GoGold Provides Outlook for 2024, Parral Production and Update on Zinc Circuit Commissioning
GoGold Provides Outlook for 2024, Parral Production and Update on
Zinc Circuit Commissioning
Shares Outstanding: 328,222,500
Trading Symbols: TSX: GGD
OTCQX: GLGDF
HALIFAX, NS
,
Jan. 10, 2024
/CNW/ -
GoGold Resources Inc.
(TSX: GGD) (OTCQX: GLGDF)
("GoGold", "the Company")
is pleased to provide an
outlook of milestones and deliverables for 2024.
"2023 was another year of significant advancements of the Los Ricos district. In less than five years, we have taken the district from having no resources
to having 186 million silver equivalent (AgEq) ounces of measured & indicated resources and 87 million AgEq ounces of inferred resources. We also
completed two preliminary economic assessments ("PEA"), in each of Los Ricos South and Los Ricos North which showed a combined total NPV of
US$871M
for the district. Additionally, in 2023 we applied for a permit to construct a mine at Los Ricos South. We're very proud of our technical team's
ability to achieve these significant accomplishments in less than five years at Los Ricos, and now we look to the future,"
Brad Langille
, President and CEO
stated. "In 2024, we see the following key milestones:
Complete commissioning of SART Zinc circuit in January at Parral, as we enter our tenth year of production;
Advancing directly from the PEA completed at Los Ricos South in 2023 to a definitive feasibility study to be completed within first six months of 2024;
Completion of Los Ricos South mine permitting technical review process in first calendar quarter of 2024, anticipating receipt of permit by mid year
pending governmental review;
Make construction decision at Los Ricos South after completion of feasibility study and receipt of mine permit;
Initiate construction of electrical and water infrastructure at Los Ricos South by end of 2024;
Enter into definitive agreement on debt financing for balance of funds required for construction of Los Ricos South, initial discussions with prospective
lenders have generated significant interest;
Assess potential debt financing options that will allow flexibility to advance Los Ricos North towards a construction decision during the potential
construction of Los Ricos South.
With the above and supported by our strong balance sheet including our year end cash balance of
$95 million USD
(see financial results PR dated
December 19, 2023
), 2024 is sure to be a transformational year for GoGold as it advances towards a substantial low-cost silver producer."
Parral Update
At Parral, the SART Zinc circuit was constructed on time and on budget over the previous two quarters, and the commissioning process should be
completed by the end of January.
Summary of Zinc circuit effects:
Saleable zinc precipitate to be added to the revenue stream;
Regeneration of approximately 750 tons of cyanide per quarter;
Anticipated to generate net increased cash flows of
$1.5 million
per quarter;
Zinc circuit capital expenditure as planned at
$2 million
over 6 month construction period;
Project payback expected within 6 months after construction;
Parral up to end of its mine life will be a producer of silver, gold, copper and zinc;
Expected to result in better precious metals recovery;
Completed on time and on budget.
"The completion of the zinc circuit in the SART is important as it expected to generate approximately
$500,000
per month for cash flow, which will pay
back the
$2M
capex quickly. We believe it will improve the metallurgical recoveries of gold and silver on the material which we are processing currently, so
we expect to see production increase once commissioning is completed," said Brad Langille, President and CEO.
Table 1: Quarterly Production Summary
Quarter Ended
Sep 2022
Dec 2022
Mar 2023
Jun 2023
Sep 2023
Dec 2023
Silver Production (oz)
145,944
159,838
173,717
203,894
169,443
109,016
Gold Production (oz)
2,278
2,399
2,016
1,512
1,106
1,848
Copper Production (tonnes)
124
222
143
135
115
95
Silver Equivalent Production (oz)
1
400,467
441,217
400,145
375,112
300,789
300,260
1. "Silver equivalent production" include gold ounces and copper tons produced and converted to a silver
equivalent based on a ratio of the average market metal price for each period. The gold:silver ratio for
each of the periods presented was: Sep 2022 – 90, Dec 2022 – 82, Mar 2023 – 84, Jun 2023 – 82, Sep
2023 – 83, Dec 2023 – 85. The copper:silver ratios were: Jun 2022 – 415, Sep 2022 – 398, Dec 2022 –
377, Mar 2023 – 399, Jun 2023 – 352, Sep 2023 – 356, Dec 2023 – 356.
Los Ricos South
During 2023, the Company completed an updated Mineral Resource Estimate ("MRE") and updated PEA at Los Ricos South, with details provided below.
For 2024, GoGold will work with our technical team and consultants to complete all engineering and technical work required to make a construction
decision on the project in the upcoming year. As part of this work, the Company is in the process of completing a definitive feasibility study and front-end
engineering design which is expected to be released in the first six months of 2024, and advancing the mine permitting application process. P&E Mining
Consultants Inc. has been selected as the lead author of the study, supported by Ausenco for the process and mill design.
2023 Mineral Resource Estimate and PEA
The Los Ricos South Mineral Resource Estimate and PEA were previously announced in a news release dated
September 12, 2023
, with an effective
date of the Report of
September 12, 2023
. See that news release or the 43-101 compliant technical report filed on SEDAR on
October 27, 2023
for
details, in addition to the following summary.
Highlights of the PEA, with a base case silver price of
US$23.75
/oz and gold price of
US$1,850
/oz are as follows (all figures in US dollars unless
otherwise stated):
After-Tax net present value ("NPV") (using a discount rate of 5%) of
US$458 Million
with an After-Tax IRR of 37% (Base Case);
11-year mine life producing a total of 88 Million payable silver equivalent ounces ("AgEq"), consisting of 47 Million silver ounces, 493 Thousand gold
ounces, and 14 Million pounds of copper;
Initial capital costs of
$148 Million
, including
$19 Million
in contingency costs, over an expected 18 month build, additional expansion capital of
$69
Million
, and sustaining capital costs of
$72 Million
over the life of mine ("LOM");
Average LOM operating cash costs of
$8.15
/oz AgEq, and all in sustaining costs ("AISC") of
$9.02
/oz AgEq
Average annual production of 8 Million AgEq oz;
Approximately half of LOM metal production is long hole underground ("UG"), and approximately half is open pit ("OP") mining.
Highlights of the updated Mineral Resource:
Increase of 55% in Measured & Indicated Silver Equivalent ("AgEq") Ounces from initial
January 2021
MRE, with 39% increase in Measured &
Indicated AgEq grade;
Inclusion of 1.9 Million tonnes Measured & Indicated at excellent grade of 516 g/t AgEq in underground Eagle Deposit;
Measured & Indicated Mineral Resource at LRS of 98.6 Million ounces AgEq grading 276 g/t AgEq contained in 11.1 Million tonnes ("Mt");
Increased confidence in MRE, with conversion of approximately 9 Million ounces AgEq from initial
January 2021
Inferred Mineral Resources to
Measured & Indicated, resulting in 13.6 Million ounces AgEq in Inferred Mineral Resources at LRS grading 185 g/t AgEq contained in 2.3 Mt;
Total Los Ricos Measured & Indicated Mineral Resources of 186 Million ounces AgEq, including Los Ricos North
Total Los Ricos Inferred Mineral Resources of 84 Million ounces AgEq, including Los Ricos North
Table 2 – LRS PEA Key Economic Assumptions and Results
Assumption / Result
Unit
Value
Assumption / Result
Unit
Value
Total OP Plant Feed Mined
kt
9,367
Net Revenue
US$M
2,049
Total UG Plant Feed Mined
kt
4,325
Initial Capital Costs
US$M
148
Total Plant Feed Mined
kt
13,692
Expansion Capital Costs
US$M
69
Operating Strip Ratio
Ratio
7.4
Sustaining Capital Costs
US$M
72
Silver Grade
1
g/t
125
OP Mining Costs
$/t Plant Feed
12.13
Gold Grade
1
g/t
1.18
UG Mining Costs
$/t Plant Feed
43.85
AgEq Grade
1
g/t
217
LOM Mining Costs
$/t Plant Feed
22.15
Silver Recovery
%
86
Operating Cash Cost
US$/oz AgEq
8.15
Gold Recovery
%
95
All in Sustaining Cost
US$/oz AgEq
9.02
Silver Price
US$/oz
23.75
Mine Life
Yrs
11
Gold Price
US$/oz
1,850
Average process rate
t/day
3,359
Copper Price
US$/lb
4.00
After-Tax NPV (5% discount)
US$M
458
Payable Silver Metal
Moz
46.8
Pre-Tax NPV (5% discount)
US$M
708
Payable Gold Metal
koz
493.1
After-Tax IRR
%
36.6
Payable Copper
Mlb
13.6
Pre-Tax IRR
%
49.1
Payable AgEq
Moz
87.5
After-Tax Payback Period
Yrs
2.3
1. Grades shown are LOM average process plant feed grades including both OP and UG sources. External dilution of approximately 10%
for OP material and 28% for UG material was incorporated in the mining schedule.
Los Ricos South Mineral Resource Estimate
The basis for the PEA is the Mineral Resource Estimate completed by P&E for the Los Ricos South Project located in Jalisco State,
Mexico
, which has an
effective date of
September 12, 2023
, which is available on SEDAR. A summary of the Mineral Resource Estimate is provided in Table 3.
Table 3: Los Ricos South Mineral Resource Estimate – Pit Constrained and Out-of-Pit
(1-9)
Mining Area
Category
Tonnes
Average Grade
Contained Metal
Au
Ag
Cu
AuEq
AgEq
Au
Ag
Cu
AuEq
AgEq
(M)
(g/t)
(g/t)
( %)
(g/t)
(g/t)
(koz)
(koz)
(Mlb)
(koz)
(koz)
Pit Constrained
5
Measured
3.9
1.08
142
0.03
2.94
231
135.9
17,858
2.3
369.1
28,898
Indicated
2.8
0.68
89
0.03
1.87
146
60.7
8,022
1.9
167.3
13,097
M&I
6.7
0.91
120
0.03
2.49
195
196.6
25,880
4.2
536.4
41,995
Inferred
0.5
0.58
99
0.04
1.91
150
9.6
1,632
0.4
31.4
2,460
Pit - Cerro C
6
Inferred
0.9
0.72
31
0.01
1.12
88
20.9
905
0.2
32.8
2,568
Out-of-Pit
7,8
Measured
0.7
3.60
298
0.35
7.94
621
80.7
6,679
5.4
178.1
13,940
Eagle
Indicated
1.2
3.13
164
0.37
5.79
453
117.5
6,176
9.5
217.5
17,028
M&I
1.9
3.30
214
0.36
6.59
516
198.2
12,855
15.0
395.6
30,969
Inferred
0.1
3.63
122
0.54
6.00
470
7.8
261
0.8
12.9
1,006
Out-of-Pit
7,8
Measured
1.1
1.22
194
0.06
3.79
297
44.7
7,093
1.6
138.8
10,865
Main
Indicated
1.4
1.58
178
0.21
4.18
327
71.5
8,013
6.6
188.4
14,753
M&I
2.5
1.42
185
0.15
4.00
313
116.2
15,106
8.1
327.2
25,618
Inferred
0.8
1.42
133
0.41
3.73
292
36.8
3,431
7.2
96.6
7,566
Total
Measured
5.7
1.42
172
0.07
3.72
291
261.4
31,631
9.3
686.0
53,703
Indicated
5.4
1.45
129
0.15
3.33
260
249.7
22,210
18.0
573.2
44,878
M&I
11.1
1.43
151
0.11
3.53
276
511.0
53,841
27.3
1,259.2
98,582
Inferred
2.3
1.02
85
0.17
2.36
185
75.0
6,230
8.6
173.7
13,601
1.
Mineral Resources which are not Mineral Reserves do not have demonstrated economic viability. The estimate of Mineral Resources may be materially affected by environmental, permitting, legal, title, taxation, socio-political, marketing, or other relevant issues.
2.
The Inferred Mineral Resource in this estimate has a lower level of confidence than that applied to an Indicated Mineral Resource and must not be converted to a Mineral Reserve. It is reasonably expected that the majority of the Inferred Mineral Resource could be upgraded
to an Indicated Mineral Resource with continued exploration.
3.
The Mineral Resources in this news release were estimated in accordance with the Canadian Institute of Mining, Metallurgy and Petroleum (CIM), CIM Standards on Mineral Resources and Reserves, Definitions and Guidelines prepared by the CIM Standing Committee on
Reserve Definitions and adopted by the CIM Council.
4.
Historically mined areas were depleted from the Mineral Resource model.
5.
The pit constrained AgEq cut-off grade of 38 g/t Ag was derived from US$1,800/oz Au price, US$23.00/oz Ag price, 85% Ag and 95% Au process recovery, US$25/tonne process and G&A cost. The constraining pit optimization parameters were $2.10/t mineralized material
and waste mining cost, and 45-degree pit slopes.
6.
Cerro Colorado Resource constrained to open pit mining methods only; out-of-pit Mineral Resources are restricted to the Eagle and Abra mineralized veins, which exhibit historical continuity and reasonable potential for extraction by cut and fill and longhole mining methods.
7.
The out-of-pit AgEq cut-off grade of 130 g/t Ag was derived from US$1,800/oz Au price, US$23.00/oz Ag price, 85% Ag and 95% Au process recovery, US$33/tonne process and G&A cost, and a $50/tonne mining cost. The out-of-pit Mineral Resource grade blocks were
quantified above the 130 g/t AgEq cut-off, below the constraining pit shell and within the constraining mineralized wireframes. Out–of-Pit Mineral Resources are restricted to the Los Ricos and Rascadero Veins, which exhibit historical continuity and reasonable potential for
extraction by cut and fill and longhole mining methods.
8.
AgEq and AuEq were calculated at an Ag/Au ratio of 78.2:1 for pit constrained and out-of-pit Resources.
9.
Totals may not sum due to rounding.
Los Ricos North
During 2023, the Company completed an updated PEA at Los Ricos North. For 2024, the Company will assess all technical and debt financing proposals
that may allow the continued advancement of the project towards a construction decision, even during a potential construction phase of Los Ricos South
should a construction decision be made on that project.
The highlights of the PEA were previously announced in a news release dated
May 17, 2023
, and the effective date of the Report is
May 17, 2023
. See
that news release or the 43-101 compliant technical report filed on SEDAR on
June 30, 2023
for details, in addition to the following summary.
Highlights of the PEA, with a base case silver price of
US$23
/oz and gold price of
US$1,800
/oz are as follows (all figures in US dollars unless otherwise
stated):
After-Tax NPV (using a discount rate of 5%) of
$413 Million
with an After-Tax IRR of 29% (Base Case);
13-year mine life producing a total of 110.3 Million payable silver equivalent ounces ("AgEq"), consisting of 68.0 Million silver ounces, 221,700 gold
ounces, 22.8 Million pounds of copper, 144.1 Million pounds of lead and 242.2 Million pounds of zinc;
Initial capital costs of
$221 Million
, including
$29 Million
in contingency costs, over an expected 18 month build, additional expansion capital of
$137
Million
, and sustaining capital costs of
$6 Million
over the life of mine ("LOM");
Average LOM operating cash costs of
$9.50
/oz AgEq, and all in sustaining costs ("AISC") of
$9.68
/oz AgEq
Average annual production of 8.8 Million AgEq oz in years one through twelve;
Approximately 3/4 of LOM production is from four open pits containing oxide mineralization and approximately 1/4 is from a separate open pit which
contains only sulphide mineralization.
Table 4 – Los Ricos North PEA Key Economic Assumptions and Results
Assumption / Result
Unit
Value
Assumption / Result
Unit
Value
Total Oxide Feed Mined
kt
25,557
Net Revenue
US$M
2,307
Total Sulphide Feed Mined
kt
9,964
Initial Capital Costs
US$M
221
Total Plant Feed Mined
kt
35,521
Expansion and Sustaining Capital Costs
US$M
143
Total Strip Ratio
Ratio
6.0
Mining Costs
$/t Mined
2.07
Mine Life
Yrs
13
Mining Costs
$/t Plant Feed
12.28
Average process rate
t/day
8,000
Operating Cash Cost
US$/oz AgEq
9.50
Silver Price
US$/oz
23.00
All in Sustaining Cost
US$/oz AgEq
9.68
Gold Price
US$/oz
1,800
After-Tax NPV (5% discount)
US$M
413
Copper Price
US$/lb
4.00
Pre-Tax NPV (5% discount)
US$M
645
Lead Price
US$/lb
1.00
After-Tax IRR
%
29.1
Zinc Price
US$/lb
1.40
Pre-Tax IRR
%
39.8
Payable AgEq
Moz
110.3
After-Tax Payback Period
Yrs
3.0
Table 5 – Los Ricos North PEA Summary of Physical Attributes
Attribute
Unit
Oxide
Sulphide
Total
Plant Feed Mined
kt
25,557
9,964
35,521
Silver Grade
1
g/t
83.2
30.1
68.3
Gold Grade
1
g/t
0.29
0.07
0.23
Copper Grade
1
%
-
0.12
-
Lead Grade
%
-
0.87
-
Zinc Grade
%
-
1.24
-
Silver Recovery
%
87
88
87
Gold Recovery
%
87
76
86
Copper Recovery
%
-
89
89
Lead Recovery
%
-
75
75
Zinc Recovery
%
-
89
89
Payable Silver
Moz
59.5
8.5
68.0
Payable Gold
koz
205.2
16.5
221.7
Payable Copper
Mlb
-
22.8
22.8
Payable Lead
Mlb
-
144.1
144.1
Payable Zinc
Mlb
-
242.2
242.2
Payable AgEq
Moz
75.5
34.8
110.3
1. Grades shown are LOM average plant feed grades. Dilution of approximately 10% was used.
Los Ricos North – Mineral Resource Estimate
The basis for the PEA is the Mineral Resource Estimate completed by P&E in the National Instrument 43-101 Technical Report on the Initial Mineral
Resource Estimate for the Los Ricos North Project located in Jalisco State,
Mexico
, which has an effective date of
December 1, 2021
. A summary of the
Mineral Resource Estimate is provided in Table 6.
Table 6: Los Ricos North Mineral Resource Estimate
(1-11)
Deposit
Tonnes
Average Grade
Contained Metal
Au
Ag
Cu
Pb
Zn
AuEq
AgEq
Au
Ag
Cu
Pb
Zn
AuEq
AgEq
(Mt)
(g/t)
(g/t)
( %)
( %)
( %)
(g/t)
(g/t)
(koz)
(koz)
(Mlb)
(Mlb)
(Mlb)
(koz)
(koz)
Indicated:
El Favor
7.7
0.27
98
-
-
-
1.61
119
68
24,413
-
-
-
399
29,454
Casados
3.2
0.42
124
-
-
-
2.09
154
43
12,871
-
-
-
218
16,061
La Trini
3.1
0.54
74
-
-
-
1.54
114
54
7,428
-
-
-
155
11,424
Mololoa
0.4
0.36
130
-
-
-
2.12
157
5
1,788
-
-
-
29
2,161
Silver-Gold
Oxide Zone
14.5
0.37
100
-
-
-
1.71
127
171
46,500
-
-
-
801
59,100
El Orito Sulphide
Zone
1
7.8
0.06
28
0.11
0.88
1.33
1.55
114
15
7,011
19
151
229
389
28,708
Total Indicated
22.3
1.66
122
186
53,510
1,190
87,808
Inferred:
El Favor
12.4
0.27
89
-
-
-
1.47
108
106
35,505
-
-
-
587
43,350
Casados
1.8
0.35
108
-
-
-
1.82
135
21
6,323
-
-
-
106
7,843
La Trini
0.1
0.43
108
-
-
-
1.89
139
1
201
-
-
-
4
260
Mololoa
0.7
0.39
94
-
-
-
1.66
122
9
2,102
-
-
-
37
2,739
Silver-Gold
Oxide Zone
15.0
0.28
91
-
-
-
1.52
112
136
44,131
-
-
-
734
54,191
El Orito Sulphide
Zone
1
5.5
0.06
28
0.12
0.74
1.20
1.46
108
11
4,888
15
90
146
258
19,007
Total Inferred
20.5
1.51
111
148
49,019
992
73,198
1.
El Orito is a silver-base metal sulphide zone, all other deposits are silver-gold oxide zones.
2.
Mineral Resources which are not Mineral Reserves do not have demonstrated economic viability. The estimate of Mineral Resources may be materially affected by environmental, permitting, legal, title, taxation, socio-political, marketing, or other relevant issues.
3.
The Inferred Mineral Resource in this estimate has a lower level of confidence than that applied to an Indicated Mineral Resource and must not be converted to a Mineral Reserve. It is reasonably expected that the majority of the Inferred Mineral Resource could be upgraded
to an Indicated Mineral Resource with continued exploration.
4.
The Mineral Resources in this news release were estimated in accordance with the Canadian Institute of Mining, Metallurgy and Petroleum (CIM), CIM Standards on Mineral Resources and Reserves, Definitions and Guidelines (2014) prepared by the CIM Standing Committee
on Reserve Definitions and adopted by the CIM Council and CIM Best Practices (2019).
5.
Historically mined areas were depleted from the Mineral Resource model.
6.
Approximately 98.9% of the Indicated and 91.3% of the Inferred contained AgEq ounces are pit constrained, with the remainder out-of-pit. See tables 4 and 6 for details of the split between pit constrained and out-of-pit deposits.
7.
The pit constrained AgEq cut-off grade of 29 g/t Ag was derived from US$1,550/oz Au price, US$21/oz Ag price, US$3.66/lb Cu, US$0.90/lb Pb, US$1.26/lb Zn, 93% process recovery for Ag and Au, 90% process recovery for Cu, 80% process recovery for Pb and Zn,
US$18/tonne process and G&A cost. The constraining pit optimization parameters were US$2.00/t mineralized mining cost, US$1.50/t waste mining cost and 50-degree pit slopes.
8.
The out-of-pit AuEq cut-off grade of 119 g/t Ag was derived from US$1,550/oz Au price, US$21/oz Ag price, US$3.66/lb Cu, US$0.90/lb Pb, US$1.26/lb Zn, 93% process recovery for Ag and Au, 90% process recovery for Cu, 80% process recovery for Pb and Zn, US$57/t
mining cost, US$18/tonne process and G&A cost. The out-of-pit Mineral Resource grade blocks were quantified above the 119 g/t AgEq cut-off, below the constraining pit shell within the constraining mineralized wireframes and exhibited sufficient continuity to be
considered for cut and fill and longhole mining
9.
No Mineral Resources are classified as Measured.
10.
AgEq and AuEq calculated at an Ag/Au ratio of 73.8:1.
11.
Totals may not agree due to rounding
Los Ricos District – Combined Mineral Resource Estimate
The Los Ricos District, including both Los Ricos North and Los Ricos South, has a combined 186 million measured & indicated silver equivalent ounces and
84 million inferred silver equivalent ounces in Mineral Resource Estimates. See Figure 1 and Table 7 below for details.
Figure 1 – Los Ricos District Mineral Resources (CNW Group/GoGold Resources Inc.)
Table 7: Los Ricos Mineral Resources – LRS & LRN
(1-4)
Deposit
Tonnes
Average Grade
Contained Metal
Au
Ag
Cu
Pb
Zn
AuEq
AgEq
Au
Ag
Cu
Pb
Zn
AuEq
AgEq
(M)
(g/t)
(g/t)
( %)
( %)
( %)
(g/t)
(g/t)
(koz)
(koz)
(Ml
b
)
(Ml
b
)
(Ml
b
)
(koz)
(koz)
LRS Measured
1
5.7
1.42
172
0.07
3.72
291
261
31,631
9
-
-
686
53,703
Indicated:
LRN (Oxide)
2
14.5
0.37
100
-
-
-
1.71
127
171
46,500
-
-
-
801
59,100
LRS (Oxide)
1
5.4
1.45
129
0.15
-
-
3.33
260
250
22,210
18
-
-
573
44,878
LRN (Sulfide)
2
7.8
0.06
28
0.11
0.88
1.33
1.55
114
15
7,011
19
151
229
389
28,708
Total Indicated
27.7
1.98
149
436
75,721
37
151
229
1,763
132,686
Measured & Indicated
33.4
2.28
174
697
107,352
46
151
229
2,449
186,390
Inferred:
LRN (Oxide)
2
15.0
0.28
91
-
-
-
1.52
112
136
44,131
-
-
-
734
54,191
LRS (Oxide)
1
2.3
1.02
85
0.17
-
-
2.36
185
75
6,230
9
-
-
174
13,601
LRN (Sulfide)
2
5.5
0.06
28
0.12
0.74
1.2
1.46
108
11
4,888
15
90
146
258
19,007
Total Inferred
22.8
1.59
119
222
55,249
24
90
146
1,166
86,799
1.
See Table 3 notes for assumptions
2.
See Table 6 notes for assumptions
3.
AgEq and AuEq calculated at an Ag/Au ratio of 87.5.
4.
Totals may not agree due to rounding.
Mr. Robert Harris, P.Eng. is the qualified person as defined by National Instrument 43-101 and is responsible for the technical information of this release
related to Parral.
Mr.
David Duncan
, P. Geo. is the qualified person as defined by National Instrument 43-101 and is responsible for the technical information of this release
related to Los Ricos North and Los Ricos South.
About GoGold Resources
GoGold Resources (TSX: GGD) is a Canadian-based silver and gold producer focused on operating, developing, exploring and acquiring high quality
projects in
Mexico
. The Company operates the Parral Tailings mine in the
state of Chihuahua
and has the Los Ricos South and Los Ricos North
exploration projects in the state of
Jalisco
. Headquartered in
Halifax, NS
, GoGold is building a portfolio of low cost, high margin projects. For more
information visit
gogoldresources.com
.
CAUTIONARY STATEMENT:
The securities described herein have not been, and will not be, registered under the United States Securities Act of 1933, as amended (the "U.S.
Securities Act"), or any state securities laws, and may not be offered or sold within
the United States
or to, or for the benefit of, U.S. persons (as defined
in Regulation S under the U.S. Securities Act) except in compliance with the registration requirements of the U.S. Securities Act and applicable state
securities laws or pursuant to exemptions therefrom. This release does not constitute an offer to sell or a solicitation of an offer to buy of any of GoGold's
securities in
the United States
.
This news release may contain "forward-looking information" as defined in applicable Canadian securities legislation. All statements other than statements
of historical fact, included in this release, including, without limitation, statements regarding the Parral tailings project, the Los Ricos project, future
operating margins, future production and processing, and future plans and objectives of GoGold, constitute forward looking information that involve various
risks and uncertainties. Forward-looking information is based on a number of factors and assumptions which have been used to develop such information
but which may prove to be incorrect, including, but not limited to, assumptions in connection with the continuance of GoGold and its subsidiaries as a going
concern, general economic and market conditions, mineral prices, the accuracy of mineral resource estimates, and the performance of the Parral project
There can be no assurance that such information will prove to be accurate and actual results and future events could differ materially from those
anticipated in such forward-looking information.
Important factors that could cause actual results to differ materially from GoGold's expectations include exploration and development risks associated with
the GoGold's projects, the failure to establish estimated mineral resources or mineral reserves, volatility of commodity prices, variations of recovery rates,
and global economic conditions. For additional information with respect to risk factors applicable to GoGold, reference should be made to GoGold's
continuous disclosure materials filed from time to time with securities regulators, including, but not limited to, GoGold's Annual Information Form. The
forward-looking information contained in this release is made as of the date of this release.
View original content to download multimedia:
https://www.prnewswire.com/news-releases/gogold-provides-outlook-for-2024-parral-production-and-update-on-zinc-circuit-commissioning-302030998.html
SOURCE
GoGold Resources Inc.
View original content to download multimedia:
http://www.newswire.ca/en/releases/archive/January2024/10/c6068.html
%SEDAR: 00029249E
For further information:
please contact: Steve Low, Corporate Development, GoGold Resources Inc., T: 416 855 0435, Email :
[email protected] Or visit : www.gogoldresources.com
CO: GoGold Resources Inc.
CNW 07:00e 10-JAN-24