Generation Mining Announces Feasibility Study Report Update for the Marathon Copper-Palladium Project
Generation Mining Announces Feasibility Study Report Update for the
Marathon Copper-Palladium Project
Highlights:
Robust Base Case economics1: An after-tax NPV6% of $1.07 billion, IRR of 28% and
1.9 year payback period based on the 3-yr trailing average metal prices at the
effective date2
Strong critical mineral production during pre-production and the first three years
of commercial operation: 151 Mlbs of payable copper, 720 koz of payable palladium
and 156 koz of platinum
Initial Capital: C$992 million3
Attractive AISC: Life of mine (“LOM”) all-in sustaining costs (“AISC”) of
US$2.05/CuEq lb or US$781/PdEq oz3
At recent long-term consensus prices2: An after-tax NPV6% of $876 million, IRR of
24% and 2.2 year payback period, with 41% of payable metal revenues attributable
to copper and 41% attributable to palladium
At recent spot prices2: An after-tax NPV6% of $749 million, IRR of 21% and 2.4 year
payback period, with 44% of payable metal revenues attributable to copper and
37% attributable to palladium.
Average annual payable metals: 42 Mlbs copper, 168 koz palladium, 38 koz
platinum, 12 koz gold and 240 koz silver over approximately 13 years of mine life
Jobs: Creation of over 800 jobs during construction and over 400 direct permanent
jobs during operations
The Next Critical Mineral, Shovel-Ready Project: Fully Permitted for Construction
federally and waiting for approval on last permit from the Government of Ontario.
TORONTO--(BUSINESS WIRE)--March 27, 2025--Generation Mining Limited (TSX: GENM;
OTCQB: GENMF) (“Gen Mining” or the “Company”) is pleased to announce positive results on
the updated Feasibility Study (“2025 FS” or the “Feasibility Study”) for the Marathon Copper-
Palladium Project (the “Project”) located near the Town of Marathon in Northwestern Ontario.
All dollar amounts are in Canadian dollars (“$” or “C$”) unless otherwise stated. All references
to “Mlbs” are to millions of pounds and “Moz” are to millions of troy ounces and “koz” are to
thousands of troy ounces.
The 2025 FS incorporates the results of the Project optimization work reported by the Company
in a news release entitled “Generation Completes Optimization Work for the Marathon Project
with Improved Mine Plan and Reduced Capex” issued on November 20, 2024, which focused on
two key aspects: 1) optimization of the mine plan to maximize metal production and defer waste
stripping in the early years of operations in order to improve early cash flows and reduce the
payback period (“Mine Plan Optimization”); and 2) optimization of the process plant design and
layout, including sizing of key equipment, plant footprint and foundations, in order to reduce the
initial Project capital costs (“Initial Capital Optimization”, and together with the Mine Plan
Optimization, the “Optimization Work”).
The Optimization Work has now been further updated to incorporate changes to Mineral
Resources, Mineral Reserves, the Life-of-Mine (LOM) mining plan and operating and capital
costs, using the same metal price assumptions which formed the basis of the November 20, 2024
news release.
The 2025 FS was prepared by Ausenco Engineering Canada ULC (“Ausenco”), along with
contributions from Moose Mountain Technical Services (“MMTS”), Knight Piésold Ltd. (“KP”),
P&E Mining Consultants Inc. (“P&E”), and JDS Energy and Mining, Inc (“JDS”).
The 2025 FS outlines the operation of an open pit mine and process plant over a mine life of 12.5
years and replaces the Company’s previous feasibility study entitled “Amended Feasibility Study
Update, Marathon Palladium & Copper Project, Ontario, Canada” dated May 31, 2024.
Jamie Levy, President and CEO of the Company, commented, “The updated Feasibility Study
for the Marathon Copper-Palladium Project clearly underscores its potential to be Ontario’s next
producing critical mineral mine. The project not only benefits from a strong commodity mix of
critical metals but also stands as a strategic Canadian response to growing threats in the global
mineral supply chain.
The Marathon Project’s significant exposure to copper and palladium positions it as a uniquely
attractive opportunity in the critical mineral space in North America. With copper facing long-
term supply constraints and persistent supply risks from the primary palladium producers in
Russia and South Africa, the Marathon Project is well positioned to support North American and
European smelters. The Project’s advanced development and permitting is also a key
differentiator, which positions us to bring metal to market faster than any other North American
copper project not yet in construction.”
Kerry Knoll, Executive Chairman of the Company commented, “Anticipating the final permit
approvals from the provincial government in the near future, the Marathon Project is on track to
become the next major shovel-ready critical metal project in Ontario and Canada. The potential
backing from provincial and national critical metal funds, combined with support from banks,
private equity, institutional investors, and retail shareholders, provides a strong foundation for
securing full financing in the near term.”
Economic Analysis
The updated Feasibility Study underscores the continued economic robustness of the Marathon
Project with an after-tax NPV6% of $1.07 billion, IRR of 28% and 1.9 year payback period based
on the 3-yr trailing average metal prices as of November 1, 2024.
The following table presents the key outputs of the economic analysis for the 2025 FS using 3-
year trailing average metal prices, together with the same analysis performed using spot and
consensus metal prices, and foreign exchange rate assumptions:
Item Units 2025 FS(c) March 25, 2025
Spot(d)
March 2025 long-term
consensus(e)
Key Assumptions
Exchange rate (C$/US$) C$/US$ 1.35 1.44 1.37
Palladium Price US$/oz 1,525 965 1,133
Copper Price US$/lb 4.00 4.43 4.52
Platinum Price US$/oz 950 1,003 1,240
Gold Price US$/oz 2,000 2,983 2,511
Silver Price US$/oz 24.00 33.68 31.19
Revenue Split (a)
Palladium % 52 37 41
Copper % 34 44 41
Platinum % 7 9 10
Gold % 5 9 7
Silver % 1 2 2
Economic Results (b)(f)
Pre-Tax Cash Flow (undiscounted) $M 3,009 2,291 2,576
Pre-Tax NPV6% $M 1,660 1,189 1,375
Pre-Tax IRR % 1.7 2.0 1.8
Pre-Tax Payback years 35.1% 27.6% 30.6%
After-Tax Cash Flow
(undiscounted) $M 2,032 1,554 1,744
After-Tax NPV6% $M 1,070 749 876
After-Tax IRR % 1.9 2.4 2.2
After-Tax Payback years 27.6% 21.4% 23.8%
Notes:
(a) Totals may not add to 100% due to rounding. Splits presented before adjustments for the impact of the Precious
Metals Purchase Agreement (“PMPA”) with Wheaton Precious Metals Corp. (“Wheaton”).
(b) The economic analysis was carried out in real terms (i.e., without inflation factors) in Q4 2024 Canadian dollars,
assuming no project construction financing but inclusive of mining equipment leasing.
(c) Metal price assumptions are based on the adjusted 3-year historical trailing averages as of November 1, 2024 for
each of the metals. The 3-year averages are as follows: Palladium - US$1,523/oz, Copper at U$4.02/lb, Platinum at
US$964/oz, Gold at US$1,995/oz and Silver at US$24.02/oz.
(d) March 25, 2025 spot prices of US$965/oz palladium, US$4.58/lb copper US$981/oz platinum, US$3,020/oz
gold, US$33.68/oz silver and exchange rate of C$1.43 : US$1.00, source: Bloomberg
(e) Long-term consensus pricing provided by Haywood Securities as of March 24, 2025.
(f) See Non-IFRS Financial Measures, below, for additional information on Pre -Tax and After-Tax Cash Flows.
Sensitivities
The Project has significant leverage to palladium and copper prices. The after-tax valuation
sensitivities for the key metrics are shown below.
After-Tax NPV6%
Results
Palladium Price Sensitivity (US$/oz)
800 1,000 1,250 1,500 1,525 1,750 2,000 2,200
Copper
Price
Sensitivity
(US$/lb)
2.50 (291) (9) 308 612 643 916 1,214 1,466
3.00 (120) 145 452 758 788 1,057 1,368 1,606
3.50 41 296 598 899 929 1,211 1,509 1,746
4.00 194 438 741 1,040 1,070 1,352 1,649 1,886
4.50 337 582 883 1,195 1,225 1,492 1,788 2,023
5.00 484 723 1,023 1,335 1,365 1,632 1,927 2,165
5.50 625 866 1,178 1,475 1,505 1,771 2,067 2,306
After-Tax IRR
Results
Palladium Price Sensitivity (US$/oz)
800 1,000 1,250 1,500 1,525 1,750 2,000 2,200
Copper
Price
Sensitivity
(US$/lb)
2.50 - 5.7% 13.5% 19.9% 20.5% 25.5% 30.7% 34.5%
3.00 2.8% 9.6% 16.4% 22.4% 23.0% 27.8% 32.7% 36.4%
3.50 7.0% 12.9% 19.2% 24.8% 25.4% 30.0% 34.7% 38.3%
4.00 10.5% 15.8% 21.7% 27.1% 27.6% 32.1% 36.6% 40.1%
4.50 13.6% 18.5% 24.1% 29.3% 29.8% 34.1% 38.5% 41.9%
5.00 16.4% 21.0% 26.4% 31.4% 31.9% 36.0% 40.3% 43.6%
5.50 19.0% 23.5% 28.6% 33.4% 33.8% 37.8% 42.1% 45.3%
After-Tax Payback Palladium Price Sensitivity (US$/oz)
800 1,000 1,250 1,500 1,525 1,750 2,000 2,200
Copper
Price
Sensitivity
(US$/lb)
2.50 - 7.8 4.3 2.5 2.5 2.0 1.8 1.5
3.00 10.4 5.6 3.3 2.3 2.2 1.9 1.5 1.4
3.50 6.8 4.9 2.9 2.1 2.1 1.8 1.5 1.4
4.00 5.6 4.2 2.4 2.0 1.9 1.6 1.4 1.3
4.50 5.0 3.0 2.1 1.9 1.8 1.5 1.4 1.3
5.00 4.2 2.4 2.0 1.6 1.6 1.4 1.3 1.2
5.50 3.0 2.2 1.9 1.5 1.5 1.4 1.3 1.2
After-Tax Results OPEX Sensitivity
+30% +15% 0% -15% -30%
NPV6% ($M) 669 871 1,070 1,282 1,479
Payback (yrs) 2.3 2.1 1.9 1.8 1.6
IRR (%) 21.2% 24.6% 27.6% 30.5% 33.1%
After-Tax Results CAPEX Sensitivity
+30% +15% 0% -15% -30%
NPV6% ($M) 860 966 1,070 1,173 1,277
Payback (yrs) 3.0 2.3 1.9 1.5 1.2
IRR (%) 19.6% 23.1% 27.6% 33.8% 42.7%
After-Tax Results FX Sensitivity
1.25 1.30 1.35 1.40 1.45
NPV6% ($M) 840 955 1,070 1,199 1,313
Payback (yrs) 2.2 2.0 1.9 1.9 1.6
IRR (%) 23.7% 25.7% 27.6% 29.5% 31.3%
Capital Costs
The initial capital costs for construction and ramp-up, together with expected sustaining capital
and closure costs, are presented in the table below:
Capital Area 2025 FS
($M)
Mobile Equipment for Construction (a) 74
Processing Plant 280
Infrastructure 88
TSF, Water Management and Earthworks 97
EPCM, General and Owners Cost 198
Preproduction, Startup, Commissioning 169
Contingency 87
Initial Capital 992
Preproduction revenue(b) (184)
Total 809
Sustaining Capital 565
Closure and Reclamation Costs 72
Notes:
(a) Mobile equipment acquired for Construction is presented as the cost of equipment deposits and lease payments
during the construction and pre-production period. The remainder of the equipment leasing costs are incurred during
operations and included in sustaining capital.
(b) Revenue net of Related Off-Site Costs (Transport, Smelter, and Royalties) and working capital adjustments. See
Economic Analysis, above, for additional information on the metal price assumptions used in the 2025 FS.
Operating Costs
The Project operating costs have been updated and are reflected in the table below.
Description Units Operating Cost
Mining(a) $/t processed 12.93
Processing $/t processed 8.57
General & Administration $/t processed 2.62
Concentrate Transport Costs $/t processed 1.96
Treatment & Refining Charges $/t processed 2.38
Royalties $/t processed 0.10
Total Operating Costs $/t processed 28.56
Average Operating Cost US$/oz PdEq(c) 663
Average All-in Sustaining Cost (b) US$/oz PdEq(c) 781
Average Operating Cost US$/lb CuEq(c) 1.74
Average All-in Sustaining Cost (b) US$/lb CuEq(c) 2.05
Notes:
(a) Mining cost per tonne mined is C$3.49/t .
(b) All-in sustaining cost excludes the impact of the Wheaton PMPA.
(c) See Non-IFRS Financial Measures, below, for additional information on Operating Costs, AISC, PdEq and CuEq.
Mine Plan
The life of mine plan has been updated and the production details are summarized in the table
below.
Units 2025 TR
LOM Throughput
Peak Process Plant Throughput tpd 27,700
Mt/year 10.1
Peak Mining Rate tpd 164,000
Mt/year 60
Mine Production (LOM)
Total Mined Mt 489.7
Total Waste Mined Mt 361.4
Total Ore Mined Mt 128.3
Strip Ratio waste:ore 2.8
Payable Metal (LOM)
Palladium koz 2,161
Copper Mlbs 532
Platinum koz 488
Gold koz 160
Silver koz 3,051
Mineral Resources
The Mineral Resource Estimate below is for the combined Marathon, Geordie and Sally
Deposits. The Mineral Resource Estimates for Marathon, Geordie and Sally were prepared by
P&E.
Pit Constrained Combined Mineral Resource Estimate for the Marathon, Geordie and
Sally Deposits (Effective date November 1, 2024)
Mineral
Resource
Classification
Tonnes Pd Cu Pt Au Ag
Mt g/t koz % Mlbs g/t koz g/t koz g/t koz
Marathon Deposit
Measured 164.0 0.56 2,973 0.20 712 0.18 970 0.07 358 1.7 9,089
Indicated 38.1 0.39 476 0.18 153 0.13 159 0.06 71 1.6 1,896
Meas. + Ind. 202.0 0.53 3,449 0.19 865 0.17 1,129 0.07 429 1.7 10,985
Inferred 2.9 0.36 34 0.16 10 0.13 12 0.06 6 1.2 112
Geordie Deposit
Indicated 17.3 0.56 312 0.35 133 0.04 20 0.05 25 2.4 1,351
Inferred 12.9 0.51 212 0.28 80 0.03 12 0.03 14 2.4 982
Sally Deposit
Indicated 24.8 0.35 278 0.17 93 0.2 160 0.07 56 0.7 567
Inferred 14.0 0.28 124 0.19 57 0.15 70 0.05 24 0.6 280
Total Project
Measured 164.0 0.56 2,973 0.20 712 0.18 970 0.07 358 1.7 9,089
Indicated 80.1 0.41 1,066 0.21 379 0.13 339 0.06 152 1.5 3,814
Meas. + Ind. 244.1 0.51 4,039 0.20 1,091 0.17 1,309 0.06 510 1.6 12,903
Inferred 29.8 0.39 370 0.22 147 0.10 94 0.05 44 1.4 1,374
Notes:
a. Mineral Resources were estimated using the Canadian Institute of Mining, Metallurgy and Petroleum (CIM),
CIM Standards on Mineral Resources and Reserves, Definitions (2014) and Best Practices Guidelines (2019)
prepared by the CIM Standing Committee on Rese rve Definitions and adopted by CIM Council.
b. Mineral Resources that are not Mineral Reserves do not have demonstrated economic viability. The estimate of
Mineral Resources may be materially affected by environmental, permitting, legal, marketing, or other relevant
issues. Mineral Resources are reported inclusive of Mineral Reserves.
c. The Inferred Mineral Resource in this estimate has a lower level of confidence than that applied to an Indicated
Mineral Resource and must not be converted to a Mineral Reserve. It is reasonably expected that the majority of the
Inferred Mineral Resource could be upgraded to an Indicated Mineral Resource with continued exploration.
d. The Marathon Mineral Resource is reported within a constrained pit shell at a NSR cut -off value of $13.6/t.
e. Marathon NSR ($/t) = (Cu % x 111.49) + (Ag g/t x 0.73) + (Au g/t x 80.18) + (Pd g/t x 56.02) +(Pt g/t x 36.49) –
2.66
f. The Marathon Mineral Resource Estimate was based on metal prices of US$1,550/oz Pd, US$4.250/lb Cu,
US$1,100/oz Pt, US$2,300/oz Au and US$27/oz Ag, and a C$:US$ exchange rate of C$1.35 to US$1.00.
g. The Sally and Geordie mineral resources are reported within a constraining pit shell at a NSR cut -off value of
$13/t.
h. Sally and Geordie NSR ($/t) = (Ag g/t x 0.48) + (Au g/t x 42.14) + (Cu % x 73.27) + (Pd g/t x 50.50) + (Pt g/t x
25.07) – 2.62
i. The Sally and Geordie Mineral Resource Estimate was based on metal prices of US$1,600/oz Pd, US$3.00/lb Cu,
US$900/oz Pt, US$1,500/oz Au and US$18/oz Ag, and a C$:US$ exchange rate of 1.30 C$ to 1.00 US$.
j. Contained metal totals may differ due to rounding.
Mineral Reserves
The Mineral Reserve estimate for the Project includes only the Marathon Deposit. The Mineral
Reserve Estimate was prepared by MMTS.
Marathon Project Open Pit Mineral Reserve Estimates
(Effective Date of November 1, 2024)
Tonnes Pd Cu Pt Au Ag
Mineral
Reserves Mt g/t koz % M lb g/t koz g/t koz g/t koz
Proven 115.5 0.66 2,434 0.22 549 0.20 754 0.07 264 1.7 6,242
Probable 12.7 0.47 193 0.20 56 0.15 61 0.06 26 1.6 635
P & P 128.3 0.64 2,627 0.21 605 0.20 815 0.07 291 1.8 6,877
Notes:
a. The mineral reserves estimate were prepared by Marc Schulte, P.Eng., who is also an independent Qualified
Person, reported using the 2014 CIM Definition Standards, and have an effective date of November 1, 2024.
b. Mineral reserves are a subset of the Measured and Indicated Mineral Resources Estimate that has an effective
date of November 1, 2024. Inferred class Mineral Resources are treated as waste.
c. Mineral Reserves are based on the 2024 Marathon Project Feasibility Study Update mine plan.
d. Mineral Reserves are mined tonnes and grade; the reference point is the process plant feed at the primary
crusher. Process Plant feed tonnes and grade include consideration of mining operational dilution and recovery.
e. Mineral Reserves are reported at a cutoff grade of $16/t NSR. The NSR cut-off assumes Pd Price of US$1,525/oz,
Cu price of US$4.00/lb, Pt Price of US$950/oz, Au price of US$2,000/oz, Ag price of US$24/oz, at an exchange rate
of 0.74 US dollar per 1.00 Canadian dollar; payable percentages of 95% for Pd, 96.5% for Cu, 93% for Pt, 93.5%
for Au, 93.5% for Ag; refining charges of US$24.5/oz for Pd, US$0.079/lb for Cu, US$24.5/oz for Pt, US$0.50/oz
for Ag; minimum deductions of 2.875 g/t for Pd, 1.1% for Cu, 2 .875 g/t for Pt, 1.0 g/t for Au, 30.0 g/t for Ag;
treatment charges of US$79/t and transport and off- site costs of US$125/t concentrates, concentrate ratio of 90.9%;
metallurgical recoveries are based on variable grade dependent metallurgical recovery curv es.
f. The NSR cut off-value covers process costs of $8.27/t, general and administrative (G&A) costs of $2.63/t,
sustaining and closure costs of $3.13/t, ore mining differential costs of $0.57/t, and stockpile rehandle costs of
$1.40/t.
g. Numbers have been rounded, which may result in summation differences. Canadian Institute of Mining,
Metallurgy and Petroleum (CIM) Definition Standards for Mineral Resources and Mineral Reserves (CIM (2014)
definitions) were used for Mineral Reserve classification.
Qualified Persons
The news release has been reviewed and approved by Daniel Janusauskas, P.Eng., Technical
Services Manager of Generation PGM Inc., a wholly-owned subsidiary of the Company, and a
Qualified Person as defined by Canadian Securities Administrators National Instrument 43-101
Standards of Disclosure for Mineral Projects.
The 2025 FS was prepared through the collaboration of the following consulting firms and
Qualified Persons, each of whom has reviewed and approved the technical information in this
news release which was within their primary area of responsibility:
Consultant Company Primary Area of Responsibility Qualified Persons
Ausenco Engineering
Canada ULC
Overall integration, capital cost estimation
compilation, process plant capital and operating
costs, economic analysis, recovery methods,
mineral processing and metallurgical testwork
Tommaso Roberto Raponi, P.
Eng.
JDS Energy and Mining,
Inc.
Infrastructure, and earthworks capital cost
estimates, and project execution plan
Jean-Francois Maille, P.Eng.
Knight Piésold Ltd.
Tailings Storage Facility, water balance,
geotechnical studies (mine rock storage piles, open
pit and local infrastructure and foundations)
Craig N. Hall, P.Eng.
Moose Mountain Technical
Services
Mineral Reserves, mining methods, mining
operating and capital cost estimate
Marc Schulte, P. Eng.