Saturday, September 26, 2026
MiningNewsTerminal
Saturday, September 26, 2026 Admin

GENM.TO ·

Generation Mining Delivers Updated Feasibility Study for Canada’s Next Critical Mineral Mine - the Marathon Palladium-Copper Project After-Tax NPV6% $1.16 Billion, IRR of 26%, Payback 2.3 years

Economic Studies

Generation Mining Delivers Updated Feasibility Study for Canada’s Next

Critical Mineral Mine - the Marathon Palladium-Copper Project

After-Tax NPV6% $1.16 Billion, IRR of 26%, Payback 2.3 years

TORONTO--(BUSINESS WIRE)--March 31, 2023--Generation Mining Limited (TSX: GENM;

OTCQB: GENMF) (“Gen Mining” or the “Company”) is pleased to announce positive results on

the updated Feasibility Study (“2023 FS” or the “Feasibility Study”) for the Marathon

Palladium-Copper Project (the “Project”) located near the Town of Marathon in Northwestern

Ontario. The 2023 FS presents an optimized design for the Project with improved clarity on

anticipated capital and operating costs in the current inflationary environment. The 2023 FS

outlines the operation of an open pit mine and process plant over a mine life of 12.5 years and

replaces the Company’s March 2021 Feasibility Study (the “2021 FS”).

All dollar amounts are in Canadian dollars unless otherwise stated. All references to Mlbs are to

millions of pounds and Moz are to millions of ounces and koz are to thousands of ounces.

Highlights:

 Robust economics1: An after-tax Net Present Value (“NPV”) at a 6% discount rate of

$1.16 billion and Internal Rate of Return (“IRR”) of 25.8% based on a long-term price of

US$1,800/oz for palladium and US$3.70/lb for copper

 Quick payback period on Initial Capital2,3: 2.3 years

 Initial Capital: $1,112 million ($898 million net of equipment financing and pre-

commercial production revenue), an increase of 25% from the 2021 FS

 Low Operating Costs and attractive AISC: Life of mine (“LOM”) average operating

costs of US$709/PdEq oz and all-in sustaining costs (“AISC”) of US$813/PdEq oz 3 .

Operating costs have increased 14% compared with the 2021 FS.

 Increased Mineral Reserve Estimate: an increase of 8.5% in Mineral Reserves

tonnages and a decreased open pit strip ratio

 Optimized operation: increased process plant throughput and improved metallurgical

recoveries over LOM

 Average annual payable metals: 166 koz palladium, 41 Mlbs copper, 38 koz platinum,

12 koz gold and 248 koz silver

 LOM payable metals: 2.1 Moz palladium, 517 Mlbs copper, 485 koz platinum, 158 koz

gold and 3.2 Moz silver

 Strong cash flows in first three years of production following commercial

production: $851 million of free cash flow 3 , 580 koz of payable palladium and 132

Mlbs of payable copper

 Jobs: Creation of over 800 jobs during construction jobs and over 400 direct permanent

jobs during operations

Jamie Levy, President and CEO of the Company, commented, “This updated Feasibility Study

underscores just how robust the Marathon Project is, even in the current inflationary

environment. This, combined with strong demand for critical minerals, makes the rationale for

the Project becoming Canada’s next critical minerals mine more compelling than ever before.

With the receipt of our Environmental Assessment approvals and our recently announced

indicative offtake term sheets, we are advancing to arrange Project financing and working hard

to obtain the permits necessary to start construction. The Project promises to be a near-term

sustainable, environmentally sensitive, low-cost producer of critical metals that Canada and the

rest of the world desperately need. On a copper equivalent basis, the Marathon Project, once in

production, is expected to be one of the lowest CO2 equivalent intensity mines in the world. The

metals we plan to produce will not only support emissions controls and the transition to a greener

economy in Ontario and Canada, but they will also support job creation and economic prosperity

for local, regional, and national stakeholders, in particular the First Nation community of

Biigtigong Nishnaabeg and the Town of Marathon.”

Following the 2021 Feasibility Study, the Company undertook considerable work to optimize

and de-risk the Project, including:

 Detailed engineering on the process plant, Tailing Storage Facility (“TSF”), and site

infrastructure designs.

 Additional metallurgical test program to optimize the flowsheet and plant design and

improve confidence in metallurgical recoveries. Results allowed the Company to remove

the PGM-Scavenger circuit from the process plant design and lower the process plant

unit-operating costs.

 Geotechnical investigations completed in areas of key infrastructure location and

confirmed the locations chosen in the construction design.

 Additional diamond drilling of 18,995 m within the Marathon Deposit targeting key areas

within the open pit Mineral Reserves in the first three years of planned production, and

areas within and proximal to the overall Mineral Resources.

 Agreement finalized with Hycroft Mining Holding Corporation (“Hycroft”) for the

purchase of an unused, surplus SAG mill and an unused, surplus ball mill4, which

together with ancillary equipment allows the Company to increase throughput by 10% in

the second full year of production.

 Community Benefits Agreement (“CBA”) signed and ratified with the Biigtigong

Nishnaabeg (“BN”), on November 12, 2022.

 Federal and Provincial Environmental Assessment approvals received on November 30,

2022.

 Initiated the process of obtaining various federal and provincial permits and approvals

required to construct and operate the project.

Drew Anwyll, P.Eng, Chief Operating Officer, said, “Our team has been working hard to

develop the Marathon Project and has successfully optimized and improved confidence in the

designs of the process plant, the open pits and the necessary infrastructure for the Project.

Detailed design will advance, and we will continue to de-risk the Project in anticipation of

finalizing the Project financing and receiving approval of the required permits to commence

construction later in 2023.”

Upcoming Webinar:

For more information on the updated Feasibility Study please join Jamie Levy, President, Chief

Executive Officer and Director, Kerry Knoll, Chairman and Director, and Drew Anwyll, Chief

Operating Officer for a live event on Monday, April 3, 2023 at 10 am ET / 7 am PT. An

opportunity to ask questions will follow the presentation. Click here to register:

https://my.6ix.com/n9qfF5Nz

The Feasibility Study was prepared by the Company and G Mining Services Inc. (“GMS”), along

with contributions from Wood Canada Limited, Knight Piésold Ltd., P&E Mining Consultants

Inc. (“P&E”), and JDS Energy and Mining, Inc., and with support from LQ Consulting and

Management Inc. and Haggarty Technical Services. The effective date of the Feasibility Study is

December 31, 2022.

KEY RESULTS AND ASSUMPTIONS IN UPDATED FEASIBILITY STUDY

Key results and assumptions for the updated Feasibility Study are summarized below.

Units 2023 FS 2021 FS

Production Data

Mine Life (operating) years 12.5 12.8

Average Process Plant Throughput tpd 27,700 25,200

Average Process Plant Throughput Mt/ year 10.1 9.2

Average Mining Rate tpd 115,000 110,000

Average Mining Rate Mt/ year 42 40

Total Ore Mined Mt 127 118

Strip Ratio waste:ore 2.63 2.80

Palladium (payable) k oz 2,122 1,905

Copper (payable) M lbs 517 467

Platinum (payable) k oz 485 537

Gold (payable) k oz 158 151

Silver (payable) k oz 3,156 2,823

LOM Palladium Equivalent Payable PdEq. koz 3,613 3,195

Average Annual Palladium – Payable Metal k oz 166 149

Average Annual Copper – Payable Metal M lbs 41 36

Average Annual Platinum – Payable Metal k oz 38 41

Average Annual Gold – Payable Metal k oz 12 12

Average Annual Silver – Payable Metal k oz 248 220

Operating Costs (Average LOM)

Mininga $/t mined 3.25 2.53

Mining $/t milled 11.45 9.23

Processing $/t milled 8.70 9.08

G&Ab $/t milled 2.67 2.48

Transport & Refining Charges $/t milled 4.13 2.80

Royalty $/t milled 0.09 0.04

Total Operating Cost $/t milled 27.04 23.63

LOM Average Operating Costs US$/oz PdEq 709 687

LOM Average AISCc US$/oz PdEq 813 809

Capital Costs

Initial Capital $M 1,112 888

Less:

Pre-commercial production revenue $M ($156) ($171)

Leased equipment, net of lease payments during construction $M ($58) ($53)

Initial Capital (Adjusted) $M 898 665

LOM Sustaining Capital $M 424 423

Closure Costs $M 72 66

Financial Evaluation

Pre-Tax Cash Flow (undiscounted) $M 3,387 3,004

Pre-Tax NPV6% $M 1,798 1,636

Pre-Tax IRR % 31.9 38.6

Payback years 2.0 1.9

Net Cash Flow (undiscounted) $M 2,285 2,060

After-Tax NPV6% $M 1,164 1,068

After-Tax IRR % 25.8 29.7

Payback years 2.3 2.3

Key Assumptionsd

Palladium Price US$/oz $1,800 $1,725

Copper Price US$/lb $3.70 $3.20

Platinum Price US$/oz $1,000 $1,000

Gold Price US$/oz $1,800 $1,400

Silver Price US$/oz $22.50 $20.00

Foreign Exchange (“FX”) C$:US$ 1.35 1.28

Diesel Price $/litre 1.17 0.77

Electricity $/kWhr 0.07 0.08

Notes:

a Including capitalized maintenance parts.

b Includes estimated costs associated with certain commitments to and agreements with Indigenous communities.

c AISC is calculated without the impact of the Precious Metal Purchase Agreement with Wheaton Precious Metals

Corp. (“WPM PMPA”).

d Metal Price Assumptions are based on the lesser of the three-year trailing average and the spot price on December

31, 2022, rounded to nearest interval.

LOM Metal Production Recovered Metal Payable Metal Revenue %a

Palladium 2,266 koz 2,122 koz 58

Copper 548 Mlbs 517 Mlbs 29

Platinum 607 koz 485 koz 7

Gold 204 koz 158 koz 4

Silver 4,529 koz 3,156 koz 1

Notes:

a Excludes the impact of the WPM PMPA on gold and platinum revenues.

Mining

The Company will mine using conventional open pit, truck and shovel operating methods. Three

open pits will be mined over the 12.5-year operating mine life, with an additional two years of

pre-production mining to be undertaken where waste material is being mined for construction

and ore stockpiling ahead of process plant commissioning. The mining equipment fleet is to be

owner-operated and will include outsourcing of certain support activities such as explosives

manufacturing and blasting. Production drilling and mining operations will take place on a 10 m

bench height. The primary loading equipment will consist of 660 tonne hydraulic face shovels

(29 m3 bucket size) and large front-end wheel loader (19 m3 bucket size). The loading fleet is

matched with a fleet of 246 tonne haulage trucks. A fleet of 90 and 45 tonne excavators will be

used to excavate the limited volume of overburden material and will also be allocated to mining

the narrow-thickness ore zones, mainly associated with the W-Horizon in the South Pit, to

mitigate additional dilution.

Peak mining production will be 43 Mt per year (118,000 tonnes per day (“t/d”)). Total material

moved over the LOM is expected to be 460 Mt of which 128 Mt is ore.

The Marathon Deposit is well defined and characterized by ore outcropping on surface, with

wide and moderately dipping mineralized zones.

The open pit operation includes a waste rock dump immediately to the east of the open pits and

an ore stockpile (peak capacity of approximately 10 Mt) to the west of the pits, proximal to the

crusher location.

Processing

The 2023 FS outlines the process plant throughput starting at 9.2 Mt per year (25,200 t/d) and

increasing to 10.1 Mt per year (27,700 t/d) following the completion of the powerline upgrade

scheduled year two of operations. The increase in process plant throughput is possible with the

inclusion of the Hycroft mills in the plant design. The process plant will produce a copper-

palladium concentrate (“Cu-PGM concentrate”).

The process plant flowsheet includes a conventional comminution circuit consisting of a SAG

mill, followed by a ball mill (an “SAB” circuit). With the added capacity of the Hycroft mills,

the pebble crusher (included in the 2021 FS) is no longer required. The flotation portion of the

process plant includes rougher flotation, concentrate regrind and three stages of cleaning.

The process plant metallurgical recovery (at the average head grade) is estimated at an average

of 88.0% palladium, 93.5% copper, 75.3% platinum, 71.5% gold and 66.4% silver. The phase 3

metallurgical test program demonstrated the PGM-Scavenger circuit outlined in the 2021 FS is

no longer required.

The flotation circuit design was revised to replace the Direct Flotation Reactors previously

included in the 2021 FS with conventional open tank cells for the roughers followed by

Woodgrove Staged Flotation Reactors™ for the cleaning circuit. Concentrate thickening,

concentrate filtering, tailings thickening, water management and a TSF complete the flowsheet.

Site Infrastructure

The existing regional infrastructure in the area of the Project is well established and will allow

for the efficient logistics associated with Project execution and operations, including the

movement of the Cu-PGM concentrate to a third-party off-site smelter.

All site infrastructure facilities, including the roads and access, process plant buildings,

workshops, warehouse, administrative buildings, water treatment plants, explosives plant,

communication systems, power and power transmission line required for the Project during

construction and operation have been considered in the Project design. Off-site infrastructure

(including transload concentrate facility, assay lab and accommodation units) required to support

the operation have also been included.

The TSF design includes downstream constructed embankments using run-of-mine waste rockfill

with embankments founded directly on bedrock. The majority of the TSF area consists of

exposed bedrock with a thin intermittent layer of sand and gravel. The upstream face of the

embankments includes an HDPE Geomembrane to minimize seepage. The construction

methodology includes bulk material placement with the mining fleet. Associated with the TSF

are separate water management facilities which will ensure the protection of the environment.

Between 2007 and 2022, there have been 10 geotechnical site investigation (“SI”) programs

completed. The SI programs have focused on TSF foundation conditions and location of key site

infrastructure, including the most recent drilling which focused on the process plant site, crusher,

mine rock storage area and water management structures foundations. The recent and historical

SI programs along with the 2021 detailed LiDAR™ topography and imagery survey have resulted

in a good understanding of the geotechnical conditions for the Project.

Capital and Operating Cost Summary

The Initial Capital cost considers a construction timeframe of approximately 24 months followed

by commissioning and ramp-up to commercial production5 over a period of approximately six

months. During the pre-commercial production, the costs and revenue associated with operations

will be capitalized and are included in the capital costs.

Construction Indirect costs and General and Owner’s costs are related to the expenses other than

direct equipment purchases and direct construction costs.

Sustaining Capital items include future equipment purchases and replacements for the mining

fleet and other site support equipment, the progressive build of the TSF over the LOM, and on

and off-site infrastructure development to support the growth and contribute to operational

improvements following initial construction.

The current capital cost estimate for the initial construction and the sustaining capital required

during the LOM are shown in the table below. As noted above, this estimate represents a 25%

($224 million) increase to the initial construction capex reported in the 2021 FS. Within this

increased capital cost, approximately 19% ($43 million) is due to scope changes, 71% ($160

million) is due to cost escalation and 10% ($22 million) with increased contingency.

Capital Costsa Initial ($M) Sustaining ($M) Total ($M)

Mining and Surface Equipment 117 130 247

Process Plant 345 3 348

Infrastructure 72 94 166

TSF, Water Management and Earthworks 95 198 293

General and Owner’s Costs 31 - 31

Construction Indirects 197 - 197

Pre-production, Start-up and Commissioning 159 - 159

Contingencyb 97 - 97

Sub-Total 1,112 424 1,537

Equipment Financing adjustment (58) - (58)

Pre-Production Revenue (156) - (156)

Total Capital (adjusted) 898 424 1,322

Notes:

a Sums in the table may not total due to rounding.

b Contingency included at project sub-category basis and totals approximately 9.5%.

Operating Costs and AISC (LOM) $ M US$/oz PdEq

Mining 1,432 300

Process Plant 1,087 228

General & Administration 334 70

Concentrate Transport Costs 230 48

Treatment & Refining Charges 286 60

Royalties 12 2

Total Operating Cost 3,381 709

Closure & Reclamation 72 15

Sustaining Capital 424 89

All-in Sustaining Cost (AISC) 3,878 813

Economic Analysis

The economic analysis is carried out in real terms (i.e., without inflation factors) in Q4 2022

Canadian Dollars without any project financing but inclusive of the WPM PMPA, and

anticipated financing of mobile equipment and closure bonding.

To provide a better understanding of the economic impact of the WPM PMPA to the overall

economics of the Project, the economic analysis is shown below including the economic impact

of the WPM PMPA (as required under the National Instrument 43-101 Standards of Disclosure

for Mineral Projects (“NI 43-101”) and excluding the economic impact of the WPM PMPA.

The economic analysis does not take into account any potential economic benefits which the

Marathon Project may qualify for under the new 30% investment tax credit on machinery and

equipment acquired to extract and process critical minerals which was announced by the

Government of Canada in its March 28, 2023 Federal Budget.

ECONOMIC ANALYSIS UNITS INCLUDING WPM

PMPA

EXCLUDING WPM PMPA

Pre-tax Undiscounted Cash Flow $M 3,387 3,780

Pre-tax NPV (6%) $M 1,798 1,979

Pre-tax IRR % 31.9 29.8

Pre-tax Payback years 2.0 2.3

After-tax Undiscounted Cash Flow $M 2,285 2,562

After-tax NPV (6%) $M 1,164 1,285

After-tax IRR % 25.8 24.2

After-tax Payback years 2.3 2.5

Sensitivities

The Project has significant leverage to palladium and copper prices. The after-tax valuation

sensitivities for the key metrics are shown below.

Palladium Price US$/oz 1,400 1,600 1,700 1,800 1,900 2,000 2,200

NPV6% ($M) 696 930 1,047 1,164 1,282 1,400 1,634

Payback (yrs) 3.3 2.9 2.5 2.3 2.2 2.0 1.9

IRR (%) 18.5 22.3 24.0 25.8 27.5 29.1 32.3

Copper Price US$/lb 2.50 3.00 3.50 3.70 3.90 4.50 5.00

NPV6% ($M) 836 972 1,109 1,164 1,219 1,386 1,522

Payback (yrs) 3.0 2.6 2.4 2.3 2.2 2.0 1.9

IRR (%) 21.1 23.1 25.0 25.8 26.5 28.7 30.4

After-Tax Results OPEX Sensitivity

+30% +15% 0% -15% -30%

NPV 6% ($M) 1,031 1,085 1,164 1,274 1,411

Payback (yrs) 2.7 2.5 2.3 2.1 2.0

IRR (%) 23.4 24.4 25.8 27.4 29.2

After-Tax Results CAPEX Sensitivity

+30% +15% 0% -15% -30%

NPV 6% ($M) 932 1,048 1,164 1,281 1,397

Payback (yrs) 3.3 3.0 2.3 1.9 1.3

IRR (%) 18.4 21.6 25.8 31.6 40.1

Discount Rate Sensitivity

(%)

NPV (After-Tax)

($M)

Foreign Exchange Rate

C$:US$

NPV (After-Tax) ($M)

0 2,285 1.25 928

5 1,303 1.30 1,046

6 1,164 1.35 1,164

8 925 1.40 1,284

10 731 1.45 1,403