The Main Fresh Air Raise is now complete, and the Return Air Raise is currently underway. Once

the fans have been installed, this significant expansion to the underground ventilation system

will allow mining activity to advance beyond the first level development and maintain a safe

working environment.

SITE UPDATE – HOUSING

Earthworks and civil engineering are well advanced with construction of a 400 -person facility

expected to be completed early Q1 2025.

TURKISH ZINC JOINT VENTURE

Zinc prices have continued to rise in recent months, positively impacting cash flow and the

Company’s share of returns from this operation. Due to the favo rable availability of Electric Arc

Furnace Dust (“EAFD”) from local steel mills in Iskenderun, Türkiye, the processing plant is

expected to run at a full capacity during Q4 2024.

About Global Atomic

Global Atomic Corporation ( www.globalatomiccorp.com) is a publicly listed company that

provides a unique combination of high- grade uranium mine development and cash-flowing zinc

concentrate production.

The Company’s Uranium Division is currently developing the fully permitted, large, high grade

Dasa Deposit, discovered in 2010 by Global Atomic geologists through grassroots field

exploration. The “First Blast Ceremony” occurred on November 5, 2022, and commissioning of

the processing plant is scheduled for Q1, 2026. Global Atomic has also identified 3 additional

uranium deposits in Niger that will be advanced with further assessment work.

Global Atomic’s Base Metals Division holds a 49% interest in the Befesa Silvermet Turkey, S.L.

(BST) Joint Venture, which operates a modern zinc recycling plant, located in Iskenderun, Türkiye.

The plant recovers zinc from Electric Arc Furnace Dust (EAFD) to produce a high-grade zinc oxide

concentrate which is sold to zinc smelters around the world. The Company's joint venture

partner, Befesa Zinc S.A.U. (B efesa) holds a 51% interest in and is the operator of the BST Joint

Venture. Befesa is a market leader in EAFD recycling, with approximately 50% of the European

EAFD market and facilities located throughout Europe, Asia and the United States of America.

Page 3 of 3

Key contacts:

Stephen G. Roman

Chairman, President and CEO

Tel: +1 (416) 368-3949

Email: [email protected]

Bob Tait

VP Investor Relations

Tel: +1 (416) 558-3858

Email: [email protected]

CAUTIONARY NOTE REGARDING FORWARD-LOOKING STATEMENTS:

The information in this release may contain forward-looking information under applicable securities laws. Forward-

looking information includes, but is not limited to, statements with respect to completion of any financings; Global

Atomics’ development pot ential and timetable of its operations, development and exploration assets; Global

Atomics’ ability to raise additional funds necessary; the future price of uranium; the estimation of mineral reserves

and resources; conclusions of economic evaluation; the realization of mineral reserve estimates; the timing and

amount of estimated future production, development and exploration; cost of future activities; capital and operating

expenditures; success of exploration activities; mining or processing issues; curr ency exchange rates; government

regulation of mining operations; and environmental and permitting risks. Generally, forward- looking statements

can be identified by the use of forward -looking terminology such as “plans”, “is expected”, “estimates”, variations

of such words and phrases or statements that certain actions, events or results “could”, “would”, “might”, “will be

taken”, “will begin”, “will include”, “are expected”, “occur” or “be achieved”. All information contained in this news

release, other than statements of current or historical fact, is forward-looking information. Statements of forward-

looking information are subject to known and unknown risks, uncertainties and other factors that may cause the

actual results, level of activity, performance or achievements of Global Atomic to be materially different from those

expressed or implied by such forward- looking statements, including but not limited to those risks described in the

annual information form of Global Atomic and in its public documents filed on SEDAR from time to time.

Forward-looking statements are based on the opinions and estimates of management at the date such statements

are made. Although management of Global Atomic has attempted to identify important factors that could cause

actual results to be materially different from those forward -looking statements, there may be other factors that

cause results not to be as anticipated, estimated or intended. There can be no assurance that such statements will

prove to be accurate, as actual results and future events could differ materially from those anticipated in such

statements. Accordingly, readers should not place undue reliance upon forward-looking statements. Global Atomic

does not undertake to update any forward-looking statements, except in accordance with applicable securities law.

Readers should also review the risks and uncertainties sections of Global Atomics’ annual and interim MD&As.

The Toronto Stock Exchange has not reviewed and does not accept responsibility for the adequacy and accuracy of

this news release.