GoGold Announces Filing of Los Ricos South Feasibility Study Technical Report
GoGold Announces Filing of Los Ricos South
Feasibility Study Technical Report
Halifax, Nova Scotia--(Newsfile Corp. - February 28, 2025) -
GoGold Resources Inc. (TSX: GGD)
(OTCQX: GLGDF) ("GoGold", "the Company")
is pleased to announce the filing of a National
Instrument 43-101 Feasibility Study ("FS") Technical Report ("the Report") at its Los Ricos South
("LRS") Project located in Jalisco State, Mexico.
The FS includes a re-engineered 2,000 tonne per day
underground mine plan compared to the Preliminary Economic Assessment ("PEA") which was
released in September 2023 and incorporates an updated Mineral Resource Estimate ("MRE").
The
Report is available on SEDAR+ and at
www.gogoldresources.com
.
Highlights of the FS, with a silver price of US$26.80/oz, gold price of US$2,330/oz and copper price of
US$4.00/lb ("Base Case") are as follows (all figures in US dollars unless otherwise stated):
After-Tax net present value ("NPV") (using a discount rate of 5%) of US$355 million with an After-
Tax IRR of 28% (Base Case);
At approximate spot metal silver price of $30/oz and gold price of $2,608/oz, NPV (using a
discount rate of 5%) of US$469 million with an After-Tax IRR of 34%;
15-year mine life producing a total of 80 million payable silver equivalent ounces ("AgEq"),
consisting of 41 million silver ounces, 424 thousand gold ounces, and 11 million pounds of copper;
Initial capital costs of $227 million, including $21 million in contingency costs, over an expected two
year build, and sustaining capital costs of $100 million over the life of mine ("LOM");
Average operating cash costs of $9.94/oz AgEq, and all in sustaining costs ("AISC") of $11.19/oz
AgEq over first 5 years of production, with average AISC of $12.32/oz AgEq over the underground
mine life;
Average annual production of 7.3 million AgEq oz over first 5 years;
Successful conversion of Mineral Resources to Proven and Probable Mineral Reserves totalling
10.2 million tonnes grading 276 g/t AgEq containing 91 million ounces AgEq, including 7.5 million
underground tonnes grading 326 g/t AgEq;
Average underground mining width of 11 metres using bulk mining method of longitudinal sub-level
long-hole mining;
"With the filing of this highly detailed feasibility study, it highlights all the great work our technical team
has completed over the last 6 years starting with the initial discovery building to a very large silver-gold
resource. Now the Company finds itself in the position once our permit is in hand, to build our first mine
in the Los Ricos district.
This will be potentially followed by our second mine in Los Ricos North," said
Brad Langille, President and CEO.
"We also look forward to exploring more of the exciting exploration
potential in the district and the opportunity for future growth and prosperity for all stakeholders in the Los
Ricos projects."
Table 1 - LRS FS Underground Key Assumptions and Results
Assumption / Result
Unit
Value
Assumption / Result
Unit
Value
Total UG Ore Mined
kt
7,512
UG Mining Costs
$/t Plant Feed
44.04
UG Silver Grade
1
g/t
170
Operating Cash Cost
$/oz AgEq
11.22
UG Gold Grade
1
g/t
1.65
All in Sustaining Cost
$/oz AgEq
12.32
UG AgEq Grade
1
g/t
326
Mine Life
Yrs
12
Silver Recovery
%
86
Average Mining Width
m
11
Gold Recovery
%
93
1. Grades shown are LOM average process plant feed grades including underground external dilution of approximately 18%.
2. The underground mining method is longitudinal sub-level long-hole mining.
3. AgEq includes gold converted at a ratio of 86.05:1 and copper % converted at a ratio of 103.4:1.
Table 2 - LRS FS Life of Mine Key Assumptions and Results
Assumption / Result
Unit
Value
Assumption / Result
Unit
Value
Total Plant Feed Mined
kt
10,233
Net Revenue
$M
2,099
Average process rate
t/day
2,000
Initial Capital Costs
$M
227
Silver Recovery
%
86
Sustaining Capital Costs
$M
100
Gold Recovery
%
93
Mining Costs
$/t Plant Feed
42.92
Silver Price
$/oz
26.80
Processing Costs
$/t Plant Feed
39.63
Gold Price
$/oz
2,330
General and Admin Costs
$/t Plant Feed
6.88
Copper Price
$/lb
4.00
Operating Cash Cost
$/oz AgEq
11.59
Payable Silver Metal
Moz
41.1
All in Sustaining Cost
$/oz AgEq
12.78
Payable Gold Metal
koz
423.6
After-Tax NPV (5% discount)
$M
355
Payable Copper
Mlb
11.2
Pre-Tax NPV (5% discount)
$M
553
Payable AgEq
1
Moz
79.9
After-Tax IRR
%
28.0
Mine Life
Yrs
15
Pre-Tax IRR
%
38.6
After-Tax Payback Period
Yrs
2.6
Figure 1 - LRS Cash Flow Profile by Year
To view an enhanced version of this graphic, please visit:
https://images.newsfilecorp.com/files/1683/242890_240c68d65466aaa7_001full.jpg
Figure 1 above highlights the excellent post-tax cash flows associated with the LRS Project.
The
economics of the Project have been evaluated based on the base case scenario $26.80/oz silver price,
gold price of $2,330/oz and copper price of $4.00/lb.
As illustrated in the following sensitivity tables, the
Project remains robust even at lower commodity prices or with higher costs.
Figure 2 - LRS Process Plant Grade and Feed Tonnes Mined by Source
To view an enhanced version of this graphic, please visit:
https://images.newsfilecorp.com/files/1683/242890_240c68d65466aaa7_002full.jpg
The Project mine plan is primarily underground, with a 12 year underground mine life engineered,
followed by an open pit mine which begins in the 10
th
year.
Figure 3 - LRS Annual Production (AgEq oz ore feed) and AISC ($/oz AgEq) by Year
To view an enhanced version of this graphic, please visit:
https://images.newsfilecorp.com/files/1683/242890_240c68d65466aaa7_003full.jpg
Table 3 - LRS FS Gold and Silver Price Sensitivities
Sensitivity
Base
Case
Silver Price ($/oz)
20
22
24
26.80
30
33
36
Gold Price ($/oz)
1,739
1,913
2,087
2,330
2,608
2,869
3,130
After-Tax NPV (5%) ($M)
110
184
255
355
469
575
681
After-Tax IRR (%)
13.6
18.3
22.5
28.0
33.7
38.8
43.7
After-Tax Payback (years)
4.7
3.8
3.2
2.6
2.0
1.8
1.7
Table 4 - LRS FS Operating Cost and Capital Cost Sensitivities
Sensitivity
-20%
-10%
Base
Case
10%
20%
Operating Costs - NPV ($M)
440
399
355
317
275
Operating Costs - IRR (%)
32.6
30.6
28.0
26.3
24.1
Capital Costs - NPV ($M)
394
373
355
331
310
Capital Costs - IRR (%)
35.1
30.9
28.0
24.5
22.0
FS Summary
The LRS Project has been envisioned as an underground mining operation for the first ten years, with
contract underground mining supplying a 2,000 tonne per day process plant.
The FS was prepared by independent consultants P&E Mining Consultants Inc ("P&E") acting as lead
consultant and completing the MRE, Mineral Reserves, and mining.
Additional contributing consultants
and their roles were as follows:
Ausenco - Process plant & infrastructure
SGS Canada Inc.'s Lakefield office - Metallurgical
WSP - Underground and Open Pit Geotechnical
CIMA - Environmental
Paterson & Cooke - Paste backfill
BQE / D.E.N.M. Engineering - SART design & costing
BCG - Tailings geotechnical
Table 5 - LOM Capital Cost Estimate
Type
Initial
($k)
Sustaining
($k)
Total
($k)
Process Plant direct costs
83,544
10,223
93,767
Underground development
51,054
62,763
113,817
Open pit stripping
17,661
17,661
Infrastructure
38,558
38,558
EPCM
17,969
17,969
Project indirect costs
14,576
14,576
Total
205,701
90,647
296,348
Contingency (10%)
20,987
9,065
30,052
Grand Total
226,688
99,712
326,400
Table 6 - Operating Costs (Average LOM)
Operating Costs (Average LOM)
$/tonne
Plant Feed
$/tonne
Mined
Open Pit Mining
17.72
2.64
Underground Mining
1
49.92
Total LOM Mining
2
42.92
Processing ($/t processed)
39.63
General and Admin ($/t processed)
6.88
Total ($/t processed)
89.43
1. Bulk underground long hole mining.
$44.04 is the mining cost, $5.88 is cemented paste backfill, and additional development costs of $8.35/t
mined are included in sustaining capital in table 6, providing a total UG mining cost of $58.27/t.
2. Average LOM mining cost of both open pit and underground.
Mining
Contract underground mining will be completed using the longitudinal sub-level long-hole mining method
and cemented paste back filling of the mined-out stopes. Approximately 10% of the underground ore will
be sourced in close proximity to historical workings.
Figure 4 - Underground Mine Plan by Year
To view an enhanced version of this graphic, please visit:
https://images.newsfilecorp.com/files/1683/242890_240c68d65466aaa7_004full.jpg
Process Plant Design
The process plant is comprised of conventional crushing and grinding followed by cyanide tank leaching.
Back-end filtration is required to maximize water recycling (dry stack tailings) as well as a SART
(sulfidation, acidification re-neutralization and thickening) circuit to recover cyanide back to the process
and to produce a saleable copper sulfide product.
The process plant will produce saleable silver-gold
doré bars and a copper precipitate.
Figure 5 - Process Plant Design
To view an enhanced version of this graphic, please visit:
https://images.newsfilecorp.com/files/1683/242890_240c68d65466aaa7_005full.jpg
Figure 6 - Mill Process Flow Sheet
To view an enhanced version of this graphic, please visit:
https://images.newsfilecorp.com/files/1683/242890_240c68d65466aaa7_006full.jpg
Metallurgy
In support of the feasibility study on the Los Ricos South deposits, an extensive metallurgical test
program was completed at SGS Lakefield on representative drill core from the deposit. The program
was designed to test and validate the key components of the process to confirm process plant
performance including:
Crushing and grinding
Thickening and filtration
Cyanide leaching and reagent consumptions
SART performance
Merrill Crowe (zinc precipitation)
Dry-stack tailings detoxification and dewatering (maximizing water recovery)
Based on the extensive program, and life of mine mill simulation, the process plant will use a
conventional whole ore leaching process and simple flow sheet to produce silver-gold doré bars and a
copper precipitate. The cyanide leaching process recoveries range from 92 to 93% for gold and 85 to
87% for silver. Approximately 70% of the copper was also leached.
Dewatered and detoxified tailings were tested at Paterson and Cook in Sudbury, Ontario to determine
the paste backfill cement addition rate for the underground mine and to minimize process water usage.
The advantages of using underground paste backfill include maximized stability of the mine and the
ability to store a majority of the process plant tailings as cemented paste underground, reducing surface
impact.
Infrastructure
The Company has an agreement in place with the Comision Federal de Electricidad ("CFE"), which has
secured an adequate power supply for LRS.
Electricity for the Project is sourced from the nearby La
Yesca hydroelectric dam.
Figure 7 - La Yesca Hydroelectric Dam
To view an enhanced version of this graphic, please visit:
https://images.newsfilecorp.com/files/1683/242890_240c68d65466aaa7_007full.jpg
The Company has also secured the rights to the land where the process plant will be located.
Agreements were entered into with multiple farmers and stakeholders providing compensation for the
usage of the required land.
Agreements are also in place with the local Ejido which owns the surface
rights over all of those concessions included in this FS.
Mineral Reserves and Mineral Resource Estimate
The basis for the FS is an inaugural Proven and Probable Mineral Reserve estimate totalling 10.2 million
tonnes grading 276 g/t AgEq (145 g/t Ag, 1.39 g/t Au, and 0.10% Cu) containing 90.7 million ounces
AgEq (47.8 Moz Ag, 457 Koz Au, 23.8 Mlb Cu), reflecting the successful conversion of Mineral
Resources.
A summary of the Mineral Reserves is provided in Table 7 and an updated Mineral
Resource Estimate is provided in Table 8.
Table 7: Los Ricos South Mineral Reserve
(1-8)
Classification
Tonnage
Average Grade
Contained Metal
Ag
Au
Cu
AgEq
Ag
Au
Cu
AgEq
(kt)
(g/t)
(g/t)
(%)
(g/t)
(koz)
(koz)
(Mlb)
(koz)
Underground
Proven
3,902
187
1.61
0.09
334
23,472
202
7.5
41,939
Probable
3,611
152
1.70
0.18
318
17,647
197
14.6
36,895
Subtotal Underground
7,512
170
1.65
0.13
326
41,119
399
22.1
78,834
Open Pit
Proven
580
95
0.72
0.02
159
1,768
13
0.3
2,965
Probable
2,140
72
0.64
0.03
130
4,961
44
1.4
8,924
Subtotal Open Pit
2,720
77
0.66
0.02
136
6,728
57
1.7
11,889
Total
Proven
4,482
175
1.49
0.08
312
25,240
215
7.7
44,904
Probable
5,751
122
1.31
0.13
248
22,607
241
16.1
45,819
Total Proven & Probable
10,233
145
1.39
0.10
276
47,847
457
23.8
90,723
1)
Mineral Reserves are based on Measured and Indicated Mineral Resource Classifications only.
2)
Mineral Reserves are reported using the 2014 CIM Definition Standards and 2019 Best Practices Guidelines and have an effective date of
January 14, 2025.
3)
Mineral Reserves are defined within mine plans and incorporate mining dilution and ore losses.
4)
Open Pit Mineral Reserves are based on metal prices of $23.75/oz Ag, $1,850/oz Au and $4.00/lb Cu, and are constrained within optimized pit
shells and designs that use 45-48º overall wall slopes, and process recoveries of 86% Ag, 95% Au and 51% Cu.
5)
An Open Pit cut-off grade of 46.4 g/t AgEq is estimated to differentiate ore from waste and is based on cost assumptions of $26.22/t
processing, $4.11/t site general and administrative, and 0.5% government mining tax on net revenue. Mining costs are estimated at $2.10/t of ore
and waste rock.
6)
Underground Mineral Reserves are based on metal prices of $23.75/oz Ag, $1,850/oz Au and $4.00/lb Cu, and are constrained within a mine
design, and use process plant recoveries of 86% Ag, 95% Au and 77% Cu.
7)
An Underground marginal cut-off grade of 150 g/t AgEq is estimated to differentiate ore from waste, and is based on cost assumptions of
$34.93/t processing, $4.46/t site general and administrative, and mining costs of $41.93/t. An Underground economic cut-off grade of 210 g/t
AgEq is estimated to account for capital development costs of $53.86/t in addition to those used to calculate the marginal cut-off grade.
8)
Totals may not sum due to rounding.
Table 8: Los Ricos South Mineral Resource Estimate - Pit Constrained and Out-of-Pit
(1-9)
Mining
Method
Category
Tonnes
Average Grade
Contained Metal
Ag
Au
Cu
AuEq
AgEq
Ag
Au
Cu
AuEq
AgEq
(M)
(g/t)
(g/t)
(%)
(g/t)
(g/t)
(koz)
(koz)
(Mlb)
(koz)
(koz)
Pit
Constrained
5
Measured
2.9
150
1.13
0.03
2.96
250
14,065
106
1.7
278
23,446
Indicated
2.0
107
0.74
0.03
2.07
174
6,747
47
1.4
130
10,974
M&I
4.9
133
0.97
0.03
2.60
219
20,812
153
3.1
408
34,420
Inferred
0.7
108
0.66
0.03
2.00
168
2,552
16
0.5
47
3,979
Pit - Cerro
C
6
Inferred
0.6
43
0.90
0.01
1.43
121
787
17
0.1
26
2,243
Indicated
0.3
34
0.87
0.01
1.28
109
377
10
0.1
14
1,217
Out-of-Pit
7,8
Measured
2.4
218
2.00
0.14
4.79
405
17,025
156
7.5
373
31,567
Indicated
3.1
187
2.25
0.26
4.80
407
18,525
223
17.4
476
40,331
M&I
5.5
201
2.14
0.20
4.79
406
35,550
379
24.9
849
71,898
Inferred
1.1
127
1.48
0.51
3.61
306
4,544
53
12.4
130
10,995
Total
Measured
5.3
181
1.53
0.08
3.79
320
31,090
262
9.2
651
55,013
Indicated
5.6
144
1.59
0.15
3.50
296
26,059
287
18.9
632
53,549
M&I
11.0
162
1.56
0.12
3.64
308
57,150
549
28.1
1,284
108,562
Inferred
2.2
106
1.11
0.27
2.70
229
7,473
79
13.0
191
16,191
1)
Mineral Resources, which are not Mineral Reserves, do not have demonstrated economic viability. The estimate of Mineral Resources may be
materially affected by environmental, permitting, legal, title, taxation, socio-political, marketing, or other relevant issues.
2)
The Inferred Mineral Resource in this estimate has a lower level of confidence than that applied to an Indicated Mineral Resource and must not
be converted to a Mineral Reserve. It is reasonably expected that the majority of the Inferred Mineral Resource could be upgraded to an Indicated
Mineral Resource with continued exploration.
3)
The Mineral Resources were estimated in accordance with the Canadian Institute of Mining, Metallurgy and Petroleum (CIM), CIM Standards on
Mineral Resources and Reserves, Definitions and Guidelines (2014) prepared by the CIM Standing Committee on Reserve Definitions and
adopted by the CIM Council and CIM Best Practices Guidelines (2019) and have an effective date of January 14, 2025.
4)
Historically mined areas were depleted from the Mineral Resource model.
5)
The pit-constrained AgEq cut-off grade of 40 g/t was derived from $1,850/oz Au price, $23.75/oz Ag price, 86% Ag and 95% Au process
recovery, $28/tonne process and G&A cost. The constraining pit optimization parameters were $2.10/t mineralized material and waste mining
cost, and 45-degree pit slopes.
6)
The Cerro Colorado Mineral Resource was constrained to open pit mining methods only; Out-of-pit Mineral Resources are restricted to the
Eagle and Abra mineralized veins, which exhibit historical continuity and reasonable potential for extraction by cut and fill and longhole
underground mining methods.
7)
The out-of-pit AgEq cut-off grade of 130 g/t Ag was derived from $1,850/oz Au price, $23.75/oz Ag price, 86% Ag and 95% Au process
plant recovery, $30/tonne process and G&A cost, and a $60/tonne mining cost. The out-of-pit Mineral Resource grade blocks were quantified
above a 130 g/t AgEq cut-off, below the constraining pit shell and within the constraining mineralized wireframes. Out-of-Pit Mineral Resources
are restricted to the Eagle and Abra Veins, which exhibit historical continuity and reasonable potential for extraction by cut and fill and longhole
mining methods.
8)
AgEq and AuEq were calculated at an Ag/Au ratio of 86:1 for pit-constrained and out-of-pit Mineral Resources.
9)
Totals may not sum due to rounding.