Generation Mining Updates ON Metallurgical Test Programs and Initiates a Pilot Plant

Metallurgy & Processing

GENERATION MINING UPDATES ON 

METALLURGICAL TEST PROGRAMS AND 

INITIATES A PILOT PLANT 

Toronto, Ontario – October 22, 2020 – Generation Mining Limited (TSX: GENM) (OTCQB: 

GENMF) (“Gen Mining” or the “Company”) is pleased to provide an update on the continued 

progress of the Feasibility Study currently underway for the Marathon Palladium project in 

northwestern Ontario (the “Marathon Project”). 

The Company previously reported on the Phase 1 bench‐scale metallurgical testing program 

(news release dated August 20, 2020) that determined the recovery to be used for the Feasibility 

Study and the expected recoveries for the Project going forward.  The Phase 1 Metallurgical 

Testing program achieved the following results: 

2020 Phase 1 Metallurgical Recovery 1 

(as determined by 2020 Met Testing) 

PEA2 Metallurgical 

Recovery 

Variance 

+ positive  

         ‐ negative 

Palladium 

(Pd) 

86.9%  82.9%  +4.0% 

Copper3  

(Cu) 

93.0%  90.0%3  +3.0% 

Platinum 

(Pt) 

84.2%  74.5%  +9.7% 

Gold  

(Au) 

72.4%  73.2% ‐ 0.8% 

Silver  

(Ag) 

Not evaluated in this program  71.5%  n/a 

1 Recovery calculations are based on the established head grade of composite samples ranging in Cu, Pd, Pt, 

and Au head grade and involving multiple benchscale flotation tests.   

2 Preliminary Economic Assessment (“PEA”) of the Company titled “Amended Technical Report, Updated 

Mineral Resource Estimate and Preliminary Economic Assessment of the Marathon Deposit, Thunder Bay 

Mining District Northwestern Ontario Canada” dated July 6, 2020 (effective date of January 6, 2020);  

3 The estimated recovery of Cu is noted per the PEA for years 6‐14  

In September 2020, the Company progressed to a Phase 2 metallurgical testing program, again 

at SGS Canada Inc. in Lakefield, Ontario.  The Phase 2 Metallurgical Testing program is being 

overseen by Steve Haggarty, P.Eng., of Haggarty Technical Services (“HTS”) and Ausenco 

Engineering Canada Inc. (“Ausenco”) (acting as the Qualified Person for the upcoming 

metallurgical and processing sections of the Feasibility Study Technical Report).  The goal of this 

program is to further define (i) the performance of the cleaning and scavenger flotation circuits, 

(ii) the optimal grind size in the regrind circuit and (iii) the overall validation of the circuit 

performance with a mini‐pilot plant.  The first two tasks have been completed.  The initial 

locked cycle testing and a pilot plant program commenced mid‐October and will be completed 

during November 2020. 

The Phase 2 metallurgical and the pilot plant will involve three bulk sample composites with 

varying Palladium (Pd) and Copper (Cu) content from freshly excavated material in the Main 

Zone, W‐Horizon, and a composite previous collected in 2012.  The range in grade and material 

types will allow the Company to optimize process design criteria and Pd‐Cu recovery, while 

advancing predictive Geo‐Met modeling to estimate Life of Mine plan metal recoveries from 

the deposit.

The progress that has been realized on Phase 1 and Phase 2 testing to date: 

1. Optimized initial grind size and applied flotation reagents to maximize platinum group 

metals (PGM) and Cu recovery to rougher concentrate; 

2. Optimized rougher concentrate regrind size and cleaner circuit performance to 

maximize PGM‐Cu capture to final concentrate; 

3. Confirmed the applicability of magnetic separation for pyrrhotite mineralization 

associated with the Marathon Palladium project to provide NSR optionality for separate 

PGM‐Cu and iron sulfide‐PGM‐Cu concentrates; 

4. Confirmed the applicability of a cycloned coarse/fine fraction of rougher tailings that 

would be subject to additional regrinding to provide incremental PGM recovery for the 

project; 

5. Validated the performance of Woodgrove Direct Flotation Reactor (DFR) technology 

which would provide similar or improved PGM‐Cu recovery at higher concentration 

ratios (lower mass pull); 

6. Implementation of DFR technology will decrease the footprint associated with the 

flotation portion of the processing plant; a smaller footprint will reduce the capital cost 

associated with the construction and is expected to decrease the plant operating costs 

and carbon footprint through reduced energy consumption; 

7. Confirmed that the alternate flowsheet (Figure 1) for plant design has improved 

performance and operability over previously defined process concepts from the 2020 

PEA (Technical Report 6 July 2020). 

“We believe that the processing plant flowsheet is an improvement over the past design and 

the metallurgical testing programs have shown improved recoveries.   The achieved successes 

and the validation of the flowsheet will be carried forward in Feasibility Study designs and into 

the subsequent detailed engineering phase.  We see the achieved recoveries and overall design 

to be very positive for the overall Project”, stated Drew Anwyll, Chief Operating Officer, 

Generation Mining. 

Figure 1 below is the processing plant flowsheet for the Marathon Project. 

Figure 1: Processing Plant Flowsheet being used in the Feasibility Study   

https://genmining.com/site/assets/files/3765/marathon_palladium_project_simplified_flowsheet.pdf

https://genmining.com/site/assets/files/3765/marathon_pgm_flotation_circuit_revd.pdf

The Phase 2 pilot plant testing will be completed during Q4, 2020 and is expected to fully 

validate the flowsheet, process design criteria, and confirm expectations for final concentrate 

grade and quality.  The pilot plant test program (as a key component of Phase 2 Metallurgical 

test program) is not a requirement of NI43‐101 and is being progressed to allow for improved 

clarity for the concentrate marketing and to proactively progress the future detailed 

engineering. 

About the Company 

Gen Mining’s focus is the development of the Marathon Palladium Project, the largest 

undeveloped platinum group metal Mineral Resource in North America. The Marathon 

property covers a land package of approximately 22,000 hectares, or 220 square kilometres.  

Gen Mining acquired a 51% interest in the Marathon Project from Sibanye Stillwater on July 10, 

2019 and can increase its interest to 80% by spending $10 million over a period of four years.  

The 80% ownership is expected to be realized later in Q4 2020.  As at the end of Q3 2020, 

approximately $8.7 million of the $10 million has been spent.  Sibanye Stillwater has certain 

back‐in rights that allow it to increase its interest in the Marathon Project back up to 51% in 

certain circumstances and subject to certain conditions after such time as Gen Mining has 

earned its 80% interest (see the Company’s press release of July 11, 2019 for more details). 

Qualified Person 

The scientific and technical content of this news release was reviewed, verified and approved 

by Drew Anwyll, P.Eng., M.Eng, Chief Operating Officer of the Company, and a Qualified Person 

as defined by Canadian Securities Administrators National Instrument 43‐101 “Standards of 

Disclosure for Mineral Projects.” 

For further information please contact:

Jamie Levy

President and Chief Executive

Officer

(416) 640-2934

(416) 567-2440

[email protected]

Forward-Looking Information

This news release includes certain information that may be deemed “forward‐looking information” under 

applicable securities laws. All statements in this release, other than statements of historical facts, that 

address  the ability of the Company and Sibanye Stillwater to vary their respective participating interests 

in the Marathon Project, Mineral Resource and Reserve potential, exploration activities and events or 

developments that the Company expects are forward‐looking information. Although the Company 

believes that the expectations expressed in such statements are based on reasonable assumptions, such 

statements are not guarantees of future performance and actual results or developments may differ 

materially from those in the statements. There are certain factors that could cause actual results to differ 

materially from those in the forward‐looking information. These include, among other factors, market 

prices, exploration and development successes, continued availability of capital and financing, and 

general economic, market or business conditions. 

Investors are cautioned that any such statements are not guarantees of future performance and actual 

results or developments may differ materially from those projected in the forward‐looking information. 

For more information on the Company, investors are encouraged to review the Company’s public filings 

at www.sedar.com. The Company disclaims any intention or obligation to update or revise any forward‐ 

looking information, whether as a result of new information, future events or otherwise, other than as 

required by law.