NEWS RELEASE

Global Atomic Continues to Advance the Dasa Project, Including

Progressing Financing Options and Positive Engagement with Niger’s

Mines Minister

Toronto, ON, June 17, 2024: Global Atomic Corporation (“Global Atomic” or the “Company”),

(TSX: GLO, OTCQX: GLATF, FRANKFURT: G12) today provided an update on its financing and

development of the Dasa Uranium Project in the Republic of Niger, including:

 Updates on the approaches made to the Company to finance the development of the Dasa

Project and timeline for the approval of the proposed US$ 295 million debt financing facility

led by a US development bank

 Updates on the recent trip to Niger by President & CEO, Stephen G. Roman, CFO, Rein Lehari,

and Chief Technology Officer, Dr. Santiago Faucher

Dasa Uranium Project – Financing Options

To complete the project financing for the development of the Dasa Project, the Company has

received several approaches, including:

 The proposed US$2 95 million debt financing, led by a U.S. development bank which is

advancing to the approval stage;

 Approaches from a variety of sources for pre-payments on uranium delivery contracts;

 Approaches for a strategic equity investment into the Company from a number of financial

institutions and private equity firms;

 Approaches for a minority Joint Venture investment at the project level; and

 Approaches from investment banks for an equity financing.

The Company is actively considering the host of funding options available and intends to advance

several of the options in parallel in order to determine the preferred funding structure.

Dasa Uranium Project – Debt Financing

 The U.S. development bank that will provide the proposed US$295 million debt financing

facility for the development of the Dasa Project, has continued to actively make progress and

is completing the final documentation to submit to its Credit Committee for approval, which

has now been scheduled to take place in mid-July 2024.

 With approval at the Committee level, the Company expects final review by the bank’s Board

of Directors in September.

Global Atomic President and CEO, Stephen G. Roman commented: “ We are excited with the

prospect of partnering with the U.S development bank. We believe that the advancement of the

Dasa Project aligns with the strategic priorities of the United States Government and its efforts to

Page 2 of 5

secure uranium supply and reduce dependence on Russia . We believe the U.S. Government

recognizes the significance of the Dasa Project and its meaningful contribution to global uranium

supply diversification.”

Dasa Uranium Project – Recent Site Visit

During the recent visit to Niger, Company executives:

 Met with several government officials, including the Mines Minister, Commissaire Colonel

Ousmane Abarchi, who confirmed his support for Dasa and offered his office’s assistance to

streamline administrative bottlenecks and offer assistance to facilitate the timely importation

of supplies and equipment.

 Visited the Dasa site to review the progress of the underground development as well as the

earthworks being undertaken to prepare for the installation of the processing plant and the

associated camp for the construction crew.

 Witnessed the exemplary safety measures and practices of the SOMIDA team, which has now

achieved 675 days without a Lost Time Injury (“LTI”).

 Attended a meeting of the SOMIDA B oard of Directors, where our new Board chairman Mr.

Abdourazakou Abdou Moumouni, who represents the office of the President of Niger , was

appointed. The new Chairman is an experienced mining engineer having worked previously

at Orano Mining’s Cominak and Somair mines.

Global Atomic President and CEO, Stephen G. Roman commented, “During my most recent trip

to Niger, I had the privilege of meeting Niger’s Mines Minister. The Government of Niger continues

to provide strong support for Dasa, and praised SOMIDA’s progress to date, which he witnessed

during his site visit in early May.”

“At our Dasa Project, I was pleased with the morale, work ethic and progress being made by the

mining and site development teams. From mining to camp construction to site preparation for

the plant to equipment maintenance to health and safety to community engagement, the whole

team is working well together and making excellent progress.”

“The implementation of innovative solutions, such as controlled blasting of large surface rocks to

assist the work of the rock-breaking equipment, are accelerating our pace to complete the project

on time and on budget . I commend the Dasa team for keeping the project on schedule and for

implementing best-practice operating policies to keep the team productive and safe.”

“The key area of focus at Dasa is logistics. Hundreds of trucks bearing plant equipment and mining

supplies will be arriving at site between now and the end of construction in Q4 2025. The

continued closure of the Benin border prevents access to the port of Cotonou, the closest and

historically most used ocean port for Niger. While we are having success using other ports, delays

can occur from time to time at various points along these extended routes . The government

assistance offered to us by the Mines Minister to help expedite our inbound shipments is very

much appreciated as the timely importation of materials is critical for Dasa and the realization of

Page 3 of 5

the tremendous benefits that Dasa can deliver to our shareholders, the Niger government , its

people and further reduce dependance on fossil fuels and electrify the world economy through

clean and reliable nuclear energy.”

“We look forward to the final approval of our debt facility by the US development bank in Q3 to

finance the Dasa processing plant . T he debt financing facility will provide 60% of the project

funding and 50% of cost overruns, if any. The Company has already invested approximately US$90

million of the required equity portion of the Dasa financing and is well advanced with project

development.”

Below are photos of Management’s recent site visit which are available on the Company’s

website www.globalatomiccorp.com.

Figure 1: Management visits Niger's Mines Minister, Commissaire Colonel Ousmane Abarchi

Page 4 of 5

Figure 2: Operating Team inspecting the ore face

Figure 3: Department Heads morning meeting

Page 5 of 5

About Global Atomic

Global Atomic Corporation ( www.globalatomiccorp.com) is a publicly listed company that

provides a unique combination of high- grade uranium mine development and cash-flowing zinc

concentrate production.

The Company’s Uranium Division is currently developing the fully permitted, large, high grade

Dasa Deposit, discovered in 2010 by Global Atomic geologists through grassroots field

exploration. The “First Blast Ceremony” occurred on November 5, 2022, and commissioning of

the processing plant is scheduled for Q1, 2026 . Global Atomic has also identified 3 additional

uranium deposits in Niger that will be advanced with further assessment work.

Global Atomic’s Base Metals Division holds a 49% interest in the Befesa Silvermet Turkey, S.L.

(BST) Joint Venture, which operates a modern zinc recycling plant, located in Iskenderun, Türkiye.

The plant recovers zinc from Electric Arc Furnace Dust (EAFD) to produce a high-grade zinc oxide

concentrate which is sold to zinc smelters around the world. The Company's joint venture

partner, Befesa Zinc S.A.U. (B efesa) holds a 51% interest in and is the operator of the BST Joint

Venture. Befesa is a market leader in EAFD recycling, with approximately 50% of the European

EAFD market and facilities located throughout Europe, Asia and the United States of America.

Key contacts:

Stephen G. Roman

Chairman, President and CEO

Tel: +1 (416) 368-3949

Email: [email protected]

Bob Tait

VP Investor Relations

Tel: +1 (416) 558-3858

Email: [email protected]

The information in this release may contain forward-looking information under applicable securities laws. Forward -looking information includes, but is not limited to, statements with respect to completion of

any financings; Global Atomics’ development potential and timetable of its operations, development and exploration assets; Global Atomics’ ability to raise additional funds necessary; the future price of uranium;

the estimation of mineral reserves and resources; conclusions of economic evaluation; the realization of mineral reserve estimates; the timing and amount of estimated future production, development and

exploration; cost of future activities; capital and operating expenditures; success of exploration activities; mining or processing issues; currency exchange rates; government regulation of mining operations; and

environmental and permitting risks. Generally, forward-looking statements can be identified by the use of forward-looking terminology such as “plans”, “is expected”, “estimates”, variations of such words and

phrases or statements that certain actions, events or results “could”, “would”, “might”, “will be taken”, “will begin”, “will include”, “are expected”, “occur” or “be achieved”. All information contained in this

news release, other than statements of current or historical fact, is forward -looking information. Statements of forward -looking information are subject to known and unknown risks, uncertainties and other

factors that may cause the actual results, level of activity, performance or achievements of Global Atomic to be materially different from those expressed or implied by such forward-looking statements, including

but not limited to those risks described in the annual information form of Global Atomic and in its public documents filed on SEDAR from time to time.

Forward-looking statements are based on the opinions and estimates of management at the date such statements are made. Although management of Global Atomic has attempted to identify important factors

that could cause actual results to be materially different from those forward-looking statements, there may be other factors that cause results not to be as anticipated, estimated or intended. There can be no

assurance that such statements will prove to be accurate, as actual results and future events could d iffer materially from those anticipated in such statements. Accordingly, readers should not place undue

reliance upon forward-looking statements. Global Atomic does not undertake to update any forward-looking statements, except in accordance with applicable securities law. Readers should also review the risks

and uncertainties sections of Global Atomics’ annual and interim MD&As.

The Toronto Stock Exchange has not reviewed and does not accept responsibility for the adequacy and accuracy of this news release.