Giga files Preliminary Economic Assessment Models production of High-grade Nickel Concentrate from the Turnagain Nickel Deposit

Economic Studies

November 20, 2020 TSX.V – GIGA

Giga files Preliminary Economic Assessment

Models production of High-grade Nickel Concentrate from the Turnagain Nickel Deposit

Vancouver, B.C. – Giga Metals Corp. (TSX.V: GIGA) announced today that, further to its news

release dated October 28, 2020, it has filed the associated National Instrument 43 -101 Standards

of Disclosure for Mineral Projects ( NI 43 -101) technical report for the Preliminary Economic

Assessment (PEA) for its wholly-owned Turnagain Project in northwest British Columbia. The

Report is dated November 18 , 2020 and can be found under the Company’s profile at

www.sedar.com and on the Company’s web site.

The PEA was prepared by Hatch Ltd of Vancouver, Canada with the assistance of Kirkham

Geosystems Ltd . (mineral resources), Knight Piésold Ltd. (tailings management), Blue Coast

Metallurgy Ltd . (metallurgical testing and process design), Kerr Wood Leidal As sociates Ltd.

(power supply), and Wood Mackenzie Ltd . (market analysis). Giga is pleased to report there are

no material differences between the key results contained in the PEA and the news release dated

October 28, 2020.

The project is estimated to produ ce nickel in concentrate with a low greenhouse gas footprint

(Scope 1 and Scope 2) of <2.5 t/t Ni over the project life. Should electric mining fleet equipment

become available in suitable capacities, the use of such a fleet is expected to reduce greenhous e

gas emissions to <0.7 t/t nickel. At these rates, the CO2-sequestering capabilities of the Turnagain

tailings may enable the project to be carbon-neutral.

The Turnagain PEA demonstrates the potential for establishing a long-life open-pit mine and mill

using conventional froth flotation technology to produce high-grade nickel sulphide concentrate.

With a phased implementation to a facility with a throughput rate of 90,000 tonnes per day, annual

production is projected to average more than 33,000 tonnes per year nickel (73 million pounds per

year) for a project life of 37 years. A summary of the PEA highlights is provided in Table 1. The

PEA has identified numerous opportunities for project improvement.

Table 1 – Turnagain Project PEA Life-of-Mine Results and Assumptions (US$)

All parameters annual average except

construction and sustaining capital cost

Phase 1 (Y1-5)

Average

Phase 2 (Y6-20)

Average

LoM (Y1-37)

Average

Ore Processed (Mt) 15.3 32.7 30.3

Nickel Grade (%) 0.260 0.220 0.221

Nickel Recovery (%) 57.3 51.6 49.6

Nickel Production (t in concentrate) 22,754 37,149 33,215

Cobalt Production (t in concentrate) 1,379 2,224 1,962

($/t ore) $9.63 $7.99 $7.89

($/lb Ni) $2.93 $3.20 $3.27

Net Operating Cost ($/lb Ni) $2.77 $3.04 $3.12

Construction Capital Cost ($M) – total $1,381 $532 $1,913

Sustaining Capital Cost ($M) - total $274 $1,011 $2,000

Base Case Nickel Price / Payability $7.50/lb / 78%

Base Case Cobalt Price / Payability $22.30/lb / 35%

Base Case Pre-tax IRR / NPV (8%) 6.3% / ($269M)

ESG Case Nickel Price / Payability $8.50/lb / 78%

ESG Case Cobalt Price / Payability $22.30/lb / 35%

ESG Case Pre-tax IRR / NPV (8%) 9.4% / $242M

Cautionary Statements

The PEA is preliminary in nature, it includes inferred mineral resources that are considered too speculative

geologically to have the economic considerations applied to them that would enable them to be categorized

as mineral reserves, and, as such, there is no certainty that the PEA results will be realized.

Qualified Persons

The technical content of this news release has been prepared and reviewed by Lyle Trytten, P.Eng., a

Qualified Person under NI 43-101 standards.

About Giga Metals Corporation

Giga Metals Corporation is focused on metals critical to modern batteries, especially those used in Electric

Vehicles and Energy Storage. The Company’s core asset is the Turnagain Project, located in northern

British Columbia, which contains one of the few sign ificant undeveloped sulphide nickel and cobalt

resources in the world.

Forward-looking Statements

Certain statements in this news release are forward -looking statements, which reflect the expectations of

management regarding the Turnagain Project. Forward-looking statements consist of statements that are

not purely historical, including any statements regarding beliefs, plans, expectations or intentions

regarding the future. Such statements include, but are not limited to, statements with respect to the fu ture

financial or operating performance of the Company and its mineral projects, the estimation of mineral

resources and mineral prices, steps to be taken towards commercialization of the resource, the timing and

amount of estimated future production and c apital, operating and exploration expenditures. Such

statements are subject to risks and uncertainties that may cause actual results, performance or

developments to differ materially from those contained in the statements. No assurance can be given that

any of the events anticipated by the forward-looking statements will occur or, if they do occur, what benefits

the Company will obtain from them. These forward-looking statements reflect management's current views

and are based on certain expectations, estim ates and assumptions which may prove to be incorrect,

including the list of additional work prior to requisitioning a Pre-feasibility study, and statements relating

to future exploration and development of the Project and mineral resource and mineral reserve estimations

relating to the Project. A number of risks and uncertainties could cause our actual results to differ

materially from those expressed or implied by the forward -looking statements, including: (1) the mineral

resource estimates relating to the Project could prove to be inaccurate for any reason whatsoever, (2) Giga

is unable to finance the Project, (3) prices for nickel and cobalt or project costs could differ substantially

and make any commercialization uneconomic, (4) inferred and indicated r esources may not materialize,

(5) permits, environmental opposition, government regulation, cost overruns or any of many other factors

may prevent the Company from commercializing the Turnagain Project, (6) additional but currently

unforeseen work may be r equired to advance to the pre -feasibility stage, and (7) even if the Project goes

into production, there is no assurance that operations will be profitable. These forward-looking statements

are made as of the date of this news release and, except as requir ed by applicable securities laws, the

Company assumes no obligation to update these forward-looking statements, or to update the reasons why

actual results differed from those projected in the forward -looking statements. Additional information

about these and other assumptions, risks and uncertainties are set out in the "Risks and Uncertainties"

section in the Company's most recent MD&A filed with Canadian security regulators.

On behalf of the Board of Directors,

MARK JARVIS

CEO

Tel - 604 681 2300

Neither TSX Venture Exchange nor its Regulation Services Provider (as that term is defined in policies of

the TSX Venture Exchange) accepts responsibility for the adequacy or accuracy of this release.